Province | Subbasin | % |
---|---|---|
Blue Mountain | Imnaha | 100.00% |
* Expenditures data includes accruals and are based on data through 30-Nov-2024.
Full Name | Organization | Write Permission | Contact Role | Work Phone | |
---|---|---|---|---|---|
Deborah Docherty | Bonneville Power Administration | Yes | COR | dldocherty@bpa.gov | (503) 230-4458 |
Neal Espinosa | Nez Perce Tribe | Yes | Technical Contact | neale@nezperce.org | (541) 432-2502x3772 |
Katey Grange | Bonneville Power Administration | No | Interested Party | kcgrange@bpa.gov | (503) 230-4047 |
James Harbeck | Nez Perce Tribe | Yes | Contract Manager | jimh@nezperce.org | (541) 432-2501 |
Arleen Henry | Nez Perce Tribe | No | Administrative Contact | arleenh@nezperce.org | (208) 621-3833 |
Jay Hesse | Nez Perce Tribe | Yes | Supervisor | jayh@nezperce.org | (208) 621-3552 |
Amber MacLachlan | Bonneville Power Administration | Yes | Contracting Officer | almcmahon@bpa.gov | (503) 230-3983 |
Jason Vogel | Nez Perce Tribe | Yes | Technical Contact | jasonv@nezperce.org | (208) 621-3602 |
Dorothy Welch | Bonneville Power Administration | Yes | F&W Approver | dwwelch@bpa.gov | (503) 230-5479 |
Jesse Wilson | Bonneville Power Administration | Yes | Env. Compliance Lead | jcwilson@bpa.gov | (503) 230-4506 |
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Environmental compliance complete | A: 165. Ensure environmental compliance requirements have been met | 12/31/2015 | 12/31/2015 | |
All administrative tasks fulfilled with timely quality products | B: 119. Manage and Administer Imhaha River Steelhead Project | 12/31/2015 | 12/31/2015 | |
Coordinated Project | C: 189. Coordinate the Imnaha Steelhead Project | 12/31/2015 | 12/31/2015 | |
Data Collection | D: 157. Data Collection | 12/31/2015 | 12/31/2015 | |
Analyzed Data | E: 162. Data Results | 12/31/2015 | 12/31/2015 | |
PIT Tagged Adult Steelhead | F: 158. Pit Tagged Adult Steelhead | 12/31/2015 | 06/19/2015 | |
Tissue Collection | G: 157. Tissue samples for DNA analysis | 12/31/2015 | 06/19/2015 | |
Weir & Array Installation | H: 70. Install Weirs & PIT Tag Arrays | 12/31/2015 | 06/19/2015 | |
Disseminated Information | I: 161. Communication of Results | 12/31/2015 | 12/31/2015 | |
Calendar year 2014 BiOp report | J: 202. Submit Calendar year 2014 BiOp report and begin work on 2015 BiOp report | 03/15/2015 | 03/15/2015 | |
Progress Report has been published | K: 132. Submit Progress Report for the period Jan 2013 - Dec 2013 | 03/15/2015 | 05/29/2015 | |
FY14 Progress Report has been published. | L: 132. Submit Progress Report for the period Jan 2014 - Dec 2014 | 09/30/2015 |
Primary Focal Species | Work Statement Elements |
---|---|
Steelhead (O. mykiss) - Snake River DPS (Threatened) |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 165 | Ensure environmental compliance requirements have been met | 01/01/2015 | ||||||
B | 119 | Manage and Administer Imhaha River Steelhead Project | 01/01/2015 | ||||||
C | 189 | Coordinate the Imnaha Steelhead Project | 01/01/2015 | ||||||
D | 157 | Data Collection | 01/01/2015 | ||||||
E | 162 | Data Results | 01/01/2015 | ||||||
F | 158 | Pit Tagged Adult Steelhead | 01/01/2015 | ||||||
G | 157 | Tissue samples for DNA analysis | 01/01/2015 | ||||||
H | 70 | Install Weirs & PIT Tag Arrays | 01/01/2015 | ||||||
I | 161 | Communication of Results | 01/01/2015 | ||||||
J | 202 | Submit Calendar year 2014 BiOp report and begin work on 2015 BiOp report | |||||||
K | 132 | Submit Progress Report for the period Jan 2013 - Dec 2013 | 01/01/2015 | ||||||
L | 132 | Submit Progress Report for the period Jan 2014 - Dec 2014 | 01/01/2015 | ||||||
M | 185 | Periodic Status Reports for BPA | 01/01/2015 |