Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 65558: 1992-061-03 EXP O&M ALBENI FALLS WL IDF&G
Project Number:
Title:
Albeni Falls Wildlife Mitigation-Idaho Department of Fish and Game (IDFG)
Stage:
Implementation
Area:
Province Subbasin %
Intermountain Pend Oreille 100.00%
Contract Number:
65558
Contract Title:
1992-061-03 EXP O&M ALBENI FALLS WL IDF&G
Contract Continuation:
Previous: Next:
62496: 1992-061-03 EXP ALBENI FALLS WL IDF&G O&M
  • 69898: 1992-061-03 EXP ALBENI FALLS O&M WL IDF&G
Contract Status:
Closed
Contract Description:
Background

The Pacific Northwest Electric Power Planning and Conservation Act (Act) of 1980 (Public Law 96-501) directed that measures be implemented by Bonneville Power Administration (BPA) to protect, mitigate, and enhance fish and wildlife to the extent affected by development and operation of hydropower projects on the Columbia River system (Martin et al. 1988).  The Act created the Northwest Power Planning and Conservation Council (Council), which in turn developed the Columbia River Basin Fish and Wildlife Program (Program). Under the Act, BPA has the authority and obligation to fund fish and wildlife mitigation activities that are consistent with the Council's Fish and Wildlife Program (USDE 1996).  Part of the Program was the development of wildlife protection, mitigation and enhancement plans for each of the hydropower facilities on the Columbia River system and ultimately, implementation of the plans to mitigate wildlife habitat losses.  The Idaho Department of Fish and Game (IDFG) developed a mitigation plan in 1987, for the Albeni Falls hydroelectric facility that was constructed by the U.S. Army Corps of Engineers (ACOE) on the Pend Oreille River in Bonner County, Idaho between 1951 and 1955 (Martin et al. 1988).  Mitigation plans for wildlife habitat losses at each of the Columbia River Basin dams were submitted by BPA to the Council in 1989, including the mitigation plan for Albeni Falls Dam in Idaho (USDE 1996).  The Council reviewed and approved the Albeni Falls plan in 1990 (USDE 1996).  The Northern Idaho Wildlife Mitigation Agreement was jointly prepared and approved by the IDFG and BPA in June 1997 (BPA and IDFG 1997).  

The Albeni Falls Wildlife Management Plan Final Environmental Assessment (BPA 1996) addressed the potential environmental effects of a proposed wildlife habitat protection and enhancement program.  Based on the analysis in the environmental assessment, the Bonneville Power Administration (BPA) concluded that funding the development and implementation of the Project would enable the IDFG, as well as other federal agencies and sovereign nations to protect and enhance a variety of wetland and riparian habitats, restore 28,587 Habitat Units (HU) lost as a result of construction of the Albeni Falls Dam, and implement long-term wildlife management activities.  The Project also complies with the Wildlife Mitigation Program Final Environmental Impact Statement (BPA 1997) and the standardized planning and implementation process prescriptions set forth in the Record of Decision.  In-lieu of annualizing habitat unit losses the Council decided to mitigate losses at a 2:1 ratio. That is, for every two HU protected the HU ledger would be reduced by one HU. In 2002, however, BPA decided to maintain a 1:1 crediting policy.  The issue of how to address the annualized wildlife habitat losses remains unresolved.

This contract is one of two IDFG contracts for protection, mitigation and enhancement of wildlife habitats in Northern Idaho.  This contract covers all enhancement, operations and maintenance responsibilities for mitigation parcels.  The other contract under Project no. 1992-061-03 covers all management and administrative responsibilities for implementing mitigation projects.  Thus, the Project goals are twofold and are: 1) to continue ongoing implementation of the Albeni Falls Wildlife Mitigation Project; and, 2) to protect, restore, maintain, and manage wetland, riparian and upland coniferous forest habitats on three wildlife management areas in Northern Idaho.  The mitigation parcels managed under this contract are described under each wildlife management area outlined below.

This contract has been developed to cover personnel, maintenance and operating costs for a 12-month contract period with the following objectives:
• Develop management plans that will include, but not be limited to, the following components:  fish and wildlife habitat, recreation and access, fire protection noxious weeds, information and education, operation and maintenance, and monitoring and evaluation.  The management plans will define the management program.
• Coordinate enhancement activities defined in the individual site plans.  Activities may include, but are not limited to, fencing, controlled burns, planting native vegetation, property clean up, and cultivating cropland.
• Coordinate operations and maintenance activities on mitigation project lands. Activities may include maintenance of fences, property and habitat improvements, access, water structures, and information and education facilities, enforcement of easement terms and noxious weed control.
• Management of Acquired Lands to manage, protect, and enhance wildlife species and their habitats based on sound ecosystem techniques and principles - to continue operation and maintenance activities on project lands.
• Enhancement and Restoration - to implement sound ecosystem management to enhance and/or restore degraded habitats on project lands over time.


Boundary Creek/Smith Creek Wildlife Management Areas (BCSCWMA)

The Boundary Creek Wildlife Management Area (WMA) was acquired as farmland in 1999, and involved an ongoing effort to restore an approximately 1,200-acre floodplain wetland complex composed of six herbaceous wetland basins.  Restoration efforts include re-establishment of floodplain deciduous forest and shrub land habitats.  The project also serves to protect 205 acres of upland coniferous forest.  The creation of the Boundary Creek Wildlife Management Area was made possible by a consortium of funding partners composed of the IDFG, Natural Resources Conservation Service (NRCS), BPA, Ducks Unlimited (DU), Intermountain West Joint Venture (IWJV), US Fish and Wildlife Service (USFWS), Crown Pacific (CP), Rocky Mountain Elk Foundation (RMEF), and Kootenai Valley Chapter of Pheasants Forever (PF).  BPA was the principal contributor (29.8%) to land acquisition funding, as well as ongoing operation and management funding. IDFG also contributes to ongoing operation and maintenance funding.   In July 2005, a 40-acre wetland parcel was purchased under the Project.  Deep Creek runs through the 40-acre parcel which is located within the McArthur Lake wildlife corridor, identified as one of the most important regional corridors to protect for large-scale animal movements.  Then in January 2007, the 620-acre Smith Creek parcel, located directly south of the Boundary Creek parcel, was donated to the Department by DU. The Smith Creek parcel was donated with the understanding that it would be enrolled and managed under the BPA Albeni Falls Wildlife Mitigation Project.  In July 2008, IDFG acquired a 20 acre parcel fronting Smith Creek and adjacent to the Smith Creek WMA.  The Boundary Creek/Smith Creek WMA complex now totals about 2,045 acres.


Pend Oreille Wildlife Management Area (POWMA)

Between 1997 and present, IDFG has acquired several wildlife mitigation parcels through the Albeni Falls Wildlife Mitigation Project for the Pend Oreille WMA totaling about 1,996 acres and yielding an estimated 3,356 HU.  The Pend Oreille WMA is composed of individual habitat segments spread from the Washington/Idaho boarder to the Montana/Idaho boarder. Thirteen habitat segments are enrolled under the Project (Table 1).  Over the past few years, many of these parcels have been added to and ownership consolidated by working with neighboring landowners.  Consequently, a new wildlife management plan was prepared for the WMA and was finalized in 2008.   In 2009, the 12-acre Pearl Island was donated to IDFG, and enrolled under the Project.  In accordance with the Monitoring and Evaluation Plan for the Albeni Falls Wildlife Mitigation Project, the purpose of the wildlife management plan is to describe the current situation and the long-term management activities necessary for the protection, enhancement and maintenance of wildlife habitat on mitigation parcels.

Table 1.  Pend Oreille Wildlife Management Area
Mitigation Property Year Acquired    Acres
Albeni Cove               1999                  97        
Carter's Island            1997             96
Cocolalla Lake           1999                118  
Denton Slough           1997             17
Derr  Creek                 1997           240  
Gold Creek                 2005           310
Lower Pack River      1999             32
Pearl Island                2009                  12
Rapid Lightning          1999                661
Tall Pines                   2011                203
Trout Creek                1999                315
Westmond Lake         1999                  65
White Island               2010                137                              

Coeur d'Alene Wildlife Management Area (CDAWMA)

IDFG acquired 62 acres in Benewah County on the St. Joe River in 2007.  An additional 100 acres, more or less, adjacent to the Lower St. Joe parcel is owned by the Avista Corporation.  The intent is to manage these additional acres under a MOA with Avista and the U.S. Forest Service in order to increase the wildlife benefit to the 62-acre St. Joe parcel.  A baseline HEP was completed for the St. Joe acquisition in 2007, and a management plan will be prepared for the St. Joe parcel after the partner agreement is completed.  At present, the 62-acre parcel yields 86.45 baseline HU.  In late 2009, IDFG acquired the 46-acre Robinson Creek parcel which is adjacent to a wetland mitigation parcel held by the Idaho Transportation Department (ITD) and a 350-acre wetland conservation easement.  ITD is willing to transfer their Robinson Creek wetland strip to the Project which will increase the restoration possibilities for the mitigation parcel.
Account Type(s):
Expense
Contract Start Date:
07/01/2014
Contract End Date:
06/30/2015
Current Contract Value:
$403,946
Expenditures:
$403,946

* Expenditures data includes accruals and are based on data through 31-Oct-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Completed Documentation Pertaining to Environmental Compliance A: 165. Environmental Compliance 06/30/2015 06/30/2015
Completed analyzes of vegetative surveys and field data B: 162. BCSCWMA - Analyze/Interpret Field Data 06/30/2015 06/30/2015
Improved Survey Methods C: 122. BCSCWMA - Continue Development of Survey Methodology 06/30/2015 06/30/2015
Control and Monitor the Spread of Noxious Weeds - known established weeds/new infestations D: 198. BCSCWMA - Control and Monitor the Spread of Noxious Weeds on the WMA 06/30/2015 06/30/2015
Control of Nuisance Animals on the Boundary Creek/Smith Creek WMA E: 190. BCSCWMA - Control Nuisance Animals 06/30/2015 06/30/2015
Native Vegetation Plantings and Food Plots F: 47. BCSCWMA - Enhance 1,800 Acres 06/30/2015 06/30/2015
Wetland Management for Maximal Wildlife Usage G: 181. BCSCWMA - Increase Wetland Diversity and Density 06/30/2015 06/30/2015
Hydrologic Control Over the Wetland Areas to Maximize Habitat Value H: 186. BCSCWMA - Maintain 24 Water Control Structures 06/30/2015 06/30/2015
Maintained Fences and Gates I: 186. BCSCWMA - Maintain Gates and Fences 06/30/2015 06/30/2015
Improved Nesting Habitat on the Boundary Creek-Smith Creek WMA. J: 36. BCSCWMA - Erect and Maintain Artificial Nesting Structures 06/30/2015 06/30/2015
Trespass Prevention K: 26. BCSCWMA - Maintain Public Access Sites 06/30/2015 06/30/2015
Updating Management Plans as Needed L: 122. BCSCWMA - Update Management Plan as Necessary 06/30/2015 06/30/2015
Maintained Fences and Gates on the Lower St. Joe Habitat Segment M: 186. CDARWMA - Maintain Gates, Fences and Public Access Sites 06/30/2015 06/30/2015
Control and Monitor the Spread of Noxious Weeds - known established weeds/new infestations N: 198. CDARWMA - Control and Monitor the Spread of Noxious Weeds on the WMA 06/30/2015 06/30/2015
Updated Management Plans as Needed O: 122. CDARWMA - Update Management Plans as Necessary 06/30/2015 06/30/2015
Completed Analyzes Vegetative Surveys and Field Data P: 162. POWMA - Analyze/Interpret Data 06/30/2015 06/30/2015
Improved Survey Methods on the Pend Oreille WMA Q: 122. POWMA - Continue Development of Survey Methodology 06/30/2015 06/30/2015
Control of Nuisance Animals on the Pend Oreille WMA R: 190. POWMA - Control Nuisance Animals 06/30/2015 06/30/2015
Improved Nesting Habitat on the Pend Oreille WMA S: 36. POWMA - Develop Goose and Wood Duck Nesting Platforms 11/05/2014 11/05/2014
Control and Monitor the Spread of Noxious Weeds - known established weeds/new infestations T: 198. POWMA - Control and Monitor the Spread of Noxious Weeds on the WMA 06/30/2015 06/30/2015
Trespass Prevention on the Pend Oreille WMA U: 188. POWMA - Implement Seasonal Closures to Protect Nesting Waterfowl from Disturbance 06/30/2015 06/30/2015
Native Vegetative Plantings on the Pend Oreille WMA V: 47. POWMA - Improve Vegetation Diversity/Waterfowl Habitat 06/30/2015 06/30/2015
Maintained Fences and Gates on the Pend Oreille WMA W: 186. POWMA - Maintain Gates, Fences and Public Access Sites 06/30/2015 06/30/2015
Maintained Nesting Habitat on the Pend Oreille WMA X: 186. POWMA - Maintain Habitat Improvements 06/30/2015 06/30/2015
Hydrologic Control Over the Wetland Y: 186. POWMA - Maintain Water Control Structures 06/30/2015 06/30/2015
Updated Management Plans as Needed Z: 122. POWMA - Update Management Plans as Necessary 06/30/2015 06/30/2015
All administrative tasks fulfilled with timely quality products AA: 119. O&M and Implementation Progress Check 06/30/2015 06/30/2015
Attach Progress Report in Pisces AC: 132. Submit Progress Report for the period (July 2014) to (June 2015) 06/30/2015 06/30/2015

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Wildlife
  • 2 instances of WE 190 Remove, Exclude and/or Relocate Animals
  • 3 instances of WE 198 Maintain Vegetation
  • 1 instance of WE 26 Investigate Trespass
  • 6 instances of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 2 instances of WE 36 Develop Terrestrial Habitat Features
  • 2 instances of WE 47 Plant Vegetation
  • 1 instance of WE 181 Create, Restore, and/or Enhance Wetland
  • 2 instances of WE 162 Analyze/Interpret Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Environmental Compliance 07/01/2014
B 162 BCSCWMA - Analyze/Interpret Field Data 07/01/2014
C 122 BCSCWMA - Continue Development of Survey Methodology 07/01/2014
D 198 BCSCWMA - Control and Monitor the Spread of Noxious Weeds on the WMA
E 190 BCSCWMA - Control Nuisance Animals 04/28/2014
F 47 BCSCWMA - Enhance 1,800 Acres 04/28/2014
G 181 BCSCWMA - Increase Wetland Diversity and Density
H 186 BCSCWMA - Maintain 24 Water Control Structures 04/28/2014
I 186 BCSCWMA - Maintain Gates and Fences 04/28/2014
J 36 BCSCWMA - Erect and Maintain Artificial Nesting Structures 07/01/2014
K 26 BCSCWMA - Maintain Public Access Sites 07/01/2014
L 122 BCSCWMA - Update Management Plan as Necessary 07/01/2014
M 186 CDARWMA - Maintain Gates, Fences and Public Access Sites 04/28/2014
N 198 CDARWMA - Control and Monitor the Spread of Noxious Weeds on the WMA
O 122 CDARWMA - Update Management Plans as Necessary 07/01/2014
P 162 POWMA - Analyze/Interpret Data 07/01/2014
Q 122 POWMA - Continue Development of Survey Methodology 07/01/2014
R 190 POWMA - Control Nuisance Animals 04/28/2014
S 36 POWMA - Develop Goose and Wood Duck Nesting Platforms 06/08/2015
T 198 POWMA - Control and Monitor the Spread of Noxious Weeds on the WMA
U 188 POWMA - Implement Seasonal Closures to Protect Nesting Waterfowl from Disturbance 07/01/2014
V 47 POWMA - Improve Vegetation Diversity/Waterfowl Habitat 07/01/2014
W 186 POWMA - Maintain Gates, Fences and Public Access Sites 07/01/2014
X 186 POWMA - Maintain Habitat Improvements 07/01/2014
Y 186 POWMA - Maintain Water Control Structures 07/01/2014
Z 122 POWMA - Update Management Plans as Necessary 07/01/2014
AA 119 O&M and Implementation Progress Check 07/01/2014
AB 185 Periodic Status Reports for BPA 07/01/2014
AC 132 Submit Progress Report for the period (July 2014) to (June 2015) 07/01/2014