Complete environmental compliance |
B: 165. Obtain NEPA/ESA Clearance - FY13 |
|
01/31/2014 |
01/31/2014 |
Complete tern data collection |
C: 157. Collect data on Caspian terns in the Columbia River estuary - FY13 |
|
10/31/2013 |
10/31/2013 |
Complete tern data analysis |
D: 162. Conduct analysis on Caspian tern data - FY13 |
|
01/31/2014 |
01/31/2014 |
Complete cormorant data collection |
E: 157. Collect data on double-crested and Brandt's cormorants - FY13 |
|
10/31/2013 |
10/31/2013 |
Complete cormorant data analysis |
F: 162. Conduct analysis on double-crested and Brandt's cormorant data - FY13 |
|
01/31/2014 |
01/31/2014 |
Complete website postings and professional presentations |
G: 161. Website maintenance and professional presentations - FY13 |
|
01/31/2014 |
01/31/2014 |
Complete project administration, accrual estimates, SOWs, and budgets |
H: 119. Coordinate field activities, administer contract and subcontracts - FY13 |
|
01/31/2014 |
01/31/2014 |
Attach Progress Report in Pisces |
I: 132. Complete Annual Report - FY12 |
|
01/31/2014 |
01/31/2014 |
Complete environmental compliance |
J: 165. Obtain NEPA/ESA Clearance - FY14 |
|
01/31/2015 |
01/31/2015 |
Complete tern data collection |
K: 157. Collect data on Caspian terns in the Columbia River estuary - FY14 |
|
07/31/2014 |
07/31/2014 |
Complete tern data analysis |
L: 162. Conduct analysis on Caspian tern data - FY14 |
|
01/31/2015 |
01/31/2015 |
Complete cormorant data collection |
M: 157. Collect data on double-crested and Brandt's cormorants - FY14 |
|
10/31/2014 |
10/31/2014 |
Complete cormorant data analysis |
N: 162. Conduct analysis on double-crested and Brandt's cormorant data - FY14 |
|
01/31/2015 |
01/31/2015 |
Complete website postings and professional presentations |
O: 161. Website maintenance and professional presentations - FY14 |
|
01/31/2015 |
01/31/2015 |
Complete project administration, accrual estimates, SOWs, and budgets |
P: 119. Coordinate field activities, administer contract and subcontracts - FY14 |
|
01/31/2015 |
01/31/2015 |
Attach Progress Report in Pisces |
Q: 132. Complete Annual Report - FY13 |
|
01/31/2015 |
01/31/2015 |
Complete environmental compliance |
R: 165. Obtain NEPA/ESA Clearance - FY15 |
|
01/31/2016 |
01/31/2016 |
Complete tern data collection |
S: 157. Collect data on Caspian terns in the Columbia River estuary - FY15 |
|
07/31/2015 |
07/31/2015 |
Complete tern data analysis |
T: 162. Conduct analysis on Caspian tern data - FY15 |
|
01/31/2016 |
01/31/2016 |
Complete website postings and professional presentations |
U: 161. Website maintenance and professional presentations - FY15 |
|
01/31/2016 |
01/31/2016 |
Complete project administration, accrual estimates, SOWs, and budgets |
V: 119. Coordinate field activities, administer contract and subcontracts - FY15 |
|
01/31/2016 |
01/31/2016 |
Attach Progress Report in Pisces |
W: 132. Complete Annual Report - FY15 |
|
01/31/2016 |
01/31/2016 |
Complete environmental compliance |
X: 165. Obtain NEPA/ESA Clearance - FY16 |
|
03/31/2016 |
03/31/2016 |
Complete tern data collection |
Y: 157. Caspian tern data collection - FY16 |
|
07/31/2016 |
09/30/2016 |
Complete tern data analysis |
Z: 162. Caspian tern data analysis - FY16 |
|
01/31/2017 |
01/31/2017 |
1 acre of suitable CATE nesting habitat at the E. end of ESI prepared prior the 2016 nesting season |
AA: 36. Caspian tern nesting habitat preparation (core colony) - FY16 |
|
04/04/2016 |
04/04/2016 |
Up to 6 acres of installed passive dissuasion at ESI, with addl. dissuasion installed if necessary |
AB: 190. Caspian tern passive nest dissuasion (off colony) - FY16 |
|
04/05/2016 |
04/05/2016 |
Conduct active dissuasion and monitoring at ESI |
AC: 190. Caspian tern active dissuasion (off colony) - FY 16 |
|
06/30/2016 |
06/30/2016 |
All administrative tasks fulfilled with timely quality products |
AD: 119. Project coordination and administration - FY16 |
|
01/31/2017 |
01/31/2017 |
Complete website postings and professional presentations |
AE: 161. Website maintenance and professional presentations - FY16 |
|
01/31/2017 |
01/31/2017 |
Completed Annual Report |
AF: 132. Complete Annual Report - FY16 |
|
01/31/2017 |
01/31/2017 |
Complete environmental compliance |
AG: 165. Obtain NEPA/ESA Clearance - FY17 |
|
01/31/2018 |
01/24/2018 |
Complete tern data collection |
AH: 157. Caspian tern data collection - FY17 |
|
08/15/2017 |
08/15/2017 |
Complete tern data analysis |
AI: 162. Caspian tern data analysis - FY17 |
|
01/31/2018 |
01/31/2018 |
1 acre of suitable tern nesting habitat on ESI prior the 2017 nesting season |
AJ: 36. Caspian tern nesting habitat preparation (core colony) - FY17 |
|
01/03/2017 |
04/14/2017 |
Up to 6 acres of installed passive dissuasion at ESI, with addl. dissuasion installed if necessary |
AK: 190. Caspian tern passive nest dissuasion (off colony) - FY17 |
|
10/30/2017 |
06/30/2017 |
Conduct active dissuasion and monitoring at ESI |
AL: 190. Caspian tern active dissuasion (off colony) - FY 17 |
|
06/30/2017 |
06/30/2017 |
All administrative tasks fulfilled with timely quality products |
AM: 119. Project coordination and administration - FY17 |
|
01/31/2018 |
01/31/2018 |
Complete website postings and professional presentations |
AN: 161. Website maintenance and professional presentations - FY17 |
|
01/31/2018 |
01/31/2018 |
Completed Annual Report |
AO: 132. Complete Annual Report - FY17 |
|
01/31/2018 |
01/31/2018 |
Complete environmental compliance |
AP: 165. Obtain NEPA/ESA Clearance - FY18 |
|
01/31/2019 |
01/31/2019 |
Produce accessible, error-checked datasets |
AQ: 157. Caspian tern data collection - FY18 |
|
01/31/2019 |
01/31/2019 |
Complete tern data analysis |
AR: 162. Caspian tern data analysis - FY18 |
|
01/31/2019 |
01/31/2019 |
1 acre of suitable tern nesting habitat on ESI prior the 2018 nesting season |
AS: 36. Caspian tern nesting habitat preparation (core colony) - FY18 |
|
02/15/2018 |
04/15/2018 |
Up to 6 acres of installed passive dissuasion at East Sand Island, with additional dissuasion installed if necessary |
AT: 190. Caspian tern passive nest dissuasion (off colony) - FY18 |
|
10/30/2018 |
10/30/2018 |
Conduct active dissuasion and monitoring at ESI |
AU: 190. Caspian tern active dissuasion (off colony) - FY 18 |
|
07/31/2018 |
07/31/2018 |
Effective implementation management and timely contract administration |
AV: 119. Project coordination and administration - FY18 |
|
01/31/2019 |
01/31/2019 |
Complete website postings and professional presentations |
AW: 161. Website maintenance and professional presentations - FY18 |
|
01/31/2019 |
01/31/2019 |
Completed Annual Report |
AX: 132. Complete Annual Report - FY18 |
|
01/31/2019 |
02/04/2019 |
Complete environmental compliance |
AY: 165. Obtain NEPA/ESA Clearance - FY19 |
|
01/31/2020 |
01/31/2020 |
Produce accessible, error-checked datasets |
AZ: 157. Caspian tern data collection - FY19 |
|
01/31/2020 |
01/31/2020 |
Complete tern data analysis |
BA: 162. Caspian tern data analysis - FY19 |
|
01/31/2020 |
01/31/2020 |
Effective implementation management and timely contract administration |
BB: 119. Project coordination and administration - FY19 |
|
01/31/2020 |
01/31/2020 |
Complete website postings and professional presentations |
BC: 161. Website maintenance and professional presentations - FY19 |
|
01/31/2020 |
01/31/2020 |
Final Report |
BD: 162. Produce Avian Predation Synthesis Report |
|
06/30/2021 |
01/31/2020 |
Completed Annual Report |
BE: 132. Complete Annual Report - FY19 |
|
01/31/2020 |
01/31/2020 |
All administrative tasks fulfilled with timely quality products |
BF: 119. Project coordination and administration - FY20 |
|
01/31/2021 |
01/31/2021 |
Annual Progress Report on Avian Predation Monitoring in the Lower Columbia River for CY 2020 |
BG: 132. Complete Annual Report - FY20 |
|
05/31/2021 |
05/31/2021 |
Produce accessible, error-checked datasets |
BH: 157. Piscivorous waterbird data collection - FY20 |
|
01/31/2021 |
01/31/2021 |
Complete website postings and professional presentations |
BI: 161. Website maintenance and professional presentations - FY20 |
|
01/31/2021 |
01/31/2021 |
Deliverable: An accessible, error-checked data set with metadata |
BJ: 162. Piscivorous waterbird data analysis - FY20 |
|
01/31/2021 |
01/31/2021 |
Complete environmental compliance |
BK: 165. Obtain NEPA/ESA Clearance - FY20 |
|
01/31/2021 |
01/31/2021 |
Produce accessible, error-checked datasets |
BL: 157. Collect PIT tag data for Piscivorous Waterbirds at sites in the Columbia River Estuary - FY20 |
|
06/30/2021 |
06/30/2021 |
Deliverable: An accessible, error-checked data set with metadata |
BM: 162. Analyze PIT data from the Columbia River estuary - FY20 |
|
01/31/2021 |
01/31/2021 |