Contract 74017 REL 77: 1983-350-00 EXP NEZ PERCE TRIBAL HATCHERY O&M
Project Number:
Title:
Nez Perce Tribal Hatchery Operations and Maintenance (O&M)
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Mountain Snake Clearwater 100.00%
Contract Number:
74017 REL 77
Contract Title:
1983-350-00 EXP NEZ PERCE TRIBAL HATCHERY O&M
Contract Continuation:
Previous: Next:
74017 REL 60: 1983-350-00 EXP NEZ PERCE TRIBAL HATCHERY O&M
  • 74017 REL 92: 1983-350-00 EXP NEZ PERCE TRIBAL HATCHERY (O&M)
Contract Status:
Closed
Contract Description:
AUTHORIZATION:

The Northwest Power Planning Council (NPPC) authorized construction of Nez Perce Tribal Hatchery Complex (NPTHC) facilities 17, May 2000.  Construction began July 2001 and was essentially completed in October 2002.  The hatchery was dedicated 9, October 2002.  Spring and fall Chinook salmon eggs were brought on-station for incubation in October, and all systems appeared to be functioning.  

This statement of work and budget contain activities and costs associated with the operation and maintenance of the Nez Perce Tribal Hatchery and six satellite facilities.  Based on NPPC authorization for out-year operation and maintenance costs we have budgeted $2,148,321 (including separate fish feed and utility contracts) for FY2020
Account Type(s):
Expense
Contract Start Date:
01/01/2021
Contract End Date:
12/31/2021
Current Contract Value:
$1,952,346
Expenditures:
$1,952,346

* Expenditures data includes accruals and are based on data through 30-Nov-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Release
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Anthony Broncheau Nez Perce Tribe No Administrative Contact anthonyb@nezperce.org (208) 843-7317
Minda Donnelly Department of Energy - IGE No Interested Party minda.donnelly@doe.gov (702) 295-0874
Carl East Nez Perce Tribe Yes Contract Manager carle@nezperce.org (208) 621-3503
Arleen Henry Nez Perce Tribe No Administrative Contact arleenh@nezperce.org (208) 621-3833
Rebecca Johnson Nez Perce Tribe Yes Supervisor beckyj@nezperce.org (208) 621-4629
Scott Kellar Nez Perce Tribe Yes Contract Manager scottk@nezperce.org (208) 827-1669
Peter Lofy Bonneville Power Administration Yes F&W Approver ptlofy@bpa.gov (503) 230-4193
Jennifer McKenna Bonneville Power Administration No CO Assistant jmmckenna@bpa.gov (503) 314-8915
Eric McOmie Bonneville Power Administration Yes COR ermcomie@bpa.gov (503) 230-4964
Crystal Miller Department of Energy - IGE No Interested Party crystal.miller@doe.gov (702) 295-0779
Carolyn Sharp Bonneville Power Administration Yes Env. Compliance Lead casharp@bpa.gov (503) 230-5206
Tod Sween Nez Perce Tribe No Interested Party tods@nezperce.org (208) 621-3582
Emily Wiegert Department of Energy - IGE No Interested Party emily.wiegert@doe.gov (123) 456-7890
Karen Wolfe Bonneville Power Administration Yes Contracting Officer ktwolfe@bpa.gov (503) 230-3448
Jae Woo Department of Energy - IGE No Interested Party jae.woo@doe.gov (702) 295-0874


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Project Administration B: 119. Manage and Administer Project 12/31/2021 12/29/2021
Procurement of permits and EC authorizations C: 165. Obtain Permits and submit copies to BPA NEPA group 12/31/2021 12/29/2021
Attach Annual Operation Plan in Pisces D: 174. Submit Annual Operation Plan 10/31/2021 10/29/2021
Regional Coordination E: 189. Coordinate Project Activities on a Regional Basis 12/31/2021 12/29/2021
Facility & Equipment Maintenance F: 61. NPTHC Facility Maintenance 12/31/2021 12/29/2021
Salmon Production - BY20 Spring Chinook G: 176. Salmon Production - BY20 Spring Chinook 12/31/2021 12/29/2021
Salmon Production - BY21 Spring Chinook H: 176. Salmon Production - BY21 Spring Chinook 12/31/2021 12/29/2021
Salmon Production - BY 21 Fall Chinook I: 176. Salmon Production - BY21 Fall Chinook 12/31/2021 12/29/2021
Education/Outreach J: 99. Conduct Outreach and Public Education 12/31/2021 12/29/2021
Submit monthly reports K: 141. Other Reports for BPA 12/31/2021 12/29/2021
Document lamprey holding activities (funded by non-BPA funds) L: 66. Hold Lamprey 12/31/2021 12/29/2021
Hold 275,000 Coho for acclimation M: 66. Hold Coho 04/05/2021 04/05/2021
Completed Annual Report N: 132. Submit Progress Report for the period Jan 1, 2020 to Dec 31, 2020 12/31/2021 12/29/2021
Hold 180,000 SCS Lolo Creek Smolts O: 66. Hold 180,000 SCS Lolo Creek smolts 04/01/2021 03/25/2021
Project Information presentations P: 161. Communicate project results 12/31/2021 12/29/2021

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (Oncorhynchus tshawytscha) - All Populations
  • 1 instance of WE 66 Trap/Collect/Hold/Transport Fish - Hatchery
Chinook (O. tshawytscha) - Snake River Fall ESU (Threatened)
  • 1 instance of WE 176 Produce Hatchery Fish
  • 1 instance of WE 61 Maintain Artificial Production Facility/Infrastructure
  • 1 instance of WE 174 Produce Plan
  • 1 instance of WE 161 Disseminate Raw/Summary Data and Results
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened)
  • 1 instance of WE 161 Disseminate Raw/Summary Data and Results
Chinook (O. tshawytscha) - Snake River Spring/Summer (not listed)
  • 2 instances of WE 176 Produce Hatchery Fish
  • 1 instance of WE 61 Maintain Artificial Production Facility/Infrastructure
  • 1 instance of WE 174 Produce Plan
Coho (O. kisutch) - Unspecified Population
  • 1 instance of WE 66 Trap/Collect/Hold/Transport Fish - Hatchery
Lamprey, Pacific (Entosphenus tridentata)
  • 1 instance of WE 66 Trap/Collect/Hold/Transport Fish - Hatchery

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA
B 119 Manage and Administer Project
C 165 Obtain Permits and submit copies to BPA NEPA group
D 174 Submit Annual Operation Plan 10/28/2020
E 189 Coordinate Project Activities on a Regional Basis
F 61 NPTHC Facility Maintenance 10/28/2020
G 176 Salmon Production - BY20 Spring Chinook 10/28/2020
H 176 Salmon Production - BY21 Spring Chinook 10/28/2020
I 176 Salmon Production - BY21 Fall Chinook 10/28/2020
J 99 Conduct Outreach and Public Education
K 141 Other Reports for BPA
L 66 Hold Lamprey 10/28/2020
M 66 Hold Coho
N 132 Submit Progress Report for the period Jan 1, 2020 to Dec 31, 2020
O 66 Hold 180,000 SCS Lolo Creek smolts
P 161 Communicate project results