Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 56662 REL 212: 1996-035-01 EXP YAKAMA RESERVATION WATERSHED PROJECT
Project Number:
Title:
Yakama Reservation Watershed Project
Stage:
Implementation
Area:
Province Subbasin %
Columbia Plateau Yakima 100.00%
Contract Number:
56662 REL 212
Contract Title:
1996-035-01 EXP YAKAMA RESERVATION WATERSHED PROJECT
Contract Continuation:
Previous: Next:
56662 REL 178: 1996-035-01 EXP YAKAMA RESERVATION WATERSHED PROJECT
  • 56662 REL 234: 1996-035-01 EXP YAKAMA RESERVATION WATERSHED PROJECT
Contract Status:
Issued
Contract Description:
The objective of this project is to monitor status and trends of the steelhead population in the Toppenish Creek watershed.  We intend to use a redd count census conducted on all known spawning habitats in the basin to obtain an index of steelhead spawner abundance.  Redd counts will also be used to track changes in steelhead spatial distribution and effectiveness monitoring for stream restoration projects (e.g. decommissioning and designs on NF Toppenish, BDA structures in wetland meadow comlexes, NF Logy Creek, Panther Creek etc.).

We will evaluate the steelhead abundance estimate by using radio tracking data collected under the Yakima VSP project during years 2011-2014 and PIT tag antennae 2011-present.  

We will operate rotary screw traps continuously capturing the entire outmigration season to obtain an estimate of steelhead juvenile outmigrant abundance using a stratified mark-recapture model.  Survival using PIT tags and population demographics (length, weight, age, condition factor) will be evaluated.
Account Type(s):
Expense
Contract Start Date:
04/01/2020
Contract End Date:
03/31/2021
Current Contract Value:
$1,127,646
Expenditures:
$0

* Expenditures data includes accruals and are based on data through 30-Nov-2024.

BPA CO:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Release
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Debbie Azure Yakama Confederated Tribes Yes Administrative Contact azud@yakamafish-nsn.gov (509) 865-5121x6334
Catherine Clark Bonneville Power Administration Yes Env. Compliance Lead cmclark@bpa.gov (503) 230-4240
Tom Elliott Yakama Confederated Tribes Yes Technical Contact ellt@yakamafish-nsn.gov (509) 865-5121x6308
Desmond Gelman Bonneville Power Administration No CO Assistant dxgelman@bpa.gov (503) 230-4960
Loverne George Yakama Confederated Tribes Yes Administrative Contact geol@yakamafish-nsn.gov (509) 865-5121x6364
Timothy Hanrahan Bonneville Power Administration Yes Backup COR TPHanrahan@bpa.gov (503) 230-3938
Tana Hoptowit Yakama Confederated Tribes Yes Administrative Contact hopt@yakamafish-nsn.gov (509) 865-5121x6318
Peter Lofy Bonneville Power Administration Yes F&W Approver ptlofy@bpa.gov (503) 230-4193
Jackie Olney Yakama Confederated Tribes No Administrative Contact olnj@yakamafish-nsn.gov (509) 865-5121x6311
Michelle O'Malley Bonneville Power Administration Yes COR mmomalley@bpa.gov (503) 230-5138
Dallas Reed Yakama Confederated Tribes Yes Technical Contact reed@yakamafish-nsn.gov (509) 790-8596
Tim Resseguie Yakama Confederated Tribes Yes Contract Manager rest@yakamafish-nsn.gov (509) 945-7409
Brandon Rogers Yakama Confederated Tribes Yes Interested Party rogb@yakamafish-nsn.gov (509) 949-4109
Paul Ward Yakama Confederated Tribes No Supervisor warp@yakamafish-nsn.gov (509) 949-4129
Shawna Warehime Yakama Confederated Tribes Yes Technical Contact wars@yakamafish-nsn.gov (509) 945-1259
Karen Wolfe Bonneville Power Administration Yes Contracting Officer ktwolfe@bpa.gov (503) 230-3448


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
SOW and LIB submitted B: 119. Manage Restoration Projects 02/28/2021 03/30/2021
List of Selected Projects (and contingency projects) to be implemented C: 114. Select habitat improvement actions and identify possible projects for next fiscal year 02/28/2021 12/01/2020
Project databases that are maintained and up to date. D: 160. Update Project Database 02/28/2021 03/30/2021
Disseminated data E: 161. Create informal summary reports and maps 02/28/2021 03/30/2021
5 outreach sessions completed F: 99. Conduct field and classroom education at local schools 02/28/2021 03/30/2021
Technical review and input provided to various policy and planning efforts G: 122. Input to various Tribal planning and policy efforts 02/28/2021 03/30/2021
Completed environmental documentation H: 165. Environmental Compliance 02/28/2021 03/30/2021
Completed Annual Report submitted to BPA I: 132. Produce Project Annual Report for FY19 Mar2019-Feb2020 02/28/2021 03/30/2021
Outmigration estimate and other data from screw traps J: 157. Operate rotary screw traps for steelhead 02/28/2021 03/30/2021
Complete three pass surveys in Satus and Ahtanum Creeks K: 157. Conduct steelhead and bull trout spawner surveys 02/28/2021
Redd distribution and adult abundance index L: 162. Analyze redd count data 02/28/2021 03/30/2021
Steelhead Outmigrant metrics M: 162. Analyze Steelhead Outmigrant Data 02/28/2021 03/30/2021
Water temperature record N: 157. Collect water temperature data 03/31/2021
Weekly manual discharge measurements O: 157. Collect discharge measurements 02/28/2021 03/30/2021
Wapato Irrigation Project diversions managed for minimum instream flow. P: 186. Assist with the operation of diversions and screens on Ahtanum Creek 02/28/2021 03/30/2021
Water diversion managed at 6 diversions to provide minimum streamflow Q: 186. Assist with operation of diversions and screens on Toppenish Creek 02/28/2021 03/30/2021
Functioning fences, wells, stock tanks, and habitat improvements R: 186. Maintain livestock wells/stock tanks/livestock fences/improved springs 02/28/2021 03/30/2021
Maintain vegetation S: 198. Maintain pre-existing vegetation 02/28/2021 03/30/2021
Pom Pom Road Decommission and Habitat Action Designs T: 175. Pom Pom Road Decommission Designs 03/31/2021
BDA structure designs U: 181. Wetland Meadow BDA Implementation 03/31/2021
Designs for Simcoe Creek Project V: 175. Simcoe Creek Designs 03/31/2021

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
  • 1 instance of WE 198 Maintain Vegetation
  • 3 instances of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 181 Create, Restore, and/or Enhance Wetland
  • 1 instance of WE 114 Identify and Select Projects
  • 2 instances of WE 175 Produce Design
  • 4 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 161 Disseminate Raw/Summary Data and Results
  • 2 instances of WE 162 Analyze/Interpret Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA
B 119 Manage Restoration Projects
C 114 Select habitat improvement actions and identify possible projects for next fiscal year
D 160 Update Project Database
E 161 Create informal summary reports and maps
F 99 Conduct field and classroom education at local schools
G 122 Input to various Tribal planning and policy efforts
H 165 Environmental Compliance
I 132 Produce Project Annual Report for FY19 Mar2019-Feb2020
J 157 Operate rotary screw traps for steelhead 04/07/2020
K 157 Conduct steelhead and bull trout spawner surveys 04/07/2020
L 162 Analyze redd count data
M 162 Analyze Steelhead Outmigrant Data
N 157 Collect water temperature data 04/07/2020
O 157 Collect discharge measurements 04/07/2020
P 186 Assist with the operation of diversions and screens on Ahtanum Creek 04/07/2020
Q 186 Assist with operation of diversions and screens on Toppenish Creek 04/07/2020
R 186 Maintain livestock wells/stock tanks/livestock fences/improved springs 04/07/2020
S 198 Maintain pre-existing vegetation 04/07/2020
T 175 Pom Pom Road Decommission Designs
U 181 Wetland Meadow BDA Implementation
V 175 Simcoe Creek Designs