Obtain environmental compliance |
B: 165. Produce Environmental Compliance Documentation for all applicable work on Coho Reintroduction |
|
01/31/2016 |
01/31/2016 |
Continue to develop operation plans and protocols |
C: 174. Hatchery Operations and Facility Plans |
|
01/31/2016 |
01/31/2016 |
Conduct and document maintenance and repair activities |
D: 61. Subcontract O&M for maintenance of facilities |
|
01/31/2016 |
01/31/2016 |
Manage and administer project, February 1, 2015 through January 31, 2016 |
E: 119. Manage and Administer 2015-2016 Project for Mid Columbia Coho Restoration |
|
01/31/2016 |
01/31/2016 |
Acclimated smolts released |
F: 176. Acclimation/Release: Wenatchee: Coulter Creek pond (BY 2013) |
|
06/01/2015 |
06/01/2015 |
Acclimated smolts released |
G: 176. Acclimation/Release: Wenatchee: Beaver Creek pond (BY 2013) |
|
06/10/2015 |
06/10/2015 |
Acclimated smolts released |
H: 176. Acclimation/Release: Wenatchee: Rohlfing's pond (BY 2013) |
|
06/01/2015 |
06/01/2015 |
Acclimated smolts released form Butcher Creek pond |
I: 176. Acclimation/Release: Wenatchee: Butcher Creek Pond (BY 2013) |
|
06/10/2015 |
06/10/2015 |
Acclimated smolts released |
J: 176. Acclimation/Release: Wenatchee: Leavenworth NFH (BY 2013) |
|
04/30/2015 |
04/30/2015 |
Acclimated smolts released |
K: 176. Acclimation/Release: Gold Creek Ponds (BY 2013) |
|
06/01/2015 |
06/01/2015 |
Acclimated smolts released |
L: 176. Acclimation/Release: Wolf Creek Pond (BY 2013) |
|
06/01/2015 |
06/01/2015 |
Acclimated smolts released |
M: 176. Acclimation/Release: Winthrop NFH back channel rearing (BY 2013) |
|
06/01/2015 |
06/01/2015 |
Acclimated smolts released |
N: 176. Acclimation/Release: Methow: Twisp Ponds (BY 2013) |
|
06/01/2015 |
06/01/2015 |
CWT or PBT mark fish BY2014 |
O: 158. Mark/Tag Animals - Subcontract CWT or PBT of approximately 1,500,000 BY14 coho pre-smolts |
|
09/01/2015 |
09/01/2015 |
Collection of 2015 Coho Broodstock: Wenatchee and Methow programs |
P: 66. Trap 2015 broodstock at Dryden, Tumwater, Wells, Methow FH, Winthrop NFH, and LNFH |
|
12/03/2015 |
12/03/2015 |
Spawn 2015 brood coho at Leavenworth NFH |
Q: 176. Spawn 2015 brood coho at Leavenworth NFH |
|
12/15/2015 |
12/15/2015 |
Spawn 2015 coho broodstock at Winthrop NFH |
R: 176. Spawn 2015 brood coho at Winthrop NFH |
|
12/15/2015 |
12/15/2015 |
Carcass distribution for BY2015 broodstock |
S: 44. Carcass dispersal of a portion of 2015 broodstock in the Wenatchee and Methow River programs |
|
01/31/2016 |
01/31/2016 |
Transport 2015 BY eyed coho eggs to rearing facilities |
T: 66. Transport 2015 brood eyed-eggs from incubation facilities to rearing facilities |
|
01/20/2016 |
01/20/2016 |
Coho redd counts and spawning composition for the 2015 return year |
U: 157. Conduct spawning ground surveys for the 2015 return year in the Wenatchee Basin |
|
01/15/2016 |
01/15/2016 |
2015 return year coho redd counts and spawning composition |
V: 157. Conduct spawning ground surveys for the 2015 return year in the Methow Basin |
|
01/25/2016 |
01/25/2016 |
Completed database |
W: 157. Collect biological data from 2015 coho brood at spawning |
|
12/01/2015 |
12/01/2015 |
CWT recovery data from the 2015 BY |
X: 157. Extract CWT from 2015 brood coho snouts collected at spawning and on spawning ground surveys |
|
01/31/2016 |
01/31/2016 |
PIT tag fish 2014 BY |
Y: 158. Mark/Tag Animals - PIT-tag 66,000 BY14 coho pre-smolts |
|
01/30/2016 |
01/30/2016 |
Analyze data from 2015 BY |
Z: 162. Analyze and interpret M&E data from 2015 brood |
|
01/31/2016 |
01/31/2016 |
Enter data |
AA: 160. Enter data into and maintain local databases |
|
01/30/2016 |
01/30/2016 |
Collect data during 2015 emergence |
AB: 157. Collect/Generate Field and Lab Data to determine 2015 emergence timing, growth and distribution |
|
01/31/2016 |
01/31/2016 |
Progress Report has been published |
AC: 132. Submit Annual Report for the FY13 period (2/1/13 to 1/31/14) |
|
11/15/2015 |
11/15/2015 |
Progress Report has been published |
AD: 132. Submit Annual Report for the FY14 period (2/1/14 to 1/31/15) |
|
11/30/2015 |
11/30/2015 |
Tissue analysis by CRITFC for genetic monitoring |
AE: 157. Analyze genetic tissue samples for PBT analysis of parental groups |
|
01/31/2016 |
01/31/2016 |
Progress Report has been published |
AF: 132. Begin preparation for annual reporting of the CY15 period (1/1/15 through 12/31/15) |
|
01/31/2016 |
|