Contract 72851: 1990-044-00 EXP CDA FISHERIES HABITAT RESTORATION
Project Number:
Title:
Coeur D'Alene Reservation Fisheries Habitat
Stage:
Implementation
Area:
Province Subbasin %
Intermountain Coeur D'Alene 100.00%
Contract Number:
72851
Contract Title:
1990-044-00 EXP CDA FISHERIES HABITAT RESTORATION
Contract Continuation:
Previous: Next:
69003: 1990-044-00 EXP CDA FISHERIES HABITAT RESTORATION
  • 76243: 1990-044-00 EXP CDA FISHERIES HABITAT RESTORATION
Contract Status:
Closed
Contract Description:
The scope of work and budget presented in this document describe the activities associated with the Coeur d'Alene Tribe's resident fish enhancement project for the Coeur d'Alene Subbasin corresponding to the contract period June 1, 2016 to May 31, 2017.  The work elements for this project have been grouped under general objective headings corresponding to Planning and Coordination, Construction and Implementation, Research and Monitoring, and Project Administration.

Objective 1 - Planning and Coordination
WE A: NEPA Analysis and Documentation
WE B: Coordinate Restoration Efforts with Stakeholders
WE C: Identify and Select New Restoration Projects
WE D: Produce Fish Passage Designs

Objective 2 - Construction and Implementation
WE E: School House Creek Fish Passage Improvement
WE F: Alder Creek Fish Passage Improvement
WE G: WF Benewah Creek Fish Passage Improvement
WE H: Reduce Sediment Delivery to Windfall Creek
WE I: Replace Bridge on WF Lake Creek
WE J: Construction and maintenance of beaver dam analogs - Benewah Creek
WE K: Lake Creek Afforestation
WE L: Remove Brook Trout from Benewah Creek
WE M: Analyze Data from Brook Trout Removal from Benewah Creek
WE N: Remove Pike from Coeur d'Alene Lake

Objective 3 - Research, Monitoring and Evaluation
WE O: Install and Maintain Migration Traps - Lake and Benewah Creeks
WE P: Trap Adfluvial Westslope Cutthroat Trout - Lake and Benewah Creeks
WE Q: Install and Maintain PIT Tag Antenna Systems in Lake and Benewah Creeks
WE R: PIT Tag Juvenile Adfluvial Westslope Cutthroat Trout - Lake and Benewah Creeks
WE S: Sample Salmonids in Target Watersheds for Population Estimation
WE T: Biological Data Management
WE U: Analyze Data Generated from Salmonid Trapping and PIT Tagging
WE V: Analyze Data Generated from Salmonid Sampling
WE W: Measure Physical Habitat in Reference and Treatment Reaches
WE X: Measure Physical Habitat Associated with Beaver Dams
WE Y: Measure Water and Air Temperature in Target Watersheds
WE Z: Physical Data Management
WE AA: Analyze Data from Physical Habitat Sampling
WE AB: Analyze Data from Temperature Monitoring
WE AC: Analyze Data from Monitoring of Engineered and Natural Beaver Dam Structures in Benewah Creek

Objective 4 - Project Administration
WE AD: Provide Education and Outreach Opportunities
WE AE: Complete Bi-Annual Report for the period Jan 2015 to Dec 2016
WE AF: Produce Periodic Status Reports for BPA
WE AG: Manage and Administer Project

The total work element budget being submitted with this scope of work is $1,504,520.
Account Type(s):
Expense
Contract Start Date:
06/01/2016
Contract End Date:
05/31/2017
Current Contract Value:
$1,503,612
Expenditures:
$1,503,612

* Expenditures data includes accruals and are based on data through 30-Nov-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Jon Firehammer Coeur D'Alene Tribe Yes Technical Contact jfirehammer@cdatribe-nsn.gov (208) 686-7037
Stephanie Green Bonneville Power Administration Yes Contracting Officer sagreen@bpa.gov (360) 418-2710
Cameron Heusser Coeur D'Alene Tribe Yes Interested Party cheusser@cdatribe-nsn.gov (208) 686-5521
Phyllis Johnson Coeur D'Alene Tribe No Contract Manager pjohnson@cdatribe-nsn.gov (208) 686-6803
Justin Moffett Bonneville Power Administration Yes Env. Compliance Lead jtmoffett@bpa.gov (503) 230-3233
Jennifer Snyder Bonneville Power Administration No Interested Party jasnyder@bpa.gov (503) 230-4187
Angelo Vitale Coeur D'Alene Tribe Yes Supervisor ajvitale@cdatribe-nsn.gov (208) 686-6903
Virgil Watts III Bonneville Power Administration Yes COR vlwatts@bpa.gov (503) 230-4625
Dorothy Welch Bonneville Power Administration Yes F&W Approver dwwelch@bpa.gov (503) 230-5479


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
NEPA Checklist A: 165. Complete NEPA analysis and documentation 05/31/2017 05/31/2017
Summary of Activities B: 189. Coordinate restoration efforts with stakeholders 05/31/2017 05/31/2017
Project Descriptions/Agreements C: 114. Identify and select new restoration projects 05/31/2017 05/31/2017
Completed designs D: 175. Produce fish passage designs for barriers in Benewah and Lake creeks 05/31/2017 05/31/2017
School House Creek Fish Passage Improvement E: 184. School House Creek fish passage improvement 05/31/2017 05/31/2017
Alder Creek Fish Passage Improvement F: 184. Alder Creek fish passage improvement 05/31/2017
WF Benewah Creek Fish Passage Improvement G: 184. WF Benewah Creek fish passage improvement 05/31/2017
Improved road conditions H: 38. Reduce sediment delivery to Windfall Creek 05/31/2017 09/30/2016
Improved road conditions I: 38. Replace bridge on WF Lake Creek 05/31/2017 05/31/2017
BDA Construction and Maintenance J: 29. Construction and maintenance of beaver dam analogs_Benewah Creek 05/31/2017 05/31/2017
Afforestation of former cropland K: 47. Lake Creek Afforestation 05/31/2017 05/31/2017
Removal of non-native brook trout from Benewah Creek L: 190. Remove brook trout from Benewah Creek 10/31/2016 09/30/2016
Evaluate the effectiveness of removal techniques M: 162. Analyze data from brook trout removal from Benewah Creek 02/28/2017 02/28/2017
Removal of non-native northern pike from Lake Coeur d'Alene N: 190. Remove northern pike from Lake Coeur d'Alene 05/31/2017 05/31/2017
Install Migration Traps in Lake and Benewah Creeks O: 70. Install and maintain migration traps in Lake and Benewah creeks 05/31/2017 05/31/2017
Monitored movements and capture rates of adfluvial cutthroat trout in Lake and Benewah creeks P: 157. Trap juvenile and adult adfluvial westslope cutthroat trout in Lake and Benewah creeks 05/31/2017 05/31/2017
Functional HDX PIT tag systems Q: 70. Install and maintain PIT-tag antenna system in Lake and Benewah Creeks 05/31/2017 05/31/2017
PIT-tag juvenile and adult westslope cutthroat trout in Lake and Benewah creeks. R: 158. PIT Tag adult and juvenile adfluvial westslope cutthroat trout in Lake and Benewah creeks 05/31/2017 05/31/2017
Indices of abundance of salmonids in target watersheds. S: 157. Sample salmonids in rearing habitats of target watersheds for indices of abundance 05/31/2017 05/31/2017
Updated database of biological and life-history salmonid variables for target watersheds. T: 160. Biological data management 05/31/2017 05/31/2017
Abundance and life-history information for adfluvial cutthroat trout in Lake and Benewah creek U: 162. Analyze data generated from trapping and PIT tagging of migratory cutthroat 05/31/2017 05/31/2017
Examination of distribution patterns of salmonid abundance at the subbasin and watershed scale V: 162. Analyze data generated from sampling salmonids in rearing habitats in target watersheds 02/28/2017 02/28/2017
Inventory of physical habitat in stream reaches that serve in effectiveness monitoring designs W: 157. Measure physical habitat in reference and treatment reaches 05/31/2017 05/31/2017
Description of beaver dam characteristics, dam stability and physical habitat influenced by dam X: 157. Measure physical habitat associated with beaver dams 10/31/2016 10/14/2016
Hourly water and air temperatures describing longitudinal patterns in target watersheds Y: 157. Measure water and air temperature in the Lake and Benewah watersheds 05/31/2017 05/31/2017
Updated database of physical habitat attributes, temperature and discharge measurements Z: 160. Physical data management 05/31/2017 05/31/2017
Analyses of physical habitat to generate indicators to serve in effectiveness monitoring AA: 162. Analyze data from physical habitat sampling 02/28/2017 02/28/2017
Analyses of temperature dynamics across various spatial scales AB: 162. Analyze data from temperature monitoring in target watersheds 02/28/2017 02/28/2017
Analyses of dam stability and physical data collected at monitored beaver dams AC: 162. Analyze data from monitoring of engineered and natural beaver dam structures in Benewah Creek 02/28/2017 02/28/2017
Summary of Education/Outreach Activities AD: 99. Provide education and outreach opportunities 05/31/2017 05/31/2017
Technical Report 2015-2016 AF: 132. Develop bi-annual report for the periods Jan 2015 to Dec 2016 05/31/2017 05/31/2017
Accrual Estimates/FY2017 SOW/Metrics Reports AG: 119. Manage and administer project 05/31/2017 05/31/2017

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Cutthroat Trout, Westslope (O. c. lewisi)
  • 2 instances of WE 190 Remove, Exclude and/or Relocate Animals
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 2 instances of WE 38 Improve Road for Instream Habitat Benefits
  • 1 instance of WE 47 Plant Vegetation
  • 3 instances of WE 184 Install Fish Passage Structure
  • 1 instance of WE 114 Identify and Select Projects
  • 1 instance of WE 175 Produce Design
  • 2 instances of WE 70 Install Fish Monitoring Equipment
  • 5 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 158 Mark/Tag Animals
  • 6 instances of WE 162 Analyze/Interpret Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Complete NEPA analysis and documentation 06/01/2016
B 189 Coordinate restoration efforts with stakeholders 06/01/2016
C 114 Identify and select new restoration projects 06/01/2016
D 175 Produce fish passage designs for barriers in Benewah and Lake creeks 06/01/2016
E 184 School House Creek fish passage improvement 12/14/2016
F 184 Alder Creek fish passage improvement 12/14/2016
G 184 WF Benewah Creek fish passage improvement 05/03/2017
H 38 Reduce sediment delivery to Windfall Creek 06/01/2016
I 38 Replace bridge on WF Lake Creek
J 29 Construction and maintenance of beaver dam analogs_Benewah Creek 06/01/2016
K 47 Lake Creek Afforestation 05/03/2017
L 190 Remove brook trout from Benewah Creek 06/01/2016
M 162 Analyze data from brook trout removal from Benewah Creek 06/01/2016
N 190 Remove northern pike from Lake Coeur d'Alene 06/01/2016
O 70 Install and maintain migration traps in Lake and Benewah creeks 06/01/2016
P 157 Trap juvenile and adult adfluvial westslope cutthroat trout in Lake and Benewah creeks 06/01/2016
Q 70 Install and maintain PIT-tag antenna system in Lake and Benewah Creeks 06/01/2016
R 158 PIT Tag adult and juvenile adfluvial westslope cutthroat trout in Lake and Benewah creeks 06/01/2016
S 157 Sample salmonids in rearing habitats of target watersheds for indices of abundance 06/01/2016
T 160 Biological data management 06/01/2016
U 162 Analyze data generated from trapping and PIT tagging of migratory cutthroat 06/01/2016
V 162 Analyze data generated from sampling salmonids in rearing habitats in target watersheds 06/01/2016
W 157 Measure physical habitat in reference and treatment reaches 06/01/2016
X 157 Measure physical habitat associated with beaver dams 06/01/2016
Y 157 Measure water and air temperature in the Lake and Benewah watersheds 06/01/2016
Z 160 Physical data management 06/01/2016
AA 162 Analyze data from physical habitat sampling 06/01/2016
AB 162 Analyze data from temperature monitoring in target watersheds 06/01/2016
AC 162 Analyze data from monitoring of engineered and natural beaver dam structures in Benewah Creek 06/01/2016
AD 99 Provide education and outreach opportunities 06/01/2016
AE 185 Periodic Status Reports for BPA 06/01/2016
AF 132 Develop bi-annual report for the periods Jan 2015 to Dec 2016 06/01/2016
AG 119 Manage and administer project 06/01/2016