74017 REL 31: 1996-043-00 EXP JCAPE O&M |
|
* Expenditures data includes accruals and are based on data through 31-Oct-2024.
Full Name | Organization | Write Permission | Contact Role | Work Phone | |
---|---|---|---|---|---|
Anthony Broncheau | Nez Perce Tribe | No | Interested Party | anthonyb@nezperce.org | (208) 843-7317 |
John Gebhards | Nez Perce Tribe | Yes | Contract Manager | johng@nezperce.org | (208) 634-5290x3305 |
Desmond Gelman | Bonneville Power Administration | No | CO Assistant | dxgelman@bpa.gov | (503) 230-4960 |
Arleen Henry | Nez Perce Tribe | No | Administrative Contact | arleenh@nezperce.org | (208) 621-3833 |
Rebecca Johnson | Nez Perce Tribe | Yes | Supervisor | beckyj@nezperce.org | (208) 621-4629 |
Peter Lofy | Bonneville Power Administration | Yes | F&W Approver | ptlofy@bpa.gov | (503) 230-4193 |
Eric McOmie | Bonneville Power Administration | Yes | COR | ermcomie@bpa.gov | (503) 230-4964 |
Craig Rabe | Nez Perce Tribe | Yes | Interested Party | craigr@nezperce.org | (208) 634-5290x3311 |
Carolyn Sharp | Bonneville Power Administration | No | Env. Compliance Lead | casharp@bpa.gov | (503) 230-5206 |
Karen Wolfe | Bonneville Power Administration | Yes | Contracting Officer | ktwolfe@bpa.gov | (503) 230-3448 |
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Environmental Compliance Documentation | B: 165. Produce Environmental Compliance Documentation | 12/31/2020 | 12/29/2020 | |
BY 2018 Smolt Release | C: 176. BY 2018 production activities for the Johnson Creek Supplementation Program | 04/10/2020 | 03/31/2020 | |
BY 2019 Johnson Creek Supplementation Juvenile Rearing | D: 176. BY 2019 production activities for the Johnson Creek Supplementation Program | 12/31/2020 | 12/29/2020 | |
BY 2020 Supplementation Activities | E: 176. BY 2020 production activities for the Johnson Creek Supplementation Program | 12/31/2020 | 12/29/2020 | |
Nutrient Enhancement in Johnson Creek | F: 44. Nutrient Enhancement in Johnson Creek | 09/11/2020 | 09/08/2020 | |
Maintain Hatchery Facilities | G: 61. Hatchery Facilities Maintenance | 12/31/2020 | 12/29/2020 | |
Project Information Presentations | H: 161. Project Information Presentations | 12/31/2020 | 12/29/2020 | |
Outreach and Education | I: 99. Conduct outreach and public education efforts | 12/31/2020 | 12/29/2020 | |
Project Coordination | J: 191. JCAPE O&M Project Coordination | 12/31/2020 | 12/29/2020 | |
Update Annual Operating Plan (AOP) | K: 174. Produce Annual Operation Plan and Hatchery Genetic Management Plan | 12/31/2020 | 12/29/2020 | |
Completed Annual Report | L: 132. Prepare Brood Year 2018 Report (May 2018 to April 2020) | 09/30/2020 | 08/17/2020 | |
Completed Annual Report | M: 132. Prepare 2019 Adult Salmon Run Report (June 2019 to December 2019) | 07/10/2020 | 05/29/2020 | |
Effective implementation management and timely contract administration | N: 119. Manage and Administer Johnson Creek O&M Project | 12/31/2020 | 12/29/2020 |
Primary Focal Species | Work Statement Elements |
---|---|
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened) |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 185 | Periodic Status Reports for BPA | |||||||
B | 165 | Produce Environmental Compliance Documentation | |||||||
C | 176 | BY 2018 production activities for the Johnson Creek Supplementation Program | 01/01/2020 | ||||||
D | 176 | BY 2019 production activities for the Johnson Creek Supplementation Program | 01/01/2020 | ||||||
E | 176 | BY 2020 production activities for the Johnson Creek Supplementation Program | 01/01/2020 | ||||||
F | 44 | Nutrient Enhancement in Johnson Creek | |||||||
G | 61 | Hatchery Facilities Maintenance | 01/01/2020 | ||||||
H | 161 | Project Information Presentations | |||||||
I | 99 | Conduct outreach and public education efforts | |||||||
J | 191 | JCAPE O&M Project Coordination | |||||||
K | 174 | Produce Annual Operation Plan and Hatchery Genetic Management Plan | 01/01/2020 | ||||||
L | 132 | Prepare Brood Year 2018 Report (May 2018 to April 2020) | |||||||
M | 132 | Prepare 2019 Adult Salmon Run Report (June 2019 to December 2019) | |||||||
N | 119 | Manage and Administer Johnson Creek O&M Project |