Province | Subbasin | % |
---|---|---|
Columbia Plateau | Tucannon | 100.00% |
* Expenditures data includes accruals and are based on data through 31-Oct-2024.
Full Name | Organization | Write Permission | Contact Role | Work Phone | |
---|---|---|---|---|---|
Julie Burke | Umatilla Confederated Tribes (CTUIR) | Yes | Administrative Contact | julieburke@ctuir.org | (541) 429-7292 |
Kris Fischer | Umatilla Confederated Tribes (CTUIR) | No | Contract Manager | KrisFischer@ctuir.org | (541) 429-7547 |
Daniel Gambetta | Bonneville Power Administration | Yes | Env. Compliance Lead | dagambetta@bpa.gov | (503) 230-3493 |
Brenda Heister | Bonneville Power Administration | Yes | Contracting Officer | bsheister@bpa.gov | (503) 230-3531 |
Eric Hoverson | Umatilla Confederated Tribes (CTUIR) | Yes | Technical Contact | erichoverson@ctuir.org | (541) 429-7555 |
Gary James | Umatilla Confederated Tribes (CTUIR) | No | Supervisor | garyjames@ctuir.org | (541) 429-7285 |
Michael Lambert | Umatilla Confederated Tribes (CTUIR) | Yes | Supervisor | mikelambert@ctuir.org | (541) 429-7240 |
Andre L'Heureux | Bonneville Power Administration | Yes | COR | allheureux@bpa.gov | (503) 230-4482 |
Peter Lofy | Bonneville Power Administration | Yes | F&W Approver | ptlofy@bpa.gov | (503) 230-4193 |
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Effective implementation management and timely contract administration | A: 119. Management of Tucannon Watershed Habitat Improvement Projects and Contract Administration | 12/31/2014 | 11/10/2014 | |
Timely and successful Environmental Compliance documentation and clearance | B: 165. Environmental Compliance Clearance for ecological restoration & habitat enhancement projects | 12/31/2014 | 06/20/2014 | |
Establish beneficial relationships and agreements with other entities | C: 191. Coordination of habitat restoration with other entities | 12/31/2014 | 12/16/2014 | |
Program guidance, prioritized project list, and implementation work plan/schedule | D: 114. Identify, prioritize and select projects for habitat improvement | 12/31/2014 | 12/16/2014 | |
LWD & boulders placed in Tucannon stream channel | E: 29. Install woody debris/boulders at PA-1 & PA-3 | 09/30/2014 | 08/24/2014 | |
Improved Vegetation: Tucannon River Project Areas 1 & 3 (RM 47 & 50) | F: 47. Plant native vegetation at PA-1 & PA-3 restoration sites | 12/31/2014 | 12/31/2014 | |
Improve and restore upstream passage into wilderness stream reaches above project area | G: 184. Rectify two passage concerns: modify previously installed poorly functioning cross vane structures | 09/30/2014 | 08/24/2014 | |
Production of educational film documenting PA 1 & 3 success | H: 99. Produce educational documentary of PA 1 & 3 process from planning to implemnentation | 12/31/2014 | 12/23/2014 | |
Submit 42-month Progress Report for 2010-2012 (07/01/2009 - 12/31/2012) | I: 132. Submit Overdue Progress Report(s) for the period: (Jul 2009) to (Dec 2012) | 03/31/2014 | 03/31/2014 |
Primary Focal Species | Work Statement Elements |
---|---|
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened) |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 119 | Management of Tucannon Watershed Habitat Improvement Projects and Contract Administration | 01/01/2014 | ||||||
B | 165 | Environmental Compliance Clearance for ecological restoration & habitat enhancement projects | 01/01/2014 | ||||||
C | 191 | Coordination of habitat restoration with other entities | 01/01/2014 | ||||||
D | 114 | Identify, prioritize and select projects for habitat improvement | 01/01/2014 | ||||||
E | 29 | Install woody debris/boulders at PA-1 & PA-3 | 05/30/2014 | ||||||
F | 47 | Plant native vegetation at PA-1 & PA-3 restoration sites | 05/30/2014 | ||||||
G | 184 | Rectify two passage concerns: modify previously installed poorly functioning cross vane structures | 05/30/2014 | ||||||
H | 99 | Produce educational documentary of PA 1 & 3 process from planning to implemnentation | 01/01/2014 | ||||||
I | 132 | Submit Overdue Progress Report(s) for the period: (Jul 2009) to (Dec 2012) | 01/01/2014 | ||||||
J | 132 | Submit 12-month Progress Report for 2013 | 01/01/2014 | ||||||
K | 185 | Periodic Status Reports for BPA | 01/01/2014 |