* Expenditures data includes accruals and are based on data through 30-Nov-2024.
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Complete EC requirements for Early Actions in preparation for project construction in CY 2012 | A: 165. Complete EC requirements and permitting for Early Actions (2012) | 06/30/2013 | 06/30/2013 | |
Design Documents to conduct 2012 restoration actions on the CLT Elochoman Property | B: 175. WDFW Design for Abandoned Logging Road Decommissioning | 12/31/2012 | 10/30/2012 | |
Decommission the abandoned logging road | C: 33. 2012: Decommission abandoned logging road transecting Elochoman wetlands | 12/28/2012 | 10/30/2012 | |
3 Fish Barriers removed on Abandoned Logging Road | D: 85. 2012: Remove Interior Culverts currently acting as fish barriers - along Abandoned Logging Roa | 11/30/2012 | 10/30/2012 | |
Remove Tide Gate lids on two existing culverts crossing SR 4 | E: 85. Remove Tide Gate lids on two existing culverts crossing SR 4 | 12/08/2012 | 10/30/2012 | |
WSDOT will complete final design under a subcontract to WDFW | F: 175. WSDOT Will Work on Engineering Designs for the MP 34.09 Culvert Replacement | 08/14/2013 | 08/14/2013 | |
Manage and Administer Elochoman Tidal Restoration Project | I: 119. WDFW will manage the Elochoman Tidal Restoration Project, and subcontract to WSDOT | 08/14/2013 | 08/14/2013 |
Primary Focal Species | Work Statement Elements |
---|---|
Chinook (Oncorhynchus tshawytscha) - All Populations |
|
Chinook (O. tshawytscha) - Lower Columbia River ESU (Threatened) |
|
Chum (Oncorhynchus keta) - Columbia River ESU (Threatened) |
|
Coho (Oncorhynchus kisutch) - Lower Columbia River ESU (Threatened) |
|
Sockeye (Oncorhynchus nerka) - All Populations |
|
Steelhead (Oncorhynchus mykiss) - All Populations |
|
Steelhead (O. mykiss) - Lower Columbia River DPS (Threatened) |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 165 | Complete EC requirements and permitting for Early Actions (2012) | 02/01/2012 | ||||||
B | 175 | WDFW Design for Abandoned Logging Road Decommissioning | 02/01/2012 | ||||||
C | 33 | 2012: Decommission abandoned logging road transecting Elochoman wetlands | 06/12/2012 | ||||||
D | 85 | 2012: Remove Interior Culverts currently acting as fish barriers - along Abandoned Logging Roa | 06/12/2012 | ||||||
E | 85 | Remove Tide Gate lids on two existing culverts crossing SR 4 | 06/12/2012 | ||||||
F | 175 | WSDOT Will Work on Engineering Designs for the MP 34.09 Culvert Replacement | 02/01/2012 | ||||||
G | 47 | Develop Plan and Conduct Revegetation | |||||||
H | 185 | Periodic Status Reports for BPA | 10/01/2011 | ||||||
I | 119 | WDFW will manage the Elochoman Tidal Restoration Project, and subcontract to WSDOT | 02/01/2012 | ||||||
J | 132 | Does not apply this year | 07/01/2012 |