Province | Subbasin | % |
---|---|---|
Blue Mountain | Grande Ronde | 100.00% |
* Expenditures data includes accruals and are based on data through 30-Nov-2024.
Full Name | Organization | Write Permission | Contact Role | Work Phone | |
---|---|---|---|---|---|
Steve Boe | Umatilla Confederated Tribes (CTUIR) | Yes | Contract Manager | steveboe@ctuir.org | (541) 429-7944 |
Julie Burke | Umatilla Confederated Tribes (CTUIR) | Yes | Administrative Contact | julieburke@ctuir.org | (541) 429-7292 |
Katey Grange | Bonneville Power Administration | Yes | Env. Compliance Lead | kcgrange@bpa.gov | (503) 230-4047 |
Brenda Heister | Bonneville Power Administration | Yes | Contracting Officer | bsheister@bpa.gov | (503) 230-3531 |
Gary James | Umatilla Confederated Tribes (CTUIR) | No | Interested Party | garyjames@ctuir.org | (541) 429-7285 |
Paul Krueger | Bonneville Power Administration | Yes | F&W Approver | pqkrueger@bpa.gov | (503) 230-5723 |
Jonathan McCloud | Bonneville Power Administration | Yes | COR | jmmccloud@bpa.gov | (503) 230-3110 |
Leslie Naylor | Umatilla Confederated Tribes (CTUIR) | Yes | Technical Contact | lesnaylor@ctuir.org | (541) 429-7942 |
Gene Shippentower | Umatilla Confederated Tribes (CTUIR) | Yes | Supervisor | geneshippentower@ctuir.org | (541) 429-7287 |
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Complete environmental compliance requirements | A: 165. Review of ESA Collection Permits as needed | 12/31/2014 | 12/30/2014 | |
Calendar Year 2013 BiOp RPA Report | B: 141. Other Reports for BPA | 08/31/2014 | 08/31/2014 | |
Create/modify, and maintain spreadsheets/databases | C: 160. Create and maintain databases | 12/31/2014 | 12/30/2014 | |
PIT tag hatchery-origin spring Chinook salmon at Lookingglass Hatchery. | D: 158. PIT tag hatchery-reared spring Chinook salmon | 12/31/2014 | 12/30/2014 | |
Collect life history data from Lookingglass Creek adult summer steelhead | E: 157. Sample adult summer steelhead from Lookingglass Creek | 12/31/2014 | 12/30/2014 | |
Sample spring Chinook salmon. | F: 157. Sample spring Chinook salmon | 12/31/2014 | 12/30/2014 | |
Sample out-migrating juvenile O. mykiss from Lookingglass Creek | G: 157. Sample juvenile O. mykiss from Lookingglass Creek | 12/31/2014 | 12/30/2014 | |
PIT tag natural-origin out-migrating O. mykiss from Lookingglass Creek. | H: 158. PIT tag or externally mark natural-origin O. mykiss outmigrants from Lookingglass Creek | 12/31/2014 | 12/30/2014 | |
Obtain/validate data for adult summer steelhead from Catherine Creek and the Upper GR traps | I: 157. Validate adult trap data from Catherine Creek and Upper Grande Ronde River | 12/31/2014 | 09/30/2014 | |
Analyze adult spring Chinook data | K: 162. Analyze adult spring Chinook life history data | 12/31/2014 | 12/30/2014 | |
Analyze adult summer steelhead data | M: 162. Analyze adult summer steelhead life history data | 12/31/2014 | 12/30/2014 | |
Analyze juvenile O. mykiss data from Lookingglass Creek. | N: 162. Analyze juvenile O. mykiss data from Lookingglass Creek | 12/31/2014 | 12/30/2014 | |
Post project data on the web. | O: 161. Post project data on the web | 12/31/2014 | 12/30/2014 | |
Steelhead redd counts | P: 157. Steelhead spawning ground survey for biomonitoring plan | 06/30/2014 | 06/24/2014 | |
Spring Chinook salmon redds | Q: 157. Spring Chinook spawning ground survey for biomonitoring plan | 09/30/2014 | 09/30/2014 | |
Productivity of juvenile steelhead | R: 157. Mark Recapture juvenile steelhead for biomonitoring plan | 11/30/2014 | 11/30/2014 | |
Mark recapture juvenile spring Chinook salmon for biomonitoring plan | S: 157. Mark Recapture juvenile spring Chinook salmon for biomonitoring plan | 11/30/2014 | 11/30/2014 | |
Quantitative results | T: 162. Analyze biomonitoring data | 12/31/2014 | 12/30/2014 | |
Attach Progress Report in Pisces | U: 132. Submit Progress Report for the period (Jan 2012 to Dec 2012) | 12/31/2014 | ||
Attach Progress Report in Pisces | V: 132. Submit Progress Report for the period (Jan 2013 to Dec 2013) | 08/31/2014 | ||
SOW/Budget/Property Inventory | W: 119. Manage and Administer Project | 12/31/2014 | 12/31/2014 |
Primary Focal Species | Work Statement Elements |
---|---|
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened) |
|
Steelhead (O. mykiss) - Snake River DPS (Threatened) |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 165 | Review of ESA Collection Permits as needed | 01/01/2014 | ||||||
B | 141 | Other Reports for BPA | 01/01/2014 | ||||||
C | 160 | Create and maintain databases | 01/01/2014 | ||||||
D | 158 | PIT tag hatchery-reared spring Chinook salmon | 11/18/2013 | ||||||
E | 157 | Sample adult summer steelhead from Lookingglass Creek | 11/26/2013 | ||||||
F | 157 | Sample spring Chinook salmon | 11/26/2013 | ||||||
G | 157 | Sample juvenile O. mykiss from Lookingglass Creek | 11/26/2013 | ||||||
H | 158 | PIT tag or externally mark natural-origin O. mykiss outmigrants from Lookingglass Creek | 11/26/2013 | ||||||
I | 157 | Validate adult trap data from Catherine Creek and Upper Grande Ronde River | 11/26/2013 | ||||||
J | 162 | Analyze juvenile spring Chinook salmon data | 01/01/2014 | ||||||
K | 162 | Analyze adult spring Chinook life history data | 01/01/2014 | ||||||
L | 159 | Obtain fish and environmental data | 01/01/2014 | ||||||
M | 162 | Analyze adult summer steelhead life history data | 01/01/2014 | ||||||
N | 162 | Analyze juvenile O. mykiss data from Lookingglass Creek | 01/01/2014 | ||||||
O | 161 | Post project data on the web | 01/01/2014 | ||||||
P | 157 | Steelhead spawning ground survey for biomonitoring plan | 11/26/2013 | ||||||
Q | 157 | Spring Chinook spawning ground survey for biomonitoring plan | 01/01/2014 | ||||||
R | 157 | Mark Recapture juvenile steelhead for biomonitoring plan | 11/26/2013 | ||||||
S | 157 | Mark Recapture juvenile spring Chinook salmon for biomonitoring plan | 11/26/2013 | ||||||
T | 162 | Analyze biomonitoring data | 01/01/2014 | ||||||
U | 132 | Submit Progress Report for the period (Jan 2012 to Dec 2012) | 01/01/2014 | ||||||
V | 132 | Submit Progress Report for the period (Jan 2013 to Dec 2013) | 01/01/2014 | ||||||
W | 119 | Manage and Administer Project | 01/01/2014 | ||||||
X | 185 | Periodic Status Reports for BPA | 01/01/2014 |