Province | Subbasin | % |
---|---|---|
Columbia Plateau | Tucannon | 100.00% |
* Expenditures data includes accruals and are based on data through 31-Oct-2024.
Full Name | Organization | Write Permission | Contact Role | Work Phone | |
---|---|---|---|---|---|
Julie Burke | Umatilla Confederated Tribes (CTUIR) | Yes | Administrative Contact | julieburke@ctuir.org | (541) 429-7292 |
Daniel Gambetta | Bonneville Power Administration | Yes | Env. Compliance Lead | dagambetta@bpa.gov | (503) 230-3493 |
Brenda Heister | Bonneville Power Administration | Yes | Contracting Officer | bsheister@bpa.gov | (503) 230-3531 |
Eric Hoverson | Umatilla Confederated Tribes (CTUIR) | Yes | Contract Manager | erichoverson@ctuir.org | (541) 429-7555 |
Gary James | Umatilla Confederated Tribes (CTUIR) | Yes | Supervisor | garyjames@ctuir.org | (541) 429-7285 |
Andre L'Heureux | Bonneville Power Administration | Yes | COR | allheureux@bpa.gov | (503) 230-4482 |
Peter Lofy | Bonneville Power Administration | Yes | F&W Approver | ptlofy@bpa.gov | (503) 230-4193 |
Jim Webster | Umatilla Confederated Tribes (CTUIR) | Yes | Supervisor | jameswebster@ctuir.org | (541) 429-7240 |
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Project managed efficiently | B: 119. Manage Tucannon Watershed Habitat Improvement Projects | 12/31/2012 | 12/27/2012 | |
All environmental compliance clearances obtained | C: 165. Obtain environmental clearance when necessary for applicable enhancement projects | 12/31/2012 | 11/16/2012 | |
Establish beneficial relationships and agreements with other entities | D: 191. Coordination of habitat restoration with other entities | 12/31/2012 | 12/04/2012 | |
Prioritized Project List for next year uploaded to Pisces | E: 114. Identify, prioritize and select projects for habitat improvement | 03/31/2012 | 03/30/2012 | |
Survey data results | F: 115. Survey habitat conditions for the Tucannon River | 12/31/2012 | 08/30/2012 | |
LWD & boulders placed in Tucannon stream channel | G: 29. Install woody debris/ boulders at Tucannon RM 42 reach | 11/30/2012 | 08/31/2012 | |
Spring Creek plantings completed | H: 47. Plant native vegetation at Russel Springs Creek | 12/31/2012 | 12/19/2012 | |
Hartsock Springs plantings completed | I: 47. Plant native vegetation at Hartsock Springs | 12/31/2012 | 12/19/2012 | |
Tucannon River RM 42 plantings completed | J: 47. Plant native vegetation at RM 42, Tucannon River | 06/30/2012 | 06/30/2012 | |
Pataha Creek plantings completed | K: 47. Plant native vegetation at Pataha Creek Passage rectification sites | 12/31/2012 | 12/19/2012 | |
Attach final progress report in Pisces | L: 132. Submit Progress Report for the period Jan 2011 to December 2011 | 12/20/2012 | ||
Attach final progress report in Pisces | M: 132. Submit Progress Report for the period Jul 2009 to December 2010 | 12/15/2012 |
Primary Focal Species | Work Statement Elements |
---|---|
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened) |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 185 | Periodic Status Reports for BPA | 01/01/2012 | ||||||
B | 119 | Manage Tucannon Watershed Habitat Improvement Projects | 01/01/2012 | ||||||
C | 165 | Obtain environmental clearance when necessary for applicable enhancement projects | 01/01/2012 | ||||||
D | 191 | Coordination of habitat restoration with other entities | 01/01/2012 | ||||||
E | 114 | Identify, prioritize and select projects for habitat improvement | 01/01/2012 | ||||||
F | 115 | Survey habitat conditions for the Tucannon River | 01/01/2012 | ||||||
G | 29 | Install woody debris/ boulders at Tucannon RM 42 reach | 01/01/2012 | ||||||
H | 47 | Plant native vegetation at Russel Springs Creek | 01/01/2012 | ||||||
I | 47 | Plant native vegetation at Hartsock Springs | 01/01/2012 | ||||||
J | 47 | Plant native vegetation at RM 42, Tucannon River | 01/01/2012 | ||||||
K | 47 | Plant native vegetation at Pataha Creek Passage rectification sites | 01/01/2012 | ||||||
L | 132 | Submit Progress Report for the period Jan 2011 to December 2011 | 01/01/2012 | ||||||
M | 132 | Submit Progress Report for the period Jul 2009 to December 2010 | 01/01/2012 |