Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 73139: 2007-224-00 EXP CCT METHOW RESTORATION
Project Number:
Title:
Okanogan Subbasin Habitat Implementation Program (OSHIP)
Stage:
Complete
Area:
Province Subbasin %
Columbia Cascade Okanogan 100.00%
Contract Number:
73139
Contract Title:
2007-224-00 EXP CCT METHOW RESTORATION
Contract Continuation:
Previous: Next:
69004: 2007-224-00 EXP CCT METHOW RESTORATION
Contract Status:
Closed
Contract Description:
This contract is to conduct aquatic habitat protection/restoration projects in the Methow Subbasin.  Projects to be implemented will primarily emphasize benefits to ESA listed spring chinook, summer steelhead, and bull trout and secondarily to other salmonids and Pacific lamprey. Work will include regular attendance of coordination meetings with project sponsors and oversight groups to ensure that work is conducted consistent with established needs and in coordination with other existing restoration efforts.
Account Type(s):
Expense
Contract Start Date:
07/01/2016
Contract End Date:
06/30/2017
Current Contract Value:
$364,556
Expenditures:
$364,556

* Expenditures data includes accruals and are based on data through 31-Oct-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Roy Beaty Bonneville Power Administration Yes F&W Approver rebeaty@bpa.gov (503) 230-5213
Joseph Connor Bonneville Power Administration Yes COR jwconnor@bpa.gov (503) 230-3172
Chris Fisher Colville Confederated Tribes No Supervisor chris.fisher@colvilletribes.com (509) 422-7427
Edward Gresh Bonneville Power Administration Yes Env. Compliance Lead esgresh@bpa.gov (503) 230-5756
Billy Gunn Colville Confederated Tribes Yes Administrative Contact billy.gunn@colvilletribes.com (509) 422-7740
Keith Kistler Colville Confederated Tribes Yes Interested Party keith.kistler@colvilletribes.com (509) 422-7429
Peter Lofy Bonneville Power Administration No Interested Party ptlofy@bpa.gov (503) 230-4193
Solomonn Marsh Bonneville Power Administration Yes Contracting Officer spmarsh@bpa.gov (503) 230-3943
Kary Nichols Colville Confederated Tribes No Interested Party kary.nichols@colvilletribes.com (509) 422-4782
Christopher Roper Bonneville Power Administration No CO Assistant cproper@bpa.gov (503) 230-3514
Tybee Sheidler Bonneville Power Administration No CO Assistant tasheidler@bpa.gov (503) 230-3820
John Stensgar, Jr Colville Confederated Tribes Yes Administrative Contact lj.stensgar.fnw@colvilletribes.com (509) 634-2109
Paul G. Wagner Colville Confederated Tribes Yes Contract Manager paul.wagner@colvilletribes.com (509) 380-3747
Elham Zolmajd-Haghighi Bonneville Power Administration No CO Assistant ezolmajd-haghighi@bpa.gov (503) 230-7414


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Environmental Compliance Documentation A: 165. EC Compliance Documentation 06/30/2017 06/30/2017
All administrative tasks fulfilled with timely quality products B: 119. Project Management 06/30/2017 06/30/2017
Watershed coordination C: 191. Methow Subbasin Coordination 06/30/2017 06/30/2017
Projects selected for implementation D: 114. Project Identification and Selection Process 06/30/2017 06/30/2017
Completed channel construction E: 30. Silver Side Channel 12/31/2016 09/05/2016
Beavers relocated to the Methow basin F: 190. Beaver Relocation Project 06/30/2017 06/30/2017
Restoration site trail loop and informational signage H: 188. M2 Trail Loop Signage 06/30/2017 06/30/2017
Initial assessment to determine stability of wetlands for potential off channel rearing habitat. I: 115. Gann Wetland Assessment 06/30/2017 06/30/2017
Completed Annual Report M: 132. Submit Progress Report for the period 7/1/15 to 6/30/16 01/16/2017 12/21/2016
Thermosink Livestock Watering Trough N: 34. Lawson Thermosink Watering Trough 04/30/2017 05/10/2017

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Upper Columbia River Spring ESU (Endangered)
  • 1 instance of WE 203 Install Water Conservation Measure
  • 1 instance of WE 34 Develop Alternative Water Source
  • 1 instance of WE 114 Identify and Select Projects
  • 1 instance of WE 115 Produce Inventory or Assessment
  • 2 instances of WE 175 Produce Design
  • 2 instances of WE 82 Install Well
Chinook (O. tshawytscha) - Upper Columbia River Summer/Fall ESU
  • 1 instance of WE 203 Install Water Conservation Measure
  • 1 instance of WE 34 Develop Alternative Water Source
Coho (O. kisutch) - Unspecified Population
  • 1 instance of WE 190 Remove, Exclude and/or Relocate Animals
  • 1 instance of WE 203 Install Water Conservation Measure
  • 1 instance of WE 30 Realign, Connect, and/or Create Channel
  • 1 instance of WE 115 Produce Inventory or Assessment
Steelhead (O. mykiss) - Upper Columbia River DPS (Threatened)
  • 1 instance of WE 190 Remove, Exclude and/or Relocate Animals
  • 1 instance of WE 203 Install Water Conservation Measure
  • 1 instance of WE 30 Realign, Connect, and/or Create Channel
  • 1 instance of WE 34 Develop Alternative Water Source
  • 1 instance of WE 184 Install Fish Passage Structure
  • 1 instance of WE 114 Identify and Select Projects
  • 1 instance of WE 115 Produce Inventory or Assessment
  • 2 instances of WE 175 Produce Design
  • 2 instances of WE 82 Install Well
Trout, Bull (S. confluentus) (Threatened)
  • 1 instance of WE 190 Remove, Exclude and/or Relocate Animals
  • 1 instance of WE 82 Install Well

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 EC Compliance Documentation 07/01/2016
B 119 Project Management 07/01/2016
C 191 Methow Subbasin Coordination 07/01/2016
D 114 Project Identification and Selection Process 07/01/2016
E 30 Silver Side Channel 07/11/2016
F 190 Beaver Relocation Project 07/01/2016
G 82 Aspen Meadows Production Well
H 188 M2 Trail Loop Signage 11/30/2016
I 115 Gann Wetland Assessment 12/06/2016
J 184 Maltais Roughened Channel
K 175 Silver Reach Instream Enhancements Phase 1
L 185 Periodic Status Reports for BPA 07/01/2016
M 132 Submit Progress Report for the period 7/1/15 to 6/30/16 07/01/2016
N 34 Lawson Thermosink Watering Trough 07/01/2016
O 82 Redshirt Ditch Production Well
P 175 Burns Garrity Floodplain Restoration Design
Q 203 Barkley Irrigation System Improvements