Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 67318: 1983-350-00 EXP NPTH O&M
Project Number:
Title:
Nez Perce Tribal Hatchery Operations and Maintenance (O&M)
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Mountain Snake Clearwater 100.00%
Contract Number:
67318
Contract Title:
1983-350-00 EXP NPTH O&M
Contract Continuation:
Previous: Next:
63480: 1983-350-00 EXP NPTH O&M
  • 71275: 1983-350-00 EXP NEZ PERCE TRIBAL HATCHERY O&M
Contract Status:
Closed
Contract Description:
AUTHORIZATION:

The Northwest Power Planning Council (NPPC) authorized construction of Nez Perce Tribal Hatchery Complex (NPTHC) facilities 17, May 2000.  Construction began July 2001 and was essentially completed in October 2002.  The hatchery was dedicated 9, October 2002.  Spring and fall Chinook salmon eggs were brought on-station for incubation in October, and all systems appeared to be functioning.  

This statement of work and budget contain activities and costs associated with the operation and maintenance of the Nez Perce Tribal Hatchery and six satellite facilities.  Based on NPPC authorization for out-year operation and maintenance costs we are requesting the following:

FY2014 O&M budget:  $2,155,377
  
2014 OBJECTIVES:  
NPTHC plans to release 1.4M FCS and 825,000 SCS into the Clearwater Subbasin.  To meet these objectives, ~962 adult FCS will be trapped at Lower Granite Dam and at the NPTH ladder.  Egg take goal for the FCS program is 1,800,000 green eggs.  ~458 adult SCS will be trapped at NPTH and may be trapped from Weirs on Lolo and Newsome Creeks, depending on returns.  Adults for the SCS program may also come from other hatcheries in the Clearwater Subbasin.  Egg take goal for the SCS program is 718,750 green eggs.

To summarize, the following numbers and groups of fish will be reared and/or released in 2014 through the NPTHC program.  

* 500,000 BY13 fall Chinook subyearlings at NPTH - released into Clearwater River
* 200,000 BY13 fall Chinook subyearlings at Cedar Flats Acclimation Facility - released into Selway River
* 200,000 BY13 fall Chinook subyearlings at Lukes Gulch Acclimation Facility - released into South Fork Clearwater River
*               500,000 BY13 fall Chinook subyearlings at North Lapwai Valley Acclimation Facility - released into Lapwai Creek

* 200,000 BY11 spring Chinook smolts at NPTH - released into Clearwater River (Early reared at IDFG's Clearwater Hatchery).
*   75,000 BY13 spring Chinook pre-smolts at Newsome Acclimation Facility - released into Newsome Creek  
* 150,000 BY13 spring Chinook pre-smolts at Yoosa/Camp Acclimation Facility - released into Lolo Creek
*               400,000 BY13 spring Chinook parr direct steam released the Selway River near the mouth of Meadow Creek
Account Type(s):
Expense
Contract Start Date:
01/01/2015
Contract End Date:
12/31/2015
Current Contract Value:
$2,155,377
Expenditures:
$2,155,377

* Expenditures data includes accruals and are based on data through 31-Oct-2024.

Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Joe Deherrera Bonneville Power Administration Yes COR jldeherrera@bpa.gov (503) 230-3442
Arleen Henry Nez Perce Tribe No Administrative Contact arleenh@nezperce.org (208) 621-3833
Rebecca Johnson Nez Perce Tribe Yes Supervisor beckyj@nezperce.org (208) 621-4629
Amber MacLachlan Bonneville Power Administration Yes Contracting Officer almcmahon@bpa.gov (503) 230-3983
Amy Mai Bonneville Power Administration Yes Env. Compliance Lead aemai@bpa.gov (503) 230-7349
Bruce McLeod Nez Perce Tribe No Interested Party brucem@nezperce.org (208) 843-7320x4628
Aaron Penney Nez Perce Tribe Yes Contract Manager aaronp@nezperce.org (208) 621-3504
Tod Sween Nez Perce Tribe No Technical Contact tods@nezperce.org (208) 621-3582
Dorothy Welch Bonneville Power Administration Yes F&W Approver dwwelch@bpa.gov (503) 230-5479
Tish Whitman Nez Perce Tribe Yes Administrative Contact tishw@nezperce.org (208) 843-7320


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Procurement of permits B: 165. Obtain Permits and submit copies to BPA NEPA group 12/31/2015 12/28/2015
Submit BiOp RPA Report in Taurus C: 202. BiOp RPA Report for CY 2014 03/15/2015
Project Administration D: 119. Manage and Administer Project 12/31/2015 12/28/2015
Attach Annual Operation Plan in Pisces E: 174. Submit Annual Operation Plan 10/31/2015
Progress Report has been published F: 132. Submit Progress Report for the period Jan 1, 2012- Dec 31, 2012 11/15/2015 11/23/2015
Progress Report has been published G: 132. Submit Progress Report for the period Jan 1, 2014 - Dec 31, 2014 12/31/2015
Progress Report has been published H: 132. Submit Progress Report for the period Jan 1, 2013 - Dec 31, 2013 06/30/2015
Regional Coordination I: 189. Coordinate Project Activities on a Regional Basis 12/31/2015 12/28/2015
Facility & Equipment Maintenance J: 61. NPTHC Facility Maintenance 12/31/2015 12/28/2015
Salmon Production - BY13 Spring Chinook K: 176. Salmon Production - BY13 Spring Chinook 04/30/2015 03/30/2015
Salmon Production - BY14 Spring Chinook L: 176. Salmon Production - BY14 Spring Chinook 10/31/2015 10/31/2015
Salmon Production - BY15 Spring Chinook M: 176. Salmon Production - BY15 Spring Chinook 12/31/2015 12/28/2015
Salmon Production - BY14 Fall Chinook N: 176. Salmon Production - BY14 Fall Chinook 06/30/2015 06/04/2015
Salmon Production - BY15 Fall Chinook O: 176. Salmon Production - BY15 Fall Chinook 12/31/2015 12/28/2015
Education/Outreach P: 99. Conduct Outreach and Public Education 12/31/2015 12/28/2015
Submit monthly reports Q: 141. Monthly reports for comanagers and BPA 12/31/2015 12/28/2015
Document lamprey holding activities (funded by non-BPA funds) R: 66. Hold Lamprey 12/31/2015 12/28/2015

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Snake River Fall ESU (Threatened)
  • 2 instances of WE 176 Produce Hatchery Fish
  • 1 instance of WE 61 Maintain Artificial Production Facility/Infrastructure
  • 1 instance of WE 174 Produce Plan
Chinook (O. tshawytscha) - Snake River Spring/Summer (not listed)
  • 3 instances of WE 176 Produce Hatchery Fish
  • 1 instance of WE 61 Maintain Artificial Production Facility/Infrastructure
  • 1 instance of WE 174 Produce Plan
Lamprey, Pacific (Entosphenus tridentata)
  • 1 instance of WE 66 Trap/Collect/Hold/Transport Fish - Hatchery

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 01/01/2015
B 165 Obtain Permits and submit copies to BPA NEPA group 01/01/2015
C 202 BiOp RPA Report for CY 2014
D 119 Manage and Administer Project 01/01/2015
E 174 Submit Annual Operation Plan 01/01/2015
F 132 Submit Progress Report for the period Jan 1, 2012- Dec 31, 2012 01/01/2015
G 132 Submit Progress Report for the period Jan 1, 2014 - Dec 31, 2014 01/01/2015
H 132 Submit Progress Report for the period Jan 1, 2013 - Dec 31, 2013 01/01/2015
I 189 Coordinate Project Activities on a Regional Basis 01/01/2015
J 61 NPTHC Facility Maintenance
K 176 Salmon Production - BY13 Spring Chinook 01/01/2015
L 176 Salmon Production - BY14 Spring Chinook 01/01/2015
M 176 Salmon Production - BY15 Spring Chinook 01/01/2015
N 176 Salmon Production - BY14 Fall Chinook 01/01/2015
O 176 Salmon Production - BY15 Fall Chinook 01/01/2015
P 99 Conduct Outreach and Public Education 01/01/2015
Q 141 Monthly reports for comanagers and BPA 01/01/2015
R 66 Hold Lamprey 01/01/2015