Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 68250: 1992-061-02 EXP ALBENI FALLS WL KALISPEL
Project Number:
Title:
Albeni Falls Wildlife Mitigation-Kalispel Tribe
Stage:
Implementation
Area:
Province Subbasin %
Intermountain Pend Oreille 100.00%
Contract Number:
68250
Contract Title:
1992-061-02 EXP ALBENI FALLS WL KALISPEL
Contract Continuation:
Previous: Next:
64001: 1992-061-02 EXP ALBENI FALLS WL KALISPEL
  • 71841: 1992-061-02 EXP ALBENI FALLS WILDLIFE MITIGATION - KALISPEL
Contract Status:
Closed
Contract Description:
Traditionally, the Kalispel Tribe relied on the pend Oreille River Basin and its abundant aquatic and terrestrial resources for subsistence.  The productivity of the area has changed dramatically over the past sixty years due to the construction and inundation by Albeni falls Dam.  Until the Pacific Northwest Power Planning and Conservation Act (Power Act) of 1980 (Public law 96-501) directed that measures be implemented to protect, mitigate, and enhance fish and wildlife to the extent affected by development and operation of hydropower projects on the Columbia River System and that the Bonneville power Administration provide funding to offset identified impacts.   The construction of Albeni Falls dam resulted in the loss of over 20,000 Habitat Units in wetland and riparian habitat types.  These losses occurred exclusively within the Kalispel adjudicated lands. Through the acquisition of property rights (fee title to management agreements), property protection, and habitat enhancement, the Kalispel Tribe is continuing to mitigate for these losses.  This ongoing project (#1992-061-02) provides for the protection, enhancement, restoration, and operation and maintenance (O&M) of acquired lands to offset the negative impacts to wildlife species and habitats affected by the construction and operation of Albeni Falls Dam.   Management activities include hydraulic restoration, wetland enhancement, shoreline protection, and vegetation restoration and enhancement.  Along with active management activities, this contract will monitor past accomplishments to provide scientific support for the continuation of these types of enhancement/restoration activities as applied to additional properties as they become part of this project.   This contract will also cover the O&M of existing habitat value and previously installed structures.
Account Type(s):
Expense
Contract Start Date:
03/01/2015
Contract End Date:
02/29/2016
Current Contract Value:
$831,651
Expenditures:
$831,651

* Expenditures data includes accruals and are based on data through 30-Nov-2024.

BPA CO:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Matthew Berger Kalispel Tribe Yes Contract Manager mberger@knrd.org (509) 447-7244
Rossana Callejas Bonneville Power Administration Yes Interested Party rxcallejas@bpa.gov (503) 230-7558
Hannah Dondy-Kaplan Bonneville Power Administration Yes COR hadondy-kaplan@bpa.gov (503) 230-4071
Ray Entz Kalispel Tribe Yes Supervisor rentz@knrd.org (509) 445-1147
Bart George Kalispel Tribe Yes Technical Contact bgeorge@kalispeltribe.com (509) 671-6149
Solomonn Marsh Bonneville Power Administration Yes Contracting Officer spmarsh@bpa.gov (503) 230-3943
Jolene Seymour Kalispel Tribe Yes Administrative Contact jseymour@kalispeltribe.com (509) 445-1147
Jennifer Snyder Bonneville Power Administration Yes Env. Compliance Lead jasnyder@bpa.gov (503) 230-4187
Dorothy Welch Bonneville Power Administration Yes F&W Approver dwwelch@bpa.gov (503) 230-5479
Elham Zolmajd-Haghighi Bonneville Power Administration No CO Assistant ezolmajd-haghighi@bpa.gov (503) 230-7414


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Completion of Required Project Reporting to BPA B: 119. Oversight of New Projects, Implementation, Construction, O&M, RM&E w/ participating agencies 02/29/2016 02/29/2016
Completed documentation of environmental compliance to BPA C: 165. Complete Permit Applications and Provide Documentation to Obtain Compliance. 02/29/2016 02/29/2016
coordination D: 191. Internal Coordination 02/29/2016 02/29/2016
Completed Acquisition and Easement Agreements E: 172. Pre-Acquisition work 02/29/2016 02/29/2016
Produce materials for Section 106 and ESA consultations for FY16 F: 165. Planning for FY 16 and FY17 work-ESA and cultural consultation 02/28/2016 02/29/2016
Completed FY15 Annual Report to BPA G: 132. Annual Report for 2015 Contract Cycle 02/29/2016 02/29/2016
Completed Operations, Maintenance and Enhancement plan for Indian Creek acquired land H: 174. Complete Management Plan for Indian Creek 01/28/2016
Maintain Existing fence I: 186. Fence Maintenance Idaho 02/29/2016 02/29/2016
Create and enhance Wetland Ponds and plug drainage ditches. J: 181. Create and enhance Wetland Ponds on Washington Management Area 02/29/2016 12/31/2015
Wetland Ponds and shorelines seeded and mulched K: 47. Seed Newly Created Wetland Pond Shorelines 10/05/2015 09/30/2015
Planted Riparian Areas on Enhancement Sites L: 47. Plant Native Trees and Shrubs WA Mngmt Area-Duramus 10/31/2015 10/31/2015
Properties Secured From Trespass M: 26. Secure Properties and Provide Enforcement Management. 02/29/2016 02/29/2016
Maintain access to water control structures. N: 38. Maintain access to water control structures. 02/29/2016 02/29/2016
Water Control Structures Maintained and Functioning O: 186. Maintain Existing Water Control Structures on Wetland Enhancement Sites. 02/29/2016 02/29/2016
Buildings and nursery maintained P: 186. Maintain buildings 02/29/2016 02/29/2016
Vegetation Removal Idaho lands Q: 199. Removal Vegetation Idaho 02/28/2016 02/29/2016
Maintain planted vegetation in Washington. R: 198. Maintain planted vegetation in Washington 11/28/2015 11/28/2015
Provide parking areas and kiosks for visitors S: 188. Provide parking and kiosks for visitors 02/29/2016 02/29/2016
Maintenance of Vegetation on Idaho properties T: 198. Maintain planted vegetation in Idaho 10/05/2015 10/05/2015
Fence Maintenance Washington U: 186. Fence Maintenance Washington 02/29/2016 02/29/2016
Planted Riparian Areas on Enhancement Sites V: 47. Plant Native Trees and Shrubs-WA mgmt area Tacoma 10/31/2015 10/31/2015
Produce Final Design and Specifications for South Flying Goose Streambank Stabilization W: 175. Produce Final Design and Specifications for South Flying Goose Streambank Stabilization 08/31/2015 08/31/2015
Construct and Implement South Flying Goose Streambank Stabilization X: 29. Construct and Implement South Flying Goose Streambank Stabilization 10/31/2015 09/30/2015
Remove Vegetation Washington Y: 199. Remove Vegetation WA 02/29/2016 02/29/2016

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Wildlife
  • 2 instances of WE 199 Remove Vegetation
  • 2 instances of WE 198 Maintain Vegetation
  • 1 instance of WE 26 Investigate Trespass
  • 4 instances of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 38 Improve Road for Instream Habitat Benefits
  • 3 instances of WE 47 Plant Vegetation
  • 1 instance of WE 181 Create, Restore, and/or Enhance Wetland
  • 1 instance of WE 172 Conduct Pre-Acquisition Activities
  • 1 instance of WE 174 Produce Plan
  • 1 instance of WE 175 Produce Design

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 03/01/2015
B 119 Oversight of New Projects, Implementation, Construction, O&M, RM&E w/ participating agencies 03/01/2015
C 165 Complete Permit Applications and Provide Documentation to Obtain Compliance. 03/01/2015
D 191 Internal Coordination 03/01/2015
E 172 Pre-Acquisition work 03/01/2015
F 165 Planning for FY 16 and FY17 work-ESA and cultural consultation 03/01/2015
G 132 Annual Report for 2015 Contract Cycle 03/01/2015
H 174 Complete Management Plan for Indian Creek 03/01/2015
I 186 Fence Maintenance Idaho 03/01/2015
J 181 Create and enhance Wetland Ponds on Washington Management Area 03/01/2015
K 47 Seed Newly Created Wetland Pond Shorelines 03/01/2015
L 47 Plant Native Trees and Shrubs WA Mngmt Area-Duramus 03/01/2015
M 26 Secure Properties and Provide Enforcement Management. 03/01/2015
N 38 Maintain access to water control structures. 03/01/2015
O 186 Maintain Existing Water Control Structures on Wetland Enhancement Sites. 07/20/2015
P 186 Maintain buildings 03/01/2015
Q 199 Removal Vegetation Idaho 07/24/2015
R 198 Maintain planted vegetation in Washington 07/20/2015
S 188 Provide parking and kiosks for visitors 07/24/2015
T 198 Maintain planted vegetation in Idaho 07/24/2015
U 186 Fence Maintenance Washington 03/01/2015
V 47 Plant Native Trees and Shrubs-WA mgmt area Tacoma 07/20/2015
W 175 Produce Final Design and Specifications for South Flying Goose Streambank Stabilization 03/01/2015
X 29 Construct and Implement South Flying Goose Streambank Stabilization 07/27/2015
Y 199 Remove Vegetation WA 07/20/2015