Province | Subbasin | % |
---|---|---|
Blue Mountain | Grande Ronde | 100.00% |
* Expenditures data includes accruals and are based on data through 31-Jan-2025.
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
NEPA Clearance and Permits | A: 165. Obtain NEPA Clearance and Permits | 09/30/2015 | 09/30/2015 | |
Upper Grande Ronde (UGR) RPA/BiOp data submission to CTUIR project leader | B: 202. UGR spring chinook RPA/BiOp Data | 02/28/2015 | 02/28/2015 | |
Rear BY 2009 | C: 176. Rear BY 2009 Safety Net Chinook salmon at Bonneville Hatchery | 09/30/2015 | 06/03/2015 | |
Rear BY 2010 | D: 176. Rear BY 2010 Safety Net Chinook salmon at Bonneville Hatchery | 09/30/2015 | 06/03/2015 | |
Rear BY 2011 | E: 176. Rear BY 2011 Safety Net Chinook salmon at Bonneville Hatchery | 09/30/2015 | 06/03/2015 | |
Fish Health | F: 60. Maintain health of Safety Net Chinook salmon | 09/30/2015 | 09/30/2015 | |
Facility Maintenance | G: 61. Maintain Safety Net Rearing Facilities at Bonneville Fish Hatchery | 09/30/2015 | 09/30/2015 | |
Annual Operating Plan Developed | H: 174. Produce Annual Operation Plan for Grande Ronde Basin Spring Chinook Salmon Safety Net Program | 04/30/2015 | 04/30/2015 | |
Attach Progress Report in Pisces | I: 132. Submit Progress Report for the period (October 2013) to (September 2014) | 06/30/2015 | 03/15/2015 | |
FY16 Contract Package | J: 119. Manage project and prepare FY 2016 Contract Package | 07/01/2015 | 07/01/2015 |
Primary Focal Species | Work Statement Elements |
---|---|
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened) |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 165 | Obtain NEPA Clearance and Permits | 10/01/2014 | ||||||
B | 202 | UGR spring chinook RPA/BiOp Data | |||||||
C | 176 | Rear BY 2009 Safety Net Chinook salmon at Bonneville Hatchery | 10/01/2014 | ||||||
D | 176 | Rear BY 2010 Safety Net Chinook salmon at Bonneville Hatchery | 10/01/2014 | ||||||
E | 176 | Rear BY 2011 Safety Net Chinook salmon at Bonneville Hatchery | 10/01/2014 | ||||||
F | 60 | Maintain health of Safety Net Chinook salmon | 10/01/2014 | ||||||
G | 61 | Maintain Safety Net Rearing Facilities at Bonneville Fish Hatchery | 10/01/2014 | ||||||
H | 174 | Produce Annual Operation Plan for Grande Ronde Basin Spring Chinook Salmon Safety Net Program | 10/01/2014 | ||||||
I | 132 | Submit Progress Report for the period (October 2013) to (September 2014) | 10/01/2014 | ||||||
J | 119 | Manage project and prepare FY 2016 Contract Package | 10/01/2014 | ||||||
K | 185 | Periodic Status Reports for BPA | 10/01/2014 |