Contract 57306: 2007-402-00 CAP IDFG SOCKEYE HATCHERY CONSTRUCTION
Project Number:
Title:
Snake River Sockeye Captive Propagation
Stage:
Implementation
Area:
Province Subbasin %
Mountain Snake Salmon 100.00%
Contract Number:
57306
Contract Title:
2007-402-00 CAP IDFG SOCKEYE HATCHERY CONSTRUCTION
Contract Continuation:
Previous: Next:
n/a
Contract Status:
Closed
Contract Description:
Currently, insufficient incubation and juvenile rearing space is available to meet the project’s long-term goal.  Juvenile sockeye salmon are reared at the IDFG Sawtooth Fish Hatchery (a Lower Snake River Compensation Plan facility) and at the Oregon Department of Fish and Wildlife’s Oxbow Fish Hatchery (a Mitchell Act facility). As both facilities are focused on higher priority mitigation mandates, limited rearing space is available for sockeye salmon.  As such, the Department is currently pursuing the acquisition of suitable hatchery space to meet this objective.  Consistent with the FCRPS Biological Opinion and the Idaho Fish Accord, the new Idaho facility would have the capacity to produce between 500,000 and 1 million full-term smolts annually for release to locations in the Sawtooth Valley. Focusing on a smolt release strategy maximizes the potential to return anadromous adults.

The interim abundance guidelines established by NOAA suggest that 1,000 naturally-produced adults are needed to return to Redfish Lake and 500 adults to Pettit and Alturas lakes over a two-generation period to initiate any policy discussions related to ESA-listing status. Little information is available to guide the development of minimum effective population size targets for this ESU. However, it is probably safe to assume, that the “50/500” rule described by Franklin (1980), Soulé (1980), and Nelson and Soulé (1987) should be considered, at a minimum, rough guidance for the development of adult return criteria. Under their rule, an effective population size of 50 or less is not considered genetically viable in the long-term and is vulnerable to the effects of inbreeding depression while an effective population size of 500 or greater would allow the population to retain adaptive genetic variation over time (evolutionary potential).

The Department anticipates that releasing up to 1 million smolts could consistently return approximately 5,000 anadromous adults annually. Increased eggs for the expanded smolt program will be produced at the Department’s newly expanded Eagle Fish Hatchery broodstock station and possibly from increased production from NOAA facilities in Washington State.

This contract will provide for funding and work flow needs directly addressing the construction of the Springfield Hatchery. Work flow and funding of Planning and Design contractual responsibilities are addressed in Planning and Design Contract # 47285.
Account Type(s):
Capital
Contract Start Date:
05/10/2012
Contract End Date:
06/30/2014
Current Contract Value:
$13,797,885
Expenditures:
$13,797,885

* Expenditures data includes accruals and are based on data through 30-Nov-2024.

Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Fulfill all administrative tasks with quality products and in a timely manner. A: 119. Submittal of September Accrual estimates and monthly invoices. 06/30/2014 06/30/2014
Procure Fiberglass Tanks and Incubators B: 171. Procurement 02/28/2013 03/29/2013
Complete Pre-Construction Demolition and Material Removal Work C: 171. Demolition 10/09/2012 09/20/2012
Complete Hatchery Area Site Work D: 171. Hatchery Site Work and Utilities 11/01/2013 09/05/2013
Complete Headbox Construction E: 171. Headbox and Degassing 08/15/2013 08/15/2013
Complete Water Supply Delivery System F: 171. Water Supply and Yard Piping 06/15/2013 08/26/2013
Complete construction of hatchery building G: 171. Hatchery Building 10/30/2013 12/13/2013
Complete construction of roads and parking areas for Springfield Hatchery H: 171. Roads and Access 10/30/2013 08/29/2013
Convert existing residence to bunkhouse I: 171. Remodel Residence 1 01/30/2014 01/16/2014
Complete Outdoor Raceways 1-24 J: 171. Raceways 10/30/2013 12/05/2013
Obtain all necessary state and local construction and disposal permits K: 165. Secure state and local permits 07/31/2012 06/30/2012
Complete Hatchery Housing and Site Construction L: 171. Construct three residences 10/01/2013 09/05/2013
Complete Shop Building M: 171. Construct Shop/Storage Building 10/27/2013 12/05/2013
Complete construction of dual cell effluent/settling basin N: 171. Effluent / Settling Basin 10/30/2013 11/07/2013
Mobilize/Demobilize to and from site. Ascertain needed bonds and insurance O: 171. Mobilization/Demobilization 12/31/2013 11/15/2013
Attach Progress Report in Pisces Q: 132. Submit Completion Report for the period (May 2012) to (Dec 2013) 06/30/2014
Provide owner designated oversight of construction activities R: 171. Construction Oversight 12/31/2013 12/31/2013
Application of General Conditions S: 171. General Conditions 06/30/2014 06/27/2014
Prepare Springfield Hatchery Operation and Maintenance Manual T: 175. Draft O and M Manual 04/30/2014 06/20/2014

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Sockeye (O. nerka) - Snake River ESU (Endangered)
  • 1 instance of WE 175 Produce Design
  • 15 instances of WE 171 Build, Modify, and/or Refurbish Artificial Production Facility

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 119 Submittal of September Accrual estimates and monthly invoices. 06/01/2012
B 171 Procurement 06/13/2012
C 171 Demolition 06/13/2012
D 171 Hatchery Site Work and Utilities 06/13/2012
E 171 Headbox and Degassing 06/13/2012
F 171 Water Supply and Yard Piping 06/13/2012
G 171 Hatchery Building 06/13/2012
H 171 Roads and Access 06/13/2012
I 171 Remodel Residence 1 06/13/2012
J 171 Raceways 06/13/2012
K 165 Secure state and local permits 06/01/2012
L 171 Construct three residences 06/13/2012
M 171 Construct Shop/Storage Building 06/13/2012
N 171 Effluent / Settling Basin 06/13/2012
O 171 Mobilization/Demobilization 06/13/2012
P 185 Periodic Status Reports for BPA 06/01/2012
Q 132 Submit Completion Report for the period (May 2012) to (Dec 2013) 06/01/2012
R 171 Construction Oversight 06/13/2012
S 171 General Conditions 06/13/2012
T 175 Draft O and M Manual 05/10/2012