Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 56662 REL 105: 2008-455-00 EXP STURGEON MANAGEMENT
Project Number:
Title:
Sturgeon Management
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Cascade Columbia Upper Middle 100.00%
Contract Number:
56662 REL 105
Contract Title:
2008-455-00 EXP STURGEON MANAGEMENT
Contract Continuation:
Previous: Next:
56662 REL 81: 2008-455-00 EXP YN STURGEON MANAGEMENT
Contract Status:
Closed
Contract Description:
The goal of the White Sturgeon Management project, at some point in the future, is to release juvenile sturgeon to restore existing stocks and to re-introduce sturgeon to areas where natural production is limited in the Mid-Columbia River.  The fish will be reared on the Yakama Reservation at the Marion Drain Hatchery.  The project will operate by cost sharing between BPA and the Yakama Nation.  

The first phase of the project will include the development and refinement of sturgeon culture techniques using captive brood in preparation for wild stock.  The Yakama Nation is holding nearly 100 broodstock from various projects throughout the Columbia River Basin.  The YN project does not propose building new hatchery facilities or releasing hatchery-reared sturgeon during Phase I.  Phase I identifies hatchery evaluation and development work to be completed concurrent with the CRITFC comprehensive strategic and hatchery master planning which will clarify appropriate applications and objectives for hatchery sturgeon in the lower mid-Columbia River (downstream from Priest Rapids).   YN Phase I involves 1-2 year contracts with the Bonneville Power Administration and does not include the development of significant new facilities.  YN Phase II might include significant new facilities contingent on the outcome of the strategic and master planning process.  Work will be completed by Yakama Tribal fishery program staff in coordination with fishery co-managers from other treaty tribes and the states.  Hatchery activities will occur at established Tribal Facilities at Marion Drain
Account Type(s):
Expense
Contract Start Date:
04/01/2016
Contract End Date:
03/31/2017
Current Contract Value:
$139,979
Expenditures:
$139,979

* Expenditures data includes accruals and are based on data through 31-Oct-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Release
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Debbie Azure Yakama Confederated Tribes Yes Administrative Contact azud@yakamafish-nsn.gov (509) 865-5121x6334
Rachel Castilleja Yakama Confederated Tribes No Administrative Contact casr@yakamafish-nsn.gov (509) 865-5121x6337
Edward Gresh Bonneville Power Administration Yes Env. Compliance Lead esgresh@bpa.gov (503) 230-5756
Peter Lofy Bonneville Power Administration Yes F&W Approver ptlofy@bpa.gov (503) 230-4193
Amy Mai Bonneville Power Administration Yes COR aemai@bpa.gov (503) 230-7349
Donella Miller Yakama Confederated Tribes Yes Contract Manager mild@yakamafish-nsn.gov (509) 945-0132
Khanida Mote Bonneville Power Administration Yes Contracting Officer kpmote@bpa.gov (503) 230-4599
Christopher Roper Bonneville Power Administration No CO Assistant cproper@bpa.gov (503) 230-3514
Bob Rose Yakama Confederated Tribes No Supervisor rosb@yakamafish-nsn.gov (509) 388-3871
Tybee Sheidler Bonneville Power Administration No CO Assistant tasheidler@bpa.gov (503) 230-3820
Elham Zolmajd-Haghighi Bonneville Power Administration No CO Assistant ezolmajd-haghighi@bpa.gov (503) 230-7414


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Environmental clearances for the project A: 165. Obtain environmental clearances for project 03/31/2017 03/31/2017
All administrative tasks fulfilled with timely quality products B: 119. Manage and Administer project 03/31/2017 03/31/2017
Rear Captive Brood C: 60. Rear Hatchery Fish 03/31/2017 03/31/2017
Rear Juvenile Sturgeon D: 60. Rear Hatchery Juveniles 03/31/2017 03/31/2017
Rear Sturgeon Larvae E: 66. Rear Sturgeon Larvae 03/31/2017 03/31/2017
Workshop Participation F: 189. Workshop Participation 03/31/2017 03/31/2017
Review Documents and Comment G: 122. Review and Comment on Strategic Plan and Master Plan/Conceptual Design 03/31/2017 03/31/2017
Completed Annual Report I: 132. Prepare and submit Progress Report for April 1 2015 to March 31 2016 01/06/2017 02/27/2017

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Sturgeon, White (A. transmontanus) - Lower Columbia River
  • 1 instance of WE 66 Trap/Collect/Hold/Transport Fish - Hatchery
  • 2 instances of WE 60 Maintain Fish Health
  • 1 instance of WE 122 Provide Technical Review and Recommendation

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Obtain environmental clearances for project 04/01/2016
B 119 Manage and Administer project 04/01/2016
C 60 Rear Hatchery Fish 04/01/2016
D 60 Rear Hatchery Juveniles 04/01/2016
E 66 Rear Sturgeon Larvae 04/01/2016
F 189 Workshop Participation 04/01/2016
G 122 Review and Comment on Strategic Plan and Master Plan/Conceptual Design 04/01/2016
H 185 Periodic Status Reports for BPA 04/01/2016
I 132 Prepare and submit Progress Report for April 1 2015 to March 31 2016 04/01/2016