Contract 68920: 2007-268-00 EXP IDAHO WATERSHED HABITAT RESTORATION
Project Number:
Title:
Idaho Watershed Habitat Restoration-Custer District
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Mountain Snake Salmon 100.00%
Contract Number:
68920
Contract Title:
2007-268-00 EXP IDAHO WATERSHED HABITAT RESTORATION
Contract Continuation:
Previous: Next:
63589: 2007-268-00 EXP IDAHO WATERSHED HABITAT RESTORATION
  • 72367: 2007-268-00 EXP IDAHO WATERSHED HABITAT RESTORATION
Contract Status:
Closed
Contract Description:
Problems identified in the Salmon Sub-basin Management Plan (May 2004) indicate that the Upper Salmon Watershed encompasses a total of five Chinook species populations, two steelhead populations and one sockeye population. The Upper Main-stem Salmon River from Pahsimeroi confluence to the headwaters has been altered by irrigation with-drawls. The plan addresses improved connectivity of tributaries that are intercepted or impacted by irrigation ditches.  Improvements to water deliver Pole Creek is anticipated to modify the sequence and/or timing of when the diversion operates and how much flow is taken out of the system at critical times to sustain the focal species. The irrigation diversion components that are addressed within this proposal are in full cooperation and partnership with Idaho Department of Fish and Game Screen Shop, Bureau of Reclamation, Sawtooth National Recreation Area, Shoshone/Bannock Tribes, Idaho Department of Water Resources, NRCS and many other partners including but not limited to OSC and the Upper Salmon Watershed Project. The project on Pole Creek Described in this Statement of Work will facilitate a restored hydrologic cycle within Pole Creek, with near natural peak and base flows. Most notably, during the late summer irrigation period, the current situation will be reversed from ˜75% of flows being removed from Pole Creek to ˜75% remaining within. These considerable flows will extend down the length of Pole Creek (˜4.5 miles) through the private lands, and add substantially to another ˜8 miles of the headwater of the Salmon River, building on the many previous investments and efforts towards the same objectives. These flows, when combined with the other ongoing or anticipated objectives on both public and private lands within Pole Creek, will also provide access to an additional ˜7 miles of critical habitat upstream of the Pole Creek Point of Diversion.
Account Type(s):
Expense
Contract Start Date:
05/01/2015
Contract End Date:
04/30/2016
Current Contract Value:
$847,625
Expenditures:
$847,625

* Expenditures data includes accruals and are based on data through 30-Nov-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Provide Necessary Environmental Compliance documentation for relevant projects A: 165. Produce Environmental Compliance Documents for projects 07/01/2015
Identify and Select Individual Projects B: 114. Identify and develop habitat projects 03/01/2016 03/01/2016
Designs and Specifications and project installation oversight from NRCS on BPA projects C: 175. NRCS Technical Engineer and Challis position 04/30/2016 04/30/2016
Visitation Log D: 26. Investigate Trespass on Easement Property 09/30/2015 09/30/2015
Conduct Education and Outreach Program to target key habitat and passages areas within CSWCD. E: 99. Provide Outreach and Education for Habitat Projects 04/29/2016 04/29/2016
Install 7 sprinkler irrigation center pivots and two pumps and pumps stations F: 203. Install sprinkler irrigation pivots, pumps & infrastructure to ensure water conservation in Pole Crk 11/30/2015 09/30/2015
All administrative tasks fulfilled with timely quality products G: 119. Routine contract actions 04/29/2016 04/29/2016
Attach Progress Report in Pisces I: 132. Annual Report for the period January 2014 through April 30, 2015 07/30/2015 12/21/2015
Remove Garden Creek Lower Diversion and Place Pipe to Deliver Gini Canal Irrigation Water J: 85. Remove Garden Creek Lower Diversion Structure 04/29/2016

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened)
  • 1 instance of WE 203 Install Water Conservation Measure
  • 1 instance of WE 26 Investigate Trespass
  • 1 instance of WE 85 Remove/Breach Fish Passage Barrier
  • 1 instance of WE 175 Produce Design
Chinook (O. tshawytscha) - Upper Columbia River Summer/Fall ESU
  • 1 instance of WE 114 Identify and Select Projects
Sockeye (O. nerka) - Snake River ESU (Endangered)
  • 1 instance of WE 175 Produce Design
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 1 instance of WE 203 Install Water Conservation Measure
  • 1 instance of WE 26 Investigate Trespass
  • 1 instance of WE 85 Remove/Breach Fish Passage Barrier
  • 1 instance of WE 114 Identify and Select Projects
  • 1 instance of WE 175 Produce Design

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Produce Environmental Compliance Documents for projects 01/01/2015
B 114 Identify and develop habitat projects 01/01/2015
C 175 NRCS Technical Engineer and Challis position
D 26 Investigate Trespass on Easement Property 01/01/2015
E 99 Provide Outreach and Education for Habitat Projects 01/01/2015
F 203 Install sprinkler irrigation pivots, pumps & infrastructure to ensure water conservation in Pole Crk 05/01/2015
G 119 Routine contract actions 01/01/2015
H 185 Periodic Status Reports for BPA 01/01/2015
I 132 Annual Report for the period January 2014 through April 30, 2015 01/01/2015
J 85 Remove Garden Creek Lower Diversion Structure