Obtain & Submit EC |
A: 165. Produce Environmental Compliance Documentation |
|
06/30/2015 |
06/30/2015 |
Install, Maintain, & Remove RSTs in WSR for Fall & Spring Out-Migration Periods |
B: 70. O. mykiss & Spring Chinook: Install, Maintain, & Remove Warm Springs River Rotary Screw Traps |
|
06/30/2015 |
06/30/2015 |
Operate WSR RSTs during Spring and Fall Out-Migration Periods |
C: 157. O. mykiss & Spring Chinook: Operate Warm Springs River Rotary Screw Trap |
|
06/30/2015 |
06/30/2015 |
PIT Tag 3,000 Juvenile Spring Chinook Salmon at WSR RSTs |
D: 158. Spring Chinook: PIT Tag Spring Chinook at Warm Springs River Rotary Screw Traps |
|
12/12/2014 |
12/08/2014 |
PIT Tag 1,000 Juvenile O. mykiss at WSR RSTs |
E: 158. O. mykiss: PIT Tag O. mykiss at Warm Springs River Rotary Screw Traps |
|
12/12/2014 |
12/08/2014 |
Install, Maintain & Remove RST in SC for Fall & Spring Out-Migration Periods |
F: 70. O. mykiss & Spring Chinook: Install, Maintain, & Remove Shitike Creek Rotary Screw Trap |
|
06/30/2015 |
06/30/2015 |
Operate SC RST during Spring & Fall Out-Migration Periods |
G: 157. O. mykiss & Spring Chinook: Operate Shitike Creek Rotary Screw Trap |
|
06/30/2015 |
06/30/2015 |
PIT Tag 1,000 Juvenile Spring Chinook Salmon at SC RST |
H: 158. Spring Chinook: PIT Tag Spring Chinook at Shitike Creek Rotary Screw Trap |
|
12/12/2014 |
12/11/2014 |
PIT Tag 2,000 Juvenile O. mykiss at SC RST |
I: 158. O. mykiss: PIT Tag O. mykiss at Shitike Creek Rotary Screw Trap |
|
12/12/2014 |
12/11/2014 |
Upload PIT Tag Data to PTAGIS |
J: 159. O. mykiss & Spring Chinook: Enter PIT Tag Data into PTAGIS |
|
06/30/2015 |
06/30/2015 |
Operate & Maintain FDX PIT Tag Antennae in WSR & SC |
K: 157. O. mykiss & Spring Chinook: Collect Data at Warm Springs River and Shitike Creek Full Duplex Arrays |
|
06/30/2015 |
06/30/2015 |
Install, Maintain, & Remove PW in SC |
L: 70. Spring Chinook: Install Picket Weir in Shitike Creek |
|
08/15/2014 |
08/15/2014 |
Operate PW with Camera Box on SC |
M: 157. Spring Chinook: Operate Picket Weir in Shitike Creek |
|
06/30/2015 |
06/30/2015 |
Install RBW |
N: 70. Spring Chinook & Steelhead: Install Resistance Board Weir in Shitike Creek (Phase 2) |
|
03/15/2015 |
02/27/2015 |
Operate RBW |
O: 157. Spring Chinook & Steelhead: Operate Resistance Board Weir in Shitike Creek |
|
06/30/2015 |
06/30/2015 |
Collect & Archive Scale Samples from O. Mykiss & Spring Chinook |
P: 157. O. mykiss & Spring Chinook: Age at Length Verification |
|
06/30/2015 |
06/30/2015 |
Steelhead: Determine Upper Distribution of Redds in Reservation Streams |
Q: 157. Steelhead: Determine Upper Distribution of Redds |
|
06/30/2015 |
06/30/2015 |
Conduct Steelhead Redd Counts on Established Index Reaches in Reservation Streams |
R: 157. Steelhead: Conduct Redd Counts in Established Index Reaches |
|
06/30/2015 |
06/12/2015 |
Select & Survey 20% of Non-Index Reaches in Reservation Streams for Steelhead Redds |
S: 157. Steelhead: Conduct Redd Counts Based on Rotating Panel Design |
|
06/30/2015 |
06/12/2015 |
Spring Chinook: Determine Upper Distribution of Redds |
T: 157. Spring Chinook: Determine Upper Distribution of Redds |
|
06/30/2015 |
06/30/2015 |
Conduct Redd Counts/Spawning Ground Surveys in Reservation Streams |
U: 157. Spring Chinook: Conduct Redd Counts in Established Index Reaches |
|
06/30/2015 |
06/30/2015 |
Select & Survey 20% of Non-Index Reaches in Reservation Streams for Spring Chinook Redds |
V: 157. Spring Chinook: Conduct Redd Counts Based on Rotating Panel Design |
|
06/30/2015 |
06/30/2015 |
Juvenile Steelhead & Spring Chinook Salmon End of Distribution Surveys |
W: 157. O. mykiss & Spring Chinook: Determine Upper Distribution of Juveniles |
|
06/30/2015 |
06/30/2015 |
Juvenile Steelhead & Spring Chinook Salmon Annual Relative Abundance Surveys |
X: 157. O. mykiss & Spring Chinook: Conduct Abundance Estimate Snorkel Surveys on Reservation Streams |
|
06/30/2015 |
06/30/2015 |
Survey Lower WSR for Species Assemblage |
Y: 157. Multiple Species: Determine Species Assemblage in lower Warm Springs River |
|
06/30/2015 |
06/30/2015 |
Attach Progress Report in Pisces |
Z: 132. Submit Progress Report for Calendar Year 2013 |
|
06/30/2015 |
|
BiOp RPA Report |
AA: 141. Other Reports for BPA |
|
06/30/2015 |
|
All Administrative Tasks Fulfilled with Timely Quality Products |
AC: 119. Manage Project |
|
06/30/2015 |
04/30/2015 |