Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 57531: 1990-044-00 EXP CDA FISHERIES HABITAT RESTORATION
Project Number:
Title:
Coeur D'Alene Reservation Fisheries Habitat
Stage:
Implementation
Area:
Province Subbasin %
Intermountain Coeur D'Alene 100.00%
Contract Number:
57531
Contract Title:
1990-044-00 EXP CDA FISHERIES HABITAT RESTORATION
Contract Continuation:
Previous: Next:
52937: 1990-044-00 EXP CDA FISHERIES HABITAT RESTORATION
  • 61299: 1990-044-00 EXP CDA FISHERIES HABITAT RESTORATION
Contract Status:
Closed
Contract Description:
The scope of work and budget presented in this document describe the activities associated with the Coeur d'Alene Tribe's resident fish enhancement project for the Coeur d'Alene Subbasin corresponding to the contract period June 1, 2012 to May 31, 2013.  The work elements for this project have been grouped under general objective headings corresponding to Planning and Coordination, Construction and Implementation, Research and Monitoring, and Project Administration.

Objective 1 - Planning and Coordination
WE A: NEPA Analysis and Documentation
WE B: Coordinate Restoration Efforts with Stakeholders
WE C: Identify and Select New Restoration Projects
WE D: Produce Fish Passage Designs

Objective 2 - Construction and Implementation
WE E: WF Lake Creek O&M
WE F: Lake Creek Afforestation of Former Cropland
WE G: West Fork Benewah Creek Fish Passage Improvement
WE H: Benewah Creek Channel Construction
WE I: Plant Disturbed Areas in Benewah Creek Following Construction
WE J: Remove Brook Trout from Benewah Creek
WE K: Analyze Data from Brook Trout Removal from Benewah Creek

Objective 3 - Research, Monitoring and Evaluation
WE L: Install and Maintain Migration Traps - Lake and Benewah Creeks
WE M: Trap Adfluvial Westslope Cutthroat Trout - Lake and Benewah Creeks
WE N: Install and Maintain PIT Tag Antenna Systems in Lake and Benewah Creeks
WE O: PIT Tag Juvenile Adfluvial Westslope Cutthroat Trout - Lake and Benewah Creeks
WE P: Sample N. Pike and Smallmouth Bass in Coeur d'Alene Lake
WE Q: Tag Pike and Smallmouth Bass in Coeur d'Alene Lake
WE R: Sample Salmonids in Target Watersheds for Population Estimation
WE S: Biological Data Management
WE T: Analyze Data Generated from Salmonid Trapping and PIT Tagging
WE U: Analyze Data Generated from Salmonid Sampling

Physical Habitat/Water Quality Monitoring
WE V: Measure Physical Habitat in Reference and Treatment Reaches
WE W: Measure Physical Habitat Associated with Beaver Dams
WE X: Measure Water and Air Temperature in Target Watersheds
WE Y: Physical Data Management
WE Z: Analyze Data from Physical Habitat Sampling
WE AA: Analyze Data from Temperature Monitoring
WE AB: Analyze Data from Monitoring of Engineered and Natural Beaver Dam Structures in Benewah Creek

Objective 4 - Project Administration
WE AC: Provide Education and Outreach Opportunities
WE AD: Produce Periodic Status Reports for BPA
WE AE: Submit Annual Report for the period Jan 2011 to Dec 2012
WE AF: Manage and Administer Project

The total work element budget being submitted with this scope of work is $1,549,288
Account Type(s):
Expense
Contract Start Date:
06/01/2012
Contract End Date:
05/31/2013
Current Contract Value:
$1,545,111
Expenditures:
$1,545,111

* Expenditures data includes accruals and are based on data through 30-Nov-2024.

BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Merve Bearcub Coeur D'Alene Tribe Yes Interested Party mmbearcub@cdatribe-nsn.gov (208) 686-5104
Stephanie Breeden Bonneville Power Administration No Interested Party sfbreeden@bpa.gov (503) 230-5192
Jon Firehammer Coeur D'Alene Tribe Yes Technical Contact jfirehammer@cdatribe-nsn.gov (208) 686-7037
Cameron Heusser Coeur D'Alene Tribe Yes Interested Party cheusser@cdatribe-nsn.gov (208) 686-5521
Paul Krueger Bonneville Power Administration Yes F&W Approver pqkrueger@bpa.gov (503) 230-5723
Jennifer Lord Bonneville Power Administration Yes Env. Compliance Lead jklord@bpa.gov (503) 230-5192
Carla Marratt Coeur D'Alene Tribe Yes Contract Manager cmarratt@cdatribe-nsn.gov (208) 686-6803
Kristi Van Leuven Bonneville Power Administration Yes Contracting Officer kjvleuven@bpa.gov (503) 230-3605
Angelo Vitale Coeur D'Alene Tribe Yes Supervisor ajvitale@cdatribe-nsn.gov (208) 686-6903
Virgil Watts III Bonneville Power Administration Yes COR vlwatts@bpa.gov (503) 230-4625


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
NEPA Checklist A: 165. Complete NEPA analysis and documentation 08/28/2012 07/06/2012
Summary of Activities B: 189. Coordinate restoration efforts with stakeholders 05/31/2013 05/24/2013
Project Descriptions/Agreements C: 114. Identify and select new restoration projects 05/31/2013 05/31/2013
Completed designs D: 175. Produce fish passage designs for barriers in Benewah and Lake creeks 05/31/2013 05/31/2013
Completed site maintenance E: 186. Conduct O&M activities for instream habitat in WF Lake Creek 05/31/2013 09/28/2012
Afforestation of former cropland F: 47. Lake Creek afforestation of former cropland and erosion control 05/31/2013 05/09/2013
West Fork Fish Passage Improvement G: 184. West Fork Benewah Creek fish passage improvement 10/31/2012 09/20/2012
Complete Restoration Design & Benewah Creek Construction H: 30. Benewah Creek channel construction 08/17/2012 08/03/2012
Plant 1,760 deciduous trees and shrubs and 6,134 herbaceous plugs I: 47. Plant disturbed areas in Benewah Creek following construction 05/31/2013 04/10/2013
Removal of non-native brook trout from Benewah Creek J: 190. Remove brook trout from Benewah Creek 10/19/2012 10/31/2012
Evaluate the effectiveness of removal techniques K: 162. Analyze data from brook trout removal from Benewah Creek 02/24/2013 02/22/2013
Install Migration Traps in Lake and Benewah Creeks L: 70. Install and maintain migration traps in Lake and Benewah creeks 05/31/2013 05/31/2013
Monitored movements and capture rates of adfluvial cutthroat trout in Lake and Benewah creeks M: 157. Trap juvenile and adult adfluvial westslope cutthroat trout in Lake and Benewah creeks 05/31/2013 05/31/2013
Functional FDX and HDX PIT tag systems N: 70. Install and maintain PIT-tag antenna system in Lake and Benewah Creeks 05/31/2013 05/31/2013
PIT-tag juvenile and adult westslope cutthroat trout in Lake and Benewah creeks. O: 158. PIT Tag adult and juvenile adfluvial westslope cutthroat trout in Lake and Benewah creeks 05/31/2013 05/31/2013
Sampling to provide dietary, abundance, morphometric and age data on bass and pike P: 157. Sample northern pike and smallmouth bass in Lake Coeur d’Alene 05/31/2013 05/31/2013
Mark and tag northern pike and smallmouth bass captured during in-lake sampling Q: 158. Tag northern pike and smallmouth bass in Lake Coeur d’Alene 05/31/2013 05/31/2013
Indices of abundance of salmonids in target watersheds. R: 157. Sample salmonids in rearing habitats of target watersheds for indices of abundance 10/30/2012 10/12/2012
Updated database of biological and life-history salmonid variables for target watersheds. S: 160. Biological data management 05/31/2013 05/31/2013
Abundance and life-history information for adfluvial cutthroat trout in Lake and Benewah creek T: 162. Analyze data generated from trapping and PIT tagging of migratory cutthroat 02/25/2013 02/22/2013
Examination of distribution patterns at the subbasin and watershed scale for indices of abundance U: 162. Analyze data generated from sampling salmonids in rearing habitats in target watersheds 02/25/2013 02/22/2013
Completed inventories V: 157. Measure physical habitat in reference and treatment reaches 10/31/2012 10/12/2012
Description of beaver dam characteristics, dam stability and physical habitat influenced by dams W: 157. Measure physical habitat associated with beaver dams 10/28/2012 11/16/2012
Hourly water and air temperatures describing longitudinal patterns in target watersheds X: 157. Measure water and air temperature in the Lake and Benewah watersheds 05/31/2013 05/31/2013
Updated database of physical habitat attributes, temperature and discharge measurements Y: 160. Physical data management 05/31/2013 05/31/2013
Analyses of physical habitat to generate indicators to serve in effectiveness monitoring Z: 162. Analyze data from physical habitat sampling 02/25/2013 02/22/2013
Analyses of temperature dynamics across various spatial scales AA: 162. Analyze data from temperature monitoring in target watersheds 02/25/2013 02/22/2013
Analyses of dam stability and physical data collected at monitored beaver dams in Benewah Creek AB: 162. Analyze data from monitoring of engineered and natural beaver dam structures in Benewah Creek 02/25/2013 02/22/2013
Summary of Education/Outreach Activities AC: 99. Provide Education and Outreach Opportunities 05/31/2013 05/31/2013
Final 2011/12 report uploaded to the BPA website AE: 132. Submit Bi-annual Report for the period Jan 2011 to Dec 2012 05/31/2013
Accrual Estimates/FY2013 SOW/Metrics Reports AF: 119. Manage and Administer Project 05/31/2013 05/31/2013

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Cutthroat Trout, Westslope (O. c. lewisi)
  • 1 instance of WE 190 Remove, Exclude and/or Relocate Animals
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 30 Realign, Connect, and/or Create Channel
  • 2 instances of WE 47 Plant Vegetation
  • 1 instance of WE 184 Install Fish Passage Structure
  • 1 instance of WE 114 Identify and Select Projects
  • 1 instance of WE 175 Produce Design
  • 2 instances of WE 70 Install Fish Monitoring Equipment
  • 6 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 2 instances of WE 158 Mark/Tag Animals
  • 6 instances of WE 162 Analyze/Interpret Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Complete NEPA analysis and documentation 06/01/2012
B 189 Coordinate restoration efforts with stakeholders 06/01/2012
C 114 Identify and select new restoration projects 06/01/2012
D 175 Produce fish passage designs for barriers in Benewah and Lake creeks 06/01/2012
E 186 Conduct O&M activities for instream habitat in WF Lake Creek 06/01/2012
F 47 Lake Creek afforestation of former cropland and erosion control 06/01/2012
G 184 West Fork Benewah Creek fish passage improvement 06/01/2012
H 30 Benewah Creek channel construction 06/01/2012
I 47 Plant disturbed areas in Benewah Creek following construction 06/01/2012
J 190 Remove brook trout from Benewah Creek 06/01/2012
K 162 Analyze data from brook trout removal from Benewah Creek 06/01/2012
L 70 Install and maintain migration traps in Lake and Benewah creeks 06/01/2012
M 157 Trap juvenile and adult adfluvial westslope cutthroat trout in Lake and Benewah creeks 06/01/2012
N 70 Install and maintain PIT-tag antenna system in Lake and Benewah Creeks 06/01/2012
O 158 PIT Tag adult and juvenile adfluvial westslope cutthroat trout in Lake and Benewah creeks 06/01/2012
P 157 Sample northern pike and smallmouth bass in Lake Coeur d’Alene 06/01/2012
Q 158 Tag northern pike and smallmouth bass in Lake Coeur d’Alene 06/01/2012
R 157 Sample salmonids in rearing habitats of target watersheds for indices of abundance 06/01/2012
S 160 Biological data management 06/01/2012
T 162 Analyze data generated from trapping and PIT tagging of migratory cutthroat 06/01/2012
U 162 Analyze data generated from sampling salmonids in rearing habitats in target watersheds 06/01/2012
V 157 Measure physical habitat in reference and treatment reaches 06/01/2012
W 157 Measure physical habitat associated with beaver dams 06/01/2012
X 157 Measure water and air temperature in the Lake and Benewah watersheds 06/01/2012
Y 160 Physical data management 06/01/2012
Z 162 Analyze data from physical habitat sampling 06/01/2012
AA 162 Analyze data from temperature monitoring in target watersheds 06/01/2012
AB 162 Analyze data from monitoring of engineered and natural beaver dam structures in Benewah Creek 06/01/2012
AC 99 Provide Education and Outreach Opportunities 06/01/2012
AD 185 Periodic Status Reports for BPA 06/01/2012
AE 132 Submit Bi-annual Report for the period Jan 2011 to Dec 2012 06/01/2012
AF 119 Manage and Administer Project 06/01/2012