Province | Subbasin | % |
---|---|---|
Blue Mountain | Grande Ronde | 100.00% |
Previous: | Next: |
---|---|
n/a |
* Expenditures data includes accruals and are based on data through 30-Nov-2024.
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Environmental Compliance for Construction Activities | A: 165. Environmental Compliance | 04/30/2016 | 04/30/2016 | |
Installation & Realignment of Exclosure Fencing on Fly Creek-Smith Property | B: 40. Installation & Realignment of Exclosure Fencing on Fly Creek-Smith Property | 12/31/2016 | 11/15/2016 | |
Woody Material Placed in Fly Creek | C: 29. Place Woody Material in Fly Creek to increase fish habitat and cover | 11/30/2016 | 11/15/2016 | |
All administrative tasks fulfilled with timely quality products | D: 119. Project/Contract Administration | 04/30/2016 | 04/30/2016 | |
Upload Completion Report | E: 132. Completion Report - May 2015 - December 2016 | 12/31/2016 |
Primary Focal Species | Work Statement Elements |
---|---|
Steelhead (O. mykiss) - Snake River DPS (Threatened) |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 165 | Environmental Compliance | 05/01/2015 | ||||||
B | 40 | Installation & Realignment of Exclosure Fencing on Fly Creek-Smith Property | 02/25/2016 | ||||||
C | 29 | Place Woody Material in Fly Creek to increase fish habitat and cover | 03/07/2016 | ||||||
D | 119 | Project/Contract Administration | 05/01/2015 | ||||||
E | 132 | Completion Report - May 2015 - December 2016 | 05/01/2015 | ||||||
F | 185 | Quarterly Status Reports | 05/01/2015 |