Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 59663: 1994-018-06 EXP TUCANNON STREAM AND RIPARIAN RESTORATION
Project Number:
Title:
Tucannon Stream and Riparian Restoration
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Plateau Tucannon 100.00%
Contract Number:
59663
Contract Title:
1994-018-06 EXP TUCANNON STREAM AND RIPARIAN RESTORATION
Contract Continuation:
Previous: Next:
55843: 1994-018-06 EXP TUCANNON STREAM & RIPARIAN REST
  • 64596: 1994-018-06 EXP TUCANNON STREAM AND RIPARIAN RESTORATION
Contract Status:
Closed
Contract Description:
Implement habitat protection, enhancement and recovery strategies to support Tucannon Subbasin Plan and Snake River Salmon Recovery Plan identified ESA focal, cultural significant and species of interest recovery in the Tucannon Subbasin.  Tucannon Stream and Riparian Protection, Enhancement and Restoration Project, implemented by the Columbia Conservation District , will address riparian recovery/maintenance, flood plain connectivity and instream habitat quantity and diversity, the primary aquatic habitat limiting attributes identified thru EDT analysis and Geomorphic Assessment and Habitat Restoration Study throughout the Tucannon Subbasin.

Riparian recovery/maintenance, flood plain connectivity and instream habitats are critical management objectives addressing the broadest diversity of limiting attributes in identified priority restoration and protection geographic areas will be addressed.  Biological objectives of diversity, reduced embeddedness, LWD recruitment, primary pools, high flow refuga, riparian recovery and temperature will be addressed with this strategy and benefit ESA and cultural significant focal species, spring and fall Chinook, steelhead and bull trout during their respective key life stages throughout the watershed.  Accumulated restoration/protection geographic areas, Pataha/Marengo thru Mountain Tucannon matches NOAA's  Major Spawning Aggregation designation, (MSA), Pataha/Marengo to Tucannon Mouth and Lower Pataha match NOAA'a Minor Spawning Aggregation designations (mSA).
Instream habitat quantity and diversity project focus is within priority protection/restoration geographic areas which cover the entire watershed due to species and species specific life cycle needs.  Projects, implementing identified strategies, address various biological objectives; sediment reduction, primary pools, flood plain connectivity and LWD recruitment/placement.  Project implementation will provide habitat benefits to spring/fall Chinook, steelhead and bull trout during their respective varied life stage needs throughout the watershed.

Program administration functions include contract reporting requirements, participation and coordination with regional recovery and resource management planning efforts, Snake River Salmon Recovery Plan, Washington Department of Ecology 2514 Watershed and TMDL planning, regional M&E planning and Subbasin Plan evaluation and adaptive management planning, project scoping, planning and implementation management.

Monitoring and evaluation efforts for projects and watershed conditions will be a cooperative approach with contract services with USFS, Pomeroy Ranger District and local WDFW staff.
Account Type(s):
Expense
Contract Start Date:
01/01/2013
Contract End Date:
03/31/2014
Current Contract Value:
$394,707
Expenditures:
$394,707

* Expenditures data includes accruals and are based on data through 30-Nov-2024.

Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Brenda Aguirre Bonneville Power Administration Yes Env. Compliance Lead baguirre@bpa.gov (503) 230-5928
Terry Bruegman Columbia Conservation District (SWCD) No Supervisor tb-ccd@daytonwa.net (509) 382-4273x102
Kris Buelow Snake River Salmon Recovery Board No Technical Contact kris@snakeriverboard.org (509) 392-3858
Andre L'Heureux Bonneville Power Administration Yes COR allheureux@bpa.gov (503) 230-4482
Peter Lofy Bonneville Power Administration Yes F&W Approver ptlofy@bpa.gov (503) 230-4193
Debra Nordheim Columbia Conservation District (SWCD) Yes Contract Manager dn-ccd@daytonwa.net (509) 382-4273x101
Kristi Van Leuven Bonneville Power Administration Yes Contracting Officer kjvleuven@bpa.gov (503) 230-3605


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Projects managed well; contracting requirements met. A: 119. Project implementation management and contract administration 03/31/2014 03/31/2014
Documentation and assistance for environmental and cultural resource clearances. B: 165. Obtain Environmental Compliance Clearance for riparian restoration & habitat enhancement projects 09/30/2013 08/20/2013
List of viable Habitat Enhancement projects for potential implementation C: 114. Develop and/or update potential project lists 07/31/2013 07/31/2013
Coordinate Tucannon Watershed Program to improve habitat D: 191. Coordinate Tucannon Watershed Program 03/31/2014 03/31/2014
Meetings, tours, presentations E: 99. Community Involvement in Habitat Restoration 03/31/2014 03/31/2014
Sediment data collected & available F: 157. ISCO Sediment Sampling 12/31/2013 12/31/2013
(Re)establish 4.0 acres of streambank and riparian zone vegetation G: 47. Establish Riparian Plant Community 01/24/2014 02/21/2014
Breach sections of the old rivers edge flood control dike. H: 180. Dike Modification 09/30/2013 09/15/2013
Install 15 LWD structures to enhance instream complexity. I: 29. Off Set Dike LWD Habitat Complexity 10/10/2013 09/15/2013
Annual Report for FY12 J: 132. Annual Report for Jan. 1, 2012 thru Dec. 31, 2012 09/13/2013 09/09/2013
Produce and review design products (report, site-plan, cost-estimate; initiate clearances L: 175. [CCR-31301] Project planning and development 03/31/2014 03/31/2014

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Snake River Fall ESU (Threatened)
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened)
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 114 Identify and Select Projects
  • 1 instance of WE 175 Produce Design
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
Chinook (O. tshawytscha) - Snake River Spring/Summer (not listed)
  • 1 instance of WE 180 Enhance Floodplain/Remove, Modify, Breach Dike
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 180 Enhance Floodplain/Remove, Modify, Breach Dike
  • 1 instance of WE 114 Identify and Select Projects
  • 1 instance of WE 175 Produce Design
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
Trout, Bull (S. confluentus) (Threatened)
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 180 Enhance Floodplain/Remove, Modify, Breach Dike
  • 1 instance of WE 114 Identify and Select Projects
  • 1 instance of WE 175 Produce Design
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 119 Project implementation management and contract administration 01/01/2013
B 165 Obtain Environmental Compliance Clearance for riparian restoration & habitat enhancement projects 01/01/2013
C 114 Develop and/or update potential project lists
D 191 Coordinate Tucannon Watershed Program 01/01/2013
E 99 Community Involvement in Habitat Restoration 01/01/2013
F 157 ISCO Sediment Sampling 03/22/2013
G 47 Establish Riparian Plant Community 08/20/2013
H 180 Dike Modification 08/19/2013
I 29 Off Set Dike LWD Habitat Complexity 08/20/2013
J 132 Annual Report for Jan. 1, 2012 thru Dec. 31, 2012 01/01/2013
K 185 Periodic Status Reports for BPA 01/01/2013
L 175 [CCR-31301] Project planning and development 03/31/2014