Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 57921: 2007-398-00 CAP YAKIMA B TRIB/PASS & FLOW-CAP
Project Number:
Title:
Yakima Basinwide Tributary Passage and Flow
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Plateau Yakima 100.00%
Contract Number:
57921
Contract Title:
2007-398-00 CAP YAKIMA B TRIB/PASS & FLOW-CAP
Contract Continuation:
Previous: Next:
n/a
Contract Status:
Closed
Contract Description:
Contract includes the construction of a water control structure for the Barnes Road Diversion facility and adjustments to KJ and MWDA facilities to provide for operations as intended.  Shakedown experiences since construction have shown the need to provide these adjustments so the facilities operate in real-world conditions as was intended when first designed.  For Barnes, the proposed structure will be incorporated in to the existing diversion structure to manage instream water surface elevations. This enhancement will improve personnel safety, functionality of the existing screens, and compliance with WDFW screen submergence criteria.  The improvements to MWDA and KJ involve upgrading power to 3 phase and changing out compressors for more rapid air cycling, increasing wall height at KJ for flood protection, improving water intake situation at the MWDA headgate, generally improving sweeping flow and silt management conditions at MWDA and KJ, and other operational enhancements.  All of this work will be implemented by issuing a firm fixed price construction contract to the winning bidder. Construction will be managed under contract 54966, as will all other A&E services related to these 3  project components.  All other final Manastash passage work will be completed under contract 54966 and in conjunction with KCCD under CR226270.
Account Type(s):
Capital
Contract Start Date:
07/01/2012
Contract End Date:
06/30/2013
Current Contract Value:
$511,236
Expenditures:
$511,236

* Expenditures data includes accruals and are based on data through 30-Nov-2024.

Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Contract
Pricing Method:
Time and Materials
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Brenda Aguirre Bonneville Power Administration Yes Env. Compliance Lead baguirre@bpa.gov (503) 230-5928
Sarah Bettmann HDR Constructors, Inc. No Administrative Contact sarah.bettmann@hdrinc.com (816) 412-1285
Ed Donahue Fishpro, Inc. No Supervisor ed.donahue@hdrinc.com (253) 858-5262
Michael Garello Fishpro, Inc. Yes Contract Manager mike.garello@hdrinc.com (253) 858-5635
Sherry Jeffery HDR Engineering, Inc. Yes Technical Contact sherry.jeffery@hdrinc.com (253) 858-5262
Peter Lofy Bonneville Power Administration Yes F&W Approver ptlofy@bpa.gov (503) 230-4193
Jay Marcotte Bonneville Power Administration Yes COR jgmarcotte@bpa.gov (503) 230-3943
Sherry Swanson Kittitas County Conservation District No Interested Party sherry-swanson@conservewa.net (509) 925-3352x6
Kristi Van Leuven Bonneville Power Administration Yes Contracting Officer kjvleuven@bpa.gov (503) 230-3605


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Installed and Functioning Water Control Structure B: 186. Install Water Control Structure at Barnes Road Diversion 05/03/2013 06/21/2013
Completed and Approved Diversion Facility Enhancements C: 186. Install Enhancements at Keach Jensen Diversion 05/17/2013 06/28/2013
Completed and Approved Diversion Facility Enhancements D: 186. Install Equipment at the MWDA-Consolidated Diversion 03/15/2013 06/28/2013
Fulfill all administrative tasks with quality products and in a timely manner. F: 119. Manage contract 06/30/2013 06/28/2013
All Environmental Compliance is complete before proceeding with any on-the-ground work. G: 165. EC complete 08/01/2012 08/01/2012

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Mid-Columbia River Spring ESU
  • 3 instances of WE 186 Operate and Maintain Habitat/Passage/Structure
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
  • 3 instances of WE 186 Operate and Maintain Habitat/Passage/Structure

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 07/01/2012
B 186 Install Water Control Structure at Barnes Road Diversion 07/01/2012
C 186 Install Enhancements at Keach Jensen Diversion 07/01/2012
D 186 Install Equipment at the MWDA-Consolidated Diversion 07/01/2012
E 132 No progress report required 07/01/2012
F 119 Manage contract 07/01/2012
G 165 EC complete 07/01/2012