Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 63378: 1989-035-00 EXP UMATILLA HATCHERY O&M
Project Number:
Title:
Umatilla Hatchery Operations and Maintenance (O&M)
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Plateau Umatilla 100.00%
Contract Number:
63378
Contract Title:
1989-035-00 EXP UMATILLA HATCHERY O&M
Contract Continuation:
Previous: Next:
59669: 1989-035-00 EXP UMATILLA HATCHERY O&M
  • 66858: 1989-035-00 EXP UMATILLA HATCHERY O&M
Contract Status:
Closed
Contract Description:
The Northwest Power Planning Council (Council) adopted the Master Plan in 1990 as part of its Fish and Wildlife Program. The Oregon Department of Fish and Wildlife (ODFW), Confederated Tribes of the Umatilla Indian Reservation (CTUIR), and other federal partners designed the Umatilla Hatchery as an experimental tool to achieve adult returns goals (hatchery-origin and natural-origin).  The adult goals include:
·Steelhead (5,500)
·Spring Chinook (8,000)
·Fall Chinook-upriver bright (12,000)
·Coho (6,000)

Maintaining artificial propagation, at its current level, was a recommended action from the Umatilla/Willow Subbasin Planning Team to the Northwest Power and Conversation Council to achieve anadromous adult return goals (memo September 27, 2005).  

Fish production has changed in the program due to Umatilla water flow limitations and adaptive management.  Generally, these changes have resulted in reduced production at Umatilla Hatchery and additional fish production in other Columbia Basin hatcheries. Current fish production for the Umatilla Hatchery includes:
·Summer Steelhead (150,000 smolts)
·Spring Chinook (810,000 smolts)
·Fall Chinook (600,000 sub-yearling smolts)

Production numbers are adaptively managed and reviewed annually under the Annual Operating Plan (AOP).

Other fish produced and transferred to the Umatilla Subbasin include:
·Fall Chinook (480,000 yearling smolts) from Bonneville Hatchery (John Day mitigation)
·Coho (1,000,000 smolts) from Cascade Hatchery (Mitchell Act)

This proposal would fund all Umatilla Hatchery fish production, hatchery maintenance, and fish transfers into the Umatilla River Subbasin.
Account Type(s):
Expense
Contract Start Date:
10/01/2013
Contract End Date:
09/30/2014
Current Contract Value:
$1,095,160
Expenditures:
$1,095,160

* Expenditures data includes accruals and are based on data through 31-Oct-2024.

Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
2013-2014 Annual Report (FY14) A: 132. Annual Report - 10/2013 - 9/2014 09/30/2014 09/30/2014
Assure environmental compliance B: 165. Assurance of Environmental Compliance 09/30/2014 09/01/2014
Fish Transfers C: 66. Fish Transport 05/31/2014 05/13/2014
Hatchery Maintenance D: 61. Maintain Umatilla Hatchery 09/30/2014 09/30/2014
Scope of work/budget/property inventory/FY14 year end accruals E: 119. Manage and Administer Projects 09/30/2014 09/30/2014
Monthly Status Reports Complete F: 141. Other Reports for BPA 09/30/2014 09/30/2014
Produce an Annual Operation Plan (AOP) H: 174. Produce an Annual Operation Plan 08/31/2014 09/02/2014
Spring Chinook production for release I: 176. Produce Conservation group Spring Chinook (BY12) 04/25/2014 03/17/2014
Spring Chinook conservation production for release J: 176. Produce Conservation group Spring Chinook (BY13) 09/30/2014 09/30/2014
Fall Chinook production for release K: 176. Produce fall Chinook sub-yearlings (BY13) 05/31/2014 05/13/2014
Spring Chinook production for acclimation L: 176. Produce Harvest group Spring Chinook (BY12) 04/30/2014 02/04/2014
Spring Chinook harvest production for release in next contract M: 176. Produce Harvest group Spring Chinook (BY13) 09/30/2014 09/30/2014
Steelhead Production for release N: 176. Produce Steelhead (BY14) 09/30/2014 06/30/2014
Fall Chinook harvest production for release P: 176. Produce Umatilla River fall Chinook eyed eggs (BY13) for harvest 03/10/2014 01/08/2014
Steelhead production for transfer and production for release Q: 176. Produced Steelhead (BY13) 05/31/2014 05/02/2014
Run Emergency Electrical Diagnostics at the Umatilla Hatchery S: 61. Run Hatchery Emergency Electrical Diagnostics 05/30/2014 06/30/2014
Installation of 200 AMP Relay to Prevent Main Electrical Breaker Trip T: 61. Perform Corrective Maintenance on Hatchery Water Supply Electrical System 07/18/2014 08/20/2014

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (Oncorhynchus tshawytscha) - All Populations
  • 1 instance of WE 61 Maintain Artificial Production Facility/Infrastructure
Chinook (O. tshawytscha) - Mid-Columbia River Spring ESU
  • 4 instances of WE 176 Produce Hatchery Fish
  • 1 instance of WE 61 Maintain Artificial Production Facility/Infrastructure
Chinook (O. tshawytscha) - Snake River Fall ESU (Threatened)
  • 3 instances of WE 176 Produce Hatchery Fish
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
  • 2 instances of WE 176 Produce Hatchery Fish
  • 1 instance of WE 66 Trap/Collect/Hold/Transport Fish - Hatchery
  • 1 instance of WE 61 Maintain Artificial Production Facility/Infrastructure
  • 1 instance of WE 174 Produce Plan

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 132 Annual Report - 10/2013 - 9/2014 10/01/2013
B 165 Assurance of Environmental Compliance 10/01/2013
C 66 Fish Transport 08/12/2013
D 61 Maintain Umatilla Hatchery 01/22/2014
E 119 Manage and Administer Projects 10/01/2013
F 141 Other Reports for BPA 10/01/2013
G 185 Periodic Status Reports for BPA 10/01/2013
H 174 Produce an Annual Operation Plan 08/12/2013
I 176 Produce Conservation group Spring Chinook (BY12) 10/17/2013
J 176 Produce Conservation group Spring Chinook (BY13) 08/12/2013
K 176 Produce fall Chinook sub-yearlings (BY13) 08/12/2013
L 176 Produce Harvest group Spring Chinook (BY12) 08/12/2013
M 176 Produce Harvest group Spring Chinook (BY13) 08/12/2013
N 176 Produce Steelhead (BY14) 08/12/2013
O 176 Produce Umatilla River fall Chinook eyed eggs (BY13) for conservation 08/12/2013
P 176 Produce Umatilla River fall Chinook eyed eggs (BY13) for harvest 08/12/2013
Q 176 Produced Steelhead (BY13) 08/12/2013
R 132 Submit Progress Report for the period (10/2012) to (9/2013) 10/01/2013
S 61 Run Hatchery Emergency Electrical Diagnostics 05/01/2014
T 61 Perform Corrective Maintenance on Hatchery Water Supply Electrical System 06/19/2014