Province | Subbasin | % |
---|---|---|
Mountain Snake | Salmon | 100.00% |
Previous: | Next: |
---|---|
n/a |
* Expenditures data includes accruals and are based on data through 31-Dec-2024.
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Funding Package - Submit draft to COTR | A: 119. Manage and Administer Project | 06/03/2013 | ||
Complete all required EC and obtain site specific permits prior to implementation of project actions | B: 165. Environmental Compliance | 06/07/2013 | 06/07/2013 | |
Construction Management Complete | C: 100. Construction management for Pond Series 3 | 09/30/2013 | 09/30/2013 | |
As built record drawings submitted to BPA. | D: 181. Create, Restore and/or Enhance Wetlands at Pond Series 3 | 08/14/2013 | 06/10/2013 | |
As built record drawings submitted to BPA. | E: 180. Enhance floodplain/remove, modify breach dike at Pond Series 3 | 08/14/2013 | 06/10/2013 | |
As built record drawings submitted to BPA. | F: 52. Remove mine tailings at Pond Series 3 | 08/14/2013 | 06/10/2013 | |
As built record drawings submitted to BPA. | G: 30. Create channel at Pond Series 3 | 08/14/2013 | 06/10/2013 | |
As built record drawings submitted to BPA. | H: 29. Increase complexity at Pond Series 3 | 09/30/2013 | 06/10/2013 | |
As built record drawings submitted to BPA. | I: 85. Remove barriers at Pond Series 3 | 08/14/2013 | 06/10/2013 | |
Plant vegetation at PS3: aquatic, wetland, riparian, and upland species | J: 47. Plant vegetation at Pond Series 3 | 09/30/2013 | 06/07/2013 | |
As built record drawings submitted. | K: 55. Construction Site Best Management Practices | 08/14/2013 | 06/10/2013 | |
Attach Progress Report in Pisces | M: 132. Submit Progress Report for the period August 2012 thru September 2013 | 09/20/2013 | ||
Utilize temporary sprinkler system to conduct 2013 field season revegetation irrigation | N: 150. Install sprinkler system for 2013 field season revegetation irrigation | 09/30/2013 | 09/13/2013 |
Primary Focal Species | Work Statement Elements |
---|---|
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened) |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 119 | Manage and Administer Project | 03/15/2012 | ||||||
B | 165 | Environmental Compliance | 03/15/2012 | ||||||
C | 100 | Construction management for Pond Series 3 | 03/15/2012 | ||||||
D | 181 | Create, Restore and/or Enhance Wetlands at Pond Series 3 | 08/17/2015 | ||||||
E | 180 | Enhance floodplain/remove, modify breach dike at Pond Series 3 | 08/27/2012 | ||||||
F | 52 | Remove mine tailings at Pond Series 3 | 08/27/2012 | ||||||
G | 30 | Create channel at Pond Series 3 | 08/27/2012 | ||||||
H | 29 | Increase complexity at Pond Series 3 | 08/27/2012 | ||||||
I | 85 | Remove barriers at Pond Series 3 | 05/29/2017 | ||||||
J | 47 | Plant vegetation at Pond Series 3 | 08/27/2012 | ||||||
K | 55 | Construction Site Best Management Practices | 08/27/2012 | ||||||
L | 185 | Periodic Status Reports for BPA | 03/15/2012 | ||||||
M | 132 | Submit Progress Report for the period August 2012 thru September 2013 | 03/15/2012 | ||||||
N | 150 | Install sprinkler system for 2013 field season revegetation irrigation | 08/29/2012 |