Contract 65288: 1992-009-00 EXP WDFW SCR O&M YAK, UCR, LCR
Project Number:
Title:
Yakima Phase II Fish Screens Operations and Maintenance (O&M) with Washington Department of Fish and Wildlife (WDFW)
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Plateau Yakima 100.00%
Contract Number:
65288
Contract Title:
1992-009-00 EXP WDFW SCR O&M YAK, UCR, LCR
Contract Continuation:
Previous: Next:
61460: 1992-009-00 EXP YAKIMA PH II SCR O&M (WDFW)
  • 69630: 1992-009-00 EXP WDFW SCR O&M, YAK, UCR, LCR
Contract Status:
Closed
Contract Description:
Task 1 - Inspection, operation, and maintenance of two fishways and twenty-four fish screens located on upper and mid-Columbia River tributaries.

Task 2 - Provide ongoing fishway operation and maintenance for 15 lower Columbia River fishways.

Task 3 - Cost-share with other proponents for the funds for fish passage and screening.
Account Type(s):
Expense
Contract Start Date:
04/01/2014
Contract End Date:
06/30/2015
Current Contract Value:
$161,436
Expenditures:
$161,436

* Expenditures data includes accruals and are based on data through 31-Dec-2024.

Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Documentation and assistance to support BPA's Environmental Compliance Group A: 165. Obtain ESA Compliance for O&M Activities 06/30/2015 02/28/2015
All administrative tasks fulfilled with timely quality products B: 119. Manage and administer project 09/30/2014 09/30/2014
Inspect and maintain Upper and mid-Columbia R screens C: 186. Maintain upper + mid-Columbia screens/fishways (Task #1) 12/31/2014 12/31/2014
O&M Lower Columbia River tributary fishway D: 186. Maintain Lower Columbia River passage (Task #2) 12/31/2014 09/30/2014
Provide pre-fabricated fish screens and fish screening materials E: 69. Provide materials to support install of fish screen (Task #3) 06/30/2015 03/31/2015

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Mid-Columbia River Spring ESU
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
Chinook (O. tshawytscha) - Upper Columbia River Spring ESU (Endangered)
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 69 Install Fish Screen
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Obtain ESA Compliance for O&M Activities 04/01/2014
B 119 Manage and administer project 04/01/2014
C 186 Maintain upper + mid-Columbia screens/fishways (Task #1) 04/28/2014
D 186 Maintain Lower Columbia River passage (Task #2) 04/28/2014
E 69 Provide materials to support install of fish screen (Task #3) 04/01/2014
F 185 Periodic Status Reports for BPA 04/01/2014
G 132 Support Annual reporting 04/01/2014