Province | Subbasin | % |
---|---|---|
Mountain Snake | Salmon | 100.00% |
* Expenditures data includes accruals and are based on data through 31-Dec-2024.
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
All administrative tasks fulfilled with timely quality products | A: 119. Routine administration of contract | 09/26/2014 | 09/26/2014 | |
Provide BPA with all necessary EC/permits | B: 165. Provide to BPA any requested EC/permits | 09/25/2014 | 09/25/2014 | |
Final Project Designs | C: 175. Final Designs for Construction | 07/25/2014 | 07/25/2014 | |
Completed FSOC/NMFS criteria fish screen. | D: 69. LHawC-03 Fish Screen Project | 09/25/2014 | 09/26/2014 | |
LHawC-03 Diversion Installation | E: 84. LHawC-03 Diversion Installation | 09/25/2014 | 09/26/2014 | |
LHawC-03 Pipeline Crossing and Pipeline Bubbler Screen | F: 149. LHawC-03 Pipeline Crossing and Pipeline Bubbler Screen | 09/01/2014 | 09/26/2014 | |
Unobstructed Tower Creek Stream Channel | G: 85. Sioux Lane Culvert Replacement Project | 09/25/2014 | 09/26/2014 | |
Completed Pump Intake Screen | H: 69. P-13 Pump Intake Fish Screen | 09/25/2014 | 09/25/2014 | |
Completed FSOC/NOAA criteria fish screen. | I: 69. SPoiC-01 Fish Screen Project | 05/30/2014 | 05/30/2014 | |
Completed FSOC/NOAA criteria fish screen | J: 69. LHC-08 Fish Screen Project | 09/25/2014 | 08/29/2014 | |
Completed FSOC/NOAA criteria fish screen | K: 69. STC-04 Fish Screen Project | 09/25/2014 | ||
Completed FSOC/NOAA criteria fish screen. | L: 69. L-20 Fish Screen Project | 09/25/2014 | ||
Completed Sprinkler System | M: 150. Carmen Creek Phase III Project | 09/05/2014 | 09/26/2014 | |
S-28 Fish Screen - Bridge Crane | N: 186. S-28 Fish Screen - Bridge Crane | 03/31/2014 | 03/28/2014 | |
Wimpey Creek Culvert Replacement - Phase II | O: 85. Wimpey Creek Culvert Replacement - Phase II | 10/07/2013 | 10/07/2013 | |
Attach Progress Report in Pisces | P: 132. Submit Progress Report for the period October 2012 to September 2013 | 09/26/2014 |
Primary Focal Species | Work Statement Elements |
---|---|
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened) |
|
Sockeye (O. nerka) - Snake River ESU (Endangered) |
|
Steelhead (O. mykiss) - Snake River DPS (Threatened) |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 119 | Routine administration of contract | 09/27/2013 | ||||||
B | 165 | Provide to BPA any requested EC/permits | 09/27/2013 | ||||||
C | 175 | Final Designs for Construction | 11/01/2013 | ||||||
D | 69 | LHawC-03 Fish Screen Project | 03/06/2014 | ||||||
E | 84 | LHawC-03 Diversion Installation | 08/07/2014 | ||||||
F | 149 | LHawC-03 Pipeline Crossing and Pipeline Bubbler Screen | 03/06/2014 | ||||||
G | 85 | Sioux Lane Culvert Replacement Project | 04/10/2014 | ||||||
H | 69 | P-13 Pump Intake Fish Screen | 08/11/2014 | ||||||
I | 69 | SPoiC-01 Fish Screen Project | 03/25/2014 | ||||||
J | 69 | LHC-08 Fish Screen Project | 03/25/2014 | ||||||
K | 69 | STC-04 Fish Screen Project | |||||||
L | 69 | L-20 Fish Screen Project | |||||||
M | 150 | Carmen Creek Phase III Project | 11/05/2013 | ||||||
N | 186 | S-28 Fish Screen - Bridge Crane | 09/27/2013 | ||||||
O | 85 | Wimpey Creek Culvert Replacement - Phase II | 11/06/2013 | ||||||
P | 132 | Submit Progress Report for the period October 2012 to September 2013 | 09/27/2013 | ||||||
Q | 185 | Periodic Status Reports for BPA | 09/27/2013 |