Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
RSS Feed for updates to Project 1983-350-00 - Nez Perce Tribal Hatchery Operations and Maintenance (O&M) Follow this via RSS feed. Help setting up RSS feeds?

Project Summary

Project 1983-350-00 - Nez Perce Tribal Hatchery Operations and Maintenance (O&M)
Project Number:
1983-350-00
Title:
Nez Perce Tribal Hatchery Operations and Maintenance (O&M)
Summary:
AUTHORIZATION:
The Northwest Power Planning Council (NPPC) authorized construction of Nez Perce Tribal Hatchery facilities 17, May 2000, in Helena, MT. Construction began July 2001 and was essentially completed in October 2002. The hatchery was dedicated 9, October 2002. Spring and fall Chinook salmon eggs were brought on-station, for incubation in October and all systems appeared to be functioning.
This statement of work and budget contain activities and costs associated with the operation and maintenance of the Nez Perce Tribal Hatchery and six satellite facilities.

Effective 10/1/2024: Work and budgets from projects: 1983-350-00 NPT Hatchery O&M, 1996-043-00 Johnson Creek Artificial Prop. O&M, and 1998-007-02 Grand Ronde Supplementation O&M are merging to become project 2025-003-00. This project will close when all contracts are closed.
Proposer:
None
Proponent Orgs:
Nez Perce Tribe (Tribe)
Starting FY:
2004
Ending FY:
2024
BPA PM:
Stage:
Implementation - Project Status Report
Area:
Province Subbasin %
Mountain Snake Clearwater 100.00%
Purpose:
Artificial Production
Emphasis:
Supplementation
Focal Species:
All Anadromous Fish
All Anadromous Salmonids
Chinook - All Populations
Chinook - Snake River Fall ESU
Chinook - Snake River Spring/Summer
Chinook - Snake River Spring/Summer ESU
Coho - Unspecified Population
Lamprey, Pacific
Other Anadromous
Species Benefit:
Anadromous: 100.0%   Resident: 0.0%   Wildlife: 0.0%
Special:
None

Description: Page: 5 Figure 1: Clearwater River Subbasin map with Nez Perce Tribal Hatchery Complex facilities identified.

Project(s): 1983-350-00

Document: P121795

Dimensions: 1056 x 781

Description: Adult lamprey being innoculated prior to being transferred to holdin tank at NPTH.

Contract(s):

45237

Dimensions: 2816 x 2112


Summary of Budgets

To view all expenditures for all fiscal years, click "Project Exp. by FY"

To see more detailed project budget information, please visit the "Project Budget" page

Decided Budget Transfers  (FY2024 - FY2026)

Acct FY Acct Type Amount Fund Budget Decision Date
FY2024 Expense $2,311,653 From: BiOp FCRPS 2008 (non-Accord) FY24 SOY Budget Upload 06/01/2023

Pending Budget Decision?  No


Actual Project Cost Share

Current Fiscal Year — 2025
Cost Share Partner Total Proposed Contribution Total Confirmed Contribution
There are no project cost share contributions to show.

Contracts

The table below contains contracts with the following statuses: Active, Closed, Complete, History, Issued.
* "Total Contracted Amount" column includes contracted amount from both capital and expense components of the contract.
Capital Contracts:
Number Contractor Name Title Status Total Contracted Amount Dates
333 REL 41 SOW Nez Perce Tribe 1983-350 NEZ PERCE TRIBAL HATCHERY Closed $782,198 1/1/2000 - 12/31/2000
429 REL 9 SOW Fishpro, Inc. 1983-350-05 CONSTRUCTION MANAGEMENT OF NEZ PERCE TRIBAL HATCHERY Closed $147,109 1/1/2000 - 12/31/2000
429 REL 13 SOW Fishpro, Inc. 1983-350-05 - CONSTRUCTION OF THE NEZ PERCE TRIBAL HATCHERY Closed $3,286,000 6/14/2000 - 12/31/2002
429 REL 15 SOW Fishpro, Inc. 1983-350-00 CONSTRUCTION OF NEZ PERCE TRIBAL HATCHERY Closed $11,441,277 10/1/2000 - 6/30/2005
429 REL 16 SOW Fishpro, Inc. 1983-350-05 CONSTRUCTION MANAGEMENT OF THE NEZ PERCE TRIBAL HATC Terminated $504,000 10/1/2000 - 9/30/2001
4504 SOW Nez Perce Tribe 1983-350-0 NEZ PERCE TRIBAL HATCHERY - O & M History $7,964,254 1/1/2001 - 12/31/2006
Expense Contracts:
Number Contractor Name Title Status Total Contracted Amount Dates
331 REL 2 SOW Concannon, Kathleen A NEZ PERCE TRIBAL HATCHERY EIS History $5,000 9/30/1998 - 9/30/1999
456 REL 2 SOW Concannon, Kathleen A T/O17362 W/E SERVICES:NEZ PERCE TRIBAL HATCHERY PROJECT History $1,325 10/1/1998 - 12/31/2000
390 REL 2 SOW Fishpro, Inc. 1983-350-01 NEZ PERCE TRIBE HATCHERY PROGRAM - DESIGN SERVICES Terminated $130,574 10/1/2000 - 12/31/2001
3114 REL 1 SOW Nez Perce Tribe 1983-350-00 NEZ PERCE TRIBAL HATCHERY - PLANNING & DESIGN Terminated $477,948 10/1/2000 - 12/31/2001
BPA-011032 Bonneville Power Administration FY01 land acquisition Active $63,440 10/1/2000 - 9/30/2001
4035 SOW Nez Perce Tribe 1983-350-00 NEZ PERCE TRIBAL HATCHERY - PLANNING & DESIGN History $622,757 3/20/2001 - 3/31/2005
4278 SOW Fishpro, Inc. 1983-350-01 NEZ PERCE TRIBAL HATCHERY - FINAL DESIGN Closed $42,973 4/2/2001 - 12/31/2002
429 REL 19 SOW Fishpro, Inc. 1983-350-05 CONSTRUCTION MANAAGEMENT OF THE NEZ PERCE TRIBAL HATC Closed $524,363 8/14/2001 - 12/31/2003
20668 SOW Nez Perce Tribe 1983 350 00 NP TRIBAL HATCHERY O&M History $1,641,326 1/1/2005 - 12/31/2005
25513 SOW Nez Perce Tribe 1983 350 00 NEZ PERCE HATCHERY O & M History $1,820,480 1/1/2006 - 12/31/2006
30513 SOW Nez Perce Tribe 1983 350 00 NEZ PERCE HATCHERY O & M History $1,936,708 1/1/2007 - 12/31/2007
36059 SOW Nez Perce Tribe 198335000 EXP NPTH O/M History $2,032,187 1/1/2008 - 12/31/2008
40151 SOW Nez Perce Tribe 198335000 EXP NPTH O&M History $2,027,782 1/1/2009 - 12/31/2009
45237 SOW Nez Perce Tribe 198335000 EXP NPTH O&M Closed $2,082,567 1/1/2010 - 12/31/2010
50764 SOW Nez Perce Tribe 1983-350-00 EXP NPTH O&M Closed $2,122,540 1/1/2011 - 12/31/2011
55489 SOW Nez Perce Tribe 1983-350-00 EXP NPTH O&M Closed $2,138,147 1/1/2012 - 12/31/2012
60242 SOW Nez Perce Tribe 1983-350-00 EXP NPTH O&M Closed $2,120,970 1/1/2013 - 12/31/2013
63480 SOW Nez Perce Tribe 1983-350-00 EXP NPTH O&M Closed $2,134,958 1/1/2014 - 12/31/2014
67318 SOW Nez Perce Tribe 1983-350-00 EXP NPTH O&M Closed $2,155,377 1/1/2015 - 12/31/2015
71275 SOW Nez Perce Tribe 1983-350-00 EXP NEZ PERCE TRIBAL HATCHERY O&M Closed $2,209,256 1/1/2016 - 12/31/2016
75325 SOW Nez Perce Tribe 1983-350-00 EXP NEZ PERCE TRIBAL HATCHERY O&M Closed $2,236,624 1/1/2017 - 12/31/2017
74017 REL 17 SOW Nez Perce Tribe 1983-350-00 EXP NEZ PERCE TRIBAL HATCHERY O&M Closed $2,214,288 1/1/2018 - 12/31/2018
74017 REL 35 SOW Nez Perce Tribe 1983-350-00 EXP NEZ PERCE TRIBAL HATCHERY O&M Closed $1,959,647 1/1/2019 - 3/31/2020
80508 SOW Clearwater Power Co FY19 Nez Perce Tribal Hatchery Closed $115,362 1/1/2019 - 12/31/2019
74017 REL 60 SOW Nez Perce Tribe 1983-350-00 EXP NEZ PERCE TRIBAL HATCHERY O&M Closed $1,994,275 1/1/2020 - 12/31/2020
83456 SOW Clearwater Power Co 1983-350-00 FY20 METER NEZ PERCE TRIBAL HATCHERY Closed $179,192 1/1/2020 - 12/31/2020
84158 SOW Bio-Oregon, Inc. 1983-350-00 EXP FISH FEED PURCHASING Closed $200,420 1/1/2020 - 1/31/2022
74017 REL 77 SOW Nez Perce Tribe 1983-350-00 EXP NEZ PERCE TRIBAL HATCHERY O&M Closed $1,952,346 1/1/2021 - 12/31/2021
85909 SOW Clearwater Power Co 1983-350-00 FY21 METER NEZ PERCE TRIBAL HATCHERY Closed $192,035 1/1/2021 - 12/31/2021
74017 REL 92 SOW Nez Perce Tribe 1983-350-00 EXP NEZ PERCE TRIBAL HATCHERY (O&M) Closed $2,300,599 1/1/2022 - 12/31/2022
88774 SOW Clearwater Power Co 1983-350-00 FY22 METER NEZ PERCE TRIBAL HATCHERY Closed $175,927 1/1/2022 - 12/31/2022
90328 SOW Bio-Oregon, Inc. 1983-350-00 EXP NPTH FISH FEED PURCHASE Complete $12,421 6/1/2022 - 12/31/2022
84044 REL 9 SOW Nez Perce Tribe 1983-350-00 EXP NEZ PERCE TRIBAL HATCHERY O&M Issued $2,218,641 1/1/2023 - 12/31/2023
90766 SOW Clearwater Power Co 1983-350-00 NEZ PERCE TRIBAL HATCHERY FY23 METER Closed $180,000 1/1/2023 - 12/31/2023
91206 SOW Clearwater Power Co 1983-350-00 FY23 METER NEZ PERCE TRIBAL HATCHERY Closed $0 1/1/2023 - 12/31/2023
91696 SOW Bio-Oregon, Inc. 1983-350-00 EXP NPTH CY23 FISH FEED PURCHASE Closed $87,525 1/10/2023 - 4/30/2023
84044 REL 31 SOW Nez Perce Tribe 1983-350-00 EXP NEZ PERCE TRIBAL HATCHERY O&M Issued $2,034,255 1/1/2024 - 12/31/2024
93535 SOW Clearwater Power Co 1983-350-00 NEZ PERCE TRIBAL HATCHERY FY24 METER Issued $180,000 1/1/2024 - 12/31/2024
93019 REL 4 SOW Bio-Oregon, Inc. 1983-350-00 EXP NPTH CY24 FISH FEED PURCHASE Closed $97,368 1/24/2024 - 6/30/2024



Annual Progress Reports
Expected (since FY2004):33
Completed:20
On time:20
Status Reports
Completed:78
On time:47
Avg Days Late:1

                Count of Contract Deliverables
Earliest Contract Subsequent Contracts Title Contractor Earliest Start Latest End Latest Status Accepted Reports Complete Green Yellow Red Total % Green and Complete Canceled
BPA-11032 FY01 land acquisition Bonneville Power Administration 10/01/2000 09/30/2001 Active 0 0 0 0 0 0 0
4504 20668, 25513, 30513, 36059, 40151, 45237, 50764, 55489, 60242, 63480, 67318, 71275, 75325, 74017 REL 17, 74017 REL 35, 74017 REL 60, 74017 REL 77, 74017 REL 92, 84044 REL 9, 84044 REL 31, 84044 REL 53 2025-003-00 EXP NPT ARTIFICIAL PRODUCTION O&M Nez Perce Tribe 01/01/2001 12/31/2025 Signature 78 261 13 0 17 291 94.16% 1
Project Totals 78 261 13 0 17 291 94.16% 1


The table content is updated frequently and thus contains more recent information than what was in the original proposal reviewed by ISRP and Council.

Review: 2022 Anadromous Fish Habitat & Hatchery Review

Council Recommendation

Assessment Number: 1983-350-00-NPCC-20230309
Project: 1983-350-00 - Nez Perce Tribal Hatchery Operations and Maintenance (O&M)
Review: 2022 Anadromous Fish Habitat & Hatchery Review
Approved Date: 4/15/2022
Recommendation: Implement with Conditions
Comments: Bonneville and Sponsor to consider condition #1 (goals) and #2 (objectives/timeline), and address in project documentation if appropriate. This project supports hatchery mitigation authorized under the Northwest Power Act (Council’s Fish and Wildlife Program) for the Nez Perce Tribal Hatchery and reconditioned steelhead kelt programs. See Policy Issue I.b., II.a. and II.b.

[Background: See https://www.nwcouncil.org/2021-2022-anadromous-habitat-and-hatchery-review/]

Independent Scientific Review Panel Assessment

Assessment Number: 1983-350-00-ISRP-20230324
Project: 1983-350-00 - Nez Perce Tribal Hatchery Operations and Maintenance (O&M)
Review: 2022 Anadromous Fish Habitat & Hatchery Review
Completed Date: None
Documentation Links:
Review: RME / AP Category Review

Council Recommendation

Assessment Number: 1983-350-00-NPCC-20110125
Project: 1983-350-00 - Nez Perce Tribal Hatchery Operations and Maintenance (O&M)
Review: RME / AP Category Review
Proposal: RMECAT-1983-350-00
Proposal State: Pending BPA Response
Approved Date: 6/10/2011
Recommendation: Fund (Qualified)
Comments: Implement with condition through 2016: Implementation subject to regional hatchery effects evaluation process described in programmatic recommendation #4.
Conditions:
Council Condition #1 Programmatic Issue: RMECAT #4 Hatchery Effectiveness—Subject to regional hatchery effects evaluation process

Independent Scientific Review Panel Assessment

Assessment Number: 1983-350-00-ISRP-20101015
Project: 1983-350-00 - Nez Perce Tribal Hatchery Operations and Maintenance (O&M)
Review: RME / AP Category Review
Proposal Number: RMECAT-1983-350-00
Completed Date: 12/17/2010
Final Round ISRP Date: 12/17/2010
Final Round ISRP Rating: Meets Scientific Review Criteria
Final Round ISRP Comment:
This meets criteria but also see comments on the M&E proposal 198335003.

Now that the program has shown that it can produce fall and spring Chinook that return to the Clearwater River as adults, perhaps it is time to begin to consider whether (and to what extent) the effort will yield self-sustaining runs of natural origin. The next iteration of the project needs to begin to address whether and how self-sustaining Clearwater River salmon runs will be achieved. Thus, while the NPT has done a good job in guiding the NPTH to this point, the ISRP’s longstanding concerns about the viability of the supplementation approach to rebuild self-sustaining natural reproduction in Idaho rives and streams remains unanswered.

1. Purpose, Significance to Regional Programs, Technical Background, and Objectives

The proponents do a good job of describing the history of the project and how it fits into regional Fish and Wildlife Program and AP planning. Technical background, along with the growth and evolution of the NPTH program is well described.

2. History: Accomplishments, Results, and Adaptive Management

Past ISRP concerns that project results were not being adequately described have been effectively dealt with by the very commendable January 2009 Orofino symposium. The current proposal summarizes material presented at the symposium but often provides inadequate narrative for those who did not have the opportunity to attend the symposium.

The proponents do a very good job of describing the project’s history and evolution, as well as to a lesser degree, how they went about solving unforeseen problems, mostly associated with low return of adults or with limited water supply. It is evident that the hatchery was built at a site having unsuitable water supply. The hatchery is reported to be operating better than in its first few years, however. Within the last year or so, production has increased to the point that objectives are being met or nearly so in terms of numbers of released fish.

One of the four or so apparent current “issues” with the project is whether the basic requirements for fish production are adequate at the NPTH facility. From the proposal it appears that ongoing improvements (of a wide variety) are adequate for the near future and that issue no longer exists.

Another issue is survival of juveniles immediately after release. It was mentioned at the symposium that results from tagging juveniles at Newsome Creek showed very high mortality by Lower Granite dam. It is important to understand relationships among fish size at release, time of movement from acclimation site, whether release is volitional or forced, and the habitat used by those fish as they overwinter. Granted, such monitoring should be (is?) done by another project (NPT M&E) but results need to be closely linked to this project so the best release strategies can be developed. Currently it does not appear that is receiving adequate attention.

Production goals for both spring and fall Chinook, in terms of numbers of juveniles leaving the various acclimation facilities, now seem close to being met. The obvious question now is whether those are the most appropriate production goals. Because the ultimate goal must be natural production, and the project duration is “until natural production in target streams can support exclusively the fishery management principles, goals and objectives listed above,” the key issue is whether the project is indeed moving toward that goal.

Objectives are not being met in terms of proportion of natural influence (PNI). The proportions of natural-origin adults in hatchery broodstocks (pNOB) are too low, and the proportions of hatchery-origin adults among naturally spawning fish (pHOS) are too high, therefore the PNI values are too low. For the ISRP to evaluate progress toward meeting PNI objectives, it would help for the proponents to provide the pNOB, pHOS, and PNI results for each year of hatchery operation.

SARs for the FCS and SCS components are roughly 0.1% and 0.3%, respectively. For natural production to be self-sustaining, SARs will have to increase by an order of magnitude. How can this be achieved? The next iteration of the project should start to address these issues and describe a plan for achieving them, otherwise, there will never be a termination date for the artificial production efforts on this project and the ultimate goals will never be achieved.

3. Project Relationships, Emerging Limiting Factors, and Tailored Questions for Type of Work (Hatchery, RME, Tagging)

Adequately described.


4. Deliverables, Work Elements, Metrics, and Methods

Adequately described.
First Round ISRP Date: 10/18/2010
First Round ISRP Rating: Meets Scientific Review Criteria
First Round ISRP Comment:

This meets criteria but also see comments on the M&E proposal 198335003. Now that the program has shown that it can produce fall and spring Chinook that return to the Clearwater River as adults, perhaps it is time to begin to consider whether (and to what extent) the effort will yield self-sustaining runs of natural origin. The next iteration of the project needs to begin to address whether and how self-sustaining Clearwater River salmon runs will be achieved. Thus, while the NPT has done a good job in guiding the NPTH to this point, the ISRP’s longstanding concerns about the viability of the supplementation approach to rebuild self-sustaining natural reproduction in Idaho rives and streams remains unanswered. 1. Purpose, Significance to Regional Programs, Technical Background, and Objectives The proponents do a good job of describing the history of the project and how it fits into regional Fish and Wildlife Program and AP planning. Technical background, along with the growth and evolution of the NPTH program is well described. 2. History: Accomplishments, Results, and Adaptive Management Past ISRP concerns that project results were not being adequately described have been effectively dealt with by the very commendable January 2009 Orofino symposium. The current proposal summarizes material presented at the symposium but often provides inadequate narrative for those who did not have the opportunity to attend the symposium. The proponents do a very good job of describing the project’s history and evolution, as well as to a lesser degree, how they went about solving unforeseen problems, mostly associated with low return of adults or with limited water supply. It is evident that the hatchery was built at a site having unsuitable water supply. The hatchery is reported to be operating better than in its first few years, however. Within the last year or so, production has increased to the point that objectives are being met or nearly so in terms of numbers of released fish. One of the four or so apparent current “issues” with the project is whether the basic requirements for fish production are adequate at the NPTH facility. From the proposal it appears that ongoing improvements (of a wide variety) are adequate for the near future and that issue no longer exists. Another issue is survival of juveniles immediately after release. It was mentioned at the symposium that results from tagging juveniles at Newsome Creek showed very high mortality by Lower Granite dam. It is important to understand relationships among fish size at release, time of movement from acclimation site, whether release is volitional or forced, and the habitat used by those fish as they overwinter. Granted, such monitoring should be (is?) done by another project (NPT M&E) but results need to be closely linked to this project so the best release strategies can be developed. Currently it does not appear that is receiving adequate attention. Production goals for both spring and fall Chinook, in terms of numbers of juveniles leaving the various acclimation facilities, now seem close to being met. The obvious question now is whether those are the most appropriate production goals. Because the ultimate goal must be natural production, and the project duration is “until natural production in target streams can support exclusively the fishery management principles, goals and objectives listed above,” the key issue is whether the project is indeed moving toward that goal. Objectives are not being met in terms of proportion of natural influence (PNI). The proportions of natural-origin adults in hatchery broodstocks (pNOB) are too low, and the proportions of hatchery-origin adults among naturally spawning fish (pHOS) are too high, therefore the PNI values are too low. For the ISRP to evaluate progress toward meeting PNI objectives, it would help for the proponents to provide the pNOB, pHOS, and PNI results for each year of hatchery operation. SARs for the FCS and SCS components are roughly 0.1% and 0.3%, respectively. For natural production to be self-sustaining, SARs will have to increase by an order of magnitude. How can this be achieved? The next iteration of the project should start to address these issues and describe a plan for achieving them, otherwise, there will never be a termination date for the artificial production efforts on this project and the ultimate goals will never be achieved. 3. Project Relationships, Emerging Limiting Factors, and Tailored Questions for Type of Work (Hatchery, RME, Tagging) Adequately described. 4. Deliverables, Work Elements, Metrics, and Methods Adequately described.

Documentation Links:

2008 FCRPS BiOp Workgroup Assessment

Assessment Number: 1983-350-00-BIOP-20101105
Project Number: 1983-350-00
Review: RME / AP Category Review
Proposal Number: RMECAT-1983-350-00
Completed Date: None
2008 FCRPS BiOp Workgroup Rating: Supports 2008 FCRPS BiOp
Comments: BiOp Workgroup Comments: No BiOp Workgoup comments

The BiOp RM&E Workgroups made the following determinations regarding the proposal's ability or need to support BiOp Research, Monitoring and Evaluation (RME) RPAs. If you have questions regarding these RPA association conclusions, please contact your BPA COTR and they will help clarify, or they will arrange further discussion with the appropriate RM&E Workgroup Leads. BiOp RPA associations for the proposed work are: ()
All Questionable RPA Associations () and
All Deleted RPA Associations (50.6 50.7 62.4 62.5 64.2 )
Proponent Response:
Review: FY07-09 Solicitation Review

Council Recommendation

Assessment Number: 1983-350-00-NPCC-20090924
Project: 1983-350-00 - Nez Perce Tribal Hatchery Operations and Maintenance (O&M)
Review: FY07-09 Solicitation Review
Approved Date: 10/23/2006
Recommendation: Fund
Comments: Flat line '07 requested amount - this level was reflected in the Step 3 NPTH decision (May 17, 2000). Other associated life histories (coho) not prioritized.

Independent Scientific Review Panel Assessment

Assessment Number: 1983-350-00-ISRP-20060831
Project: 1983-350-00 - Nez Perce Tribal Hatchery Operations and Maintenance (O&M)
Review: FY07-09 Solicitation Review
Completed Date: 8/31/2006
Final Round ISRP Date: None
Final Round ISRP Rating: Meets Scientific Review Criteria
Final Round ISRP Comment:
While the ISRP recommends the project as fundable, the ISRP also expects the sponsors to do a better job of reporting results in their future proposals. The Project History reports only actions performed, e.g., the planning and creation of the hatchery, and numbers of fish of different sorts stocked each year since releases began in 2003. Adult return rates cannot yet be reported, of course, but it would be helpful to have information for each released group on egg-to-smolt survival and on smolt survival to points downstream. Reasons for variation in such results should be discussed, including comparison with literature values.

In their response, the sponsors provided additional data and explanations, and these seem adequate; however, in future review cycles, sponsors could do a better job of following the topical outline for proposals.
Documentation Links:

Legal Assessment (In-Lieu)

Assessment Number: 1983-350-00-INLIEU-20090521
Project Number: 1983-350-00
Review: FY07-09 Solicitation Review
Completed Date: 10/6/2006
In Lieu Rating: No Problems Exist
Cost Share Rating: None
Comment: O&M for BPA-funded hatchery mitigating for FCRPS.

Capital Assessment

Assessment Number: 1983-350-00-CAPITAL-20090618
Project Number: 1983-350-00
Review: FY07-09 Solicitation Review
Completed Date: 2/27/2007
Capital Rating: Does Not Qualify for Capital Funding
Capital Asset Category: None
Comment: None

Project Relationships: This project Merged To 2025-003-00 effective on 10/1/2024
Relationship Description: Work and budgets from projects: 1983-350-00 NPT Hatchery O&M, 1996-043-00 Johnson Creek Artificial Prop. O&M, and 1998-007-02 Grand Ronde Supplementation O&M are merging to become project 2025-003-00.


Name Role Organization
Rebecca Johnson Supervisor Nez Perce Tribe
Jay Hesse Interested Party Nez Perce Tribe
Sherman Sprague Interested Party Nez Perce Tribe
Bill Arnsberg Interested Party Nez Perce Tribe
Carl East Project Lead Nez Perce Tribe
Peter Lofy Supervisor Bonneville Power Administration
Scott Kellar Project Lead Nez Perce Tribe
Andrew Traylor Interested Party Bonneville Power Administration
Brian McIlraith Project Manager Bonneville Power Administration
Lindsey Arotin Env. Compliance Lead Bonneville Power Administration