Contract 74017 REL 81: 2010-003-00 EXP LOWER SOUTH FORK CLEARWATER RIVER WATERSHED
Project Number:
Title:
Lower South Fork Clearwater/Slate Creek Watershed Restoration
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Mountain Snake Clearwater 100.00%
Contract Number:
74017 REL 81
Contract Title:
2010-003-00 EXP LOWER SOUTH FORK CLEARWATER RIVER WATERSHED
Contract Continuation:
Previous: Next:
74017 REL 65: 2010-003-00 EXP LOWER SOUTH FORK CLEARWATER RIVER WATERSHED
  • 74017 REL 99: 2010-003-00 EXP LOWER SOUTH FORK CLEARWATER RIVER WATERSHED
Contract Status:
Closed
Contract Description:
Contract History:

This project is implemented as part of the Nez Perce-Clearwater National Forests (NPCNF)/Nez Perce Tribe (NPT) restoration partnership.  This project represents a merger of two Bonneville Power Administration (BPA) and NPT restoration projects, Slate Creek Watershed Restoration (2007-064-00)  and Lower South Fork Clearwater Restoration (2010-003-00).  The restoration partnership has been ongoing in the basin since 1996 and this project unification greatly increases the geographic area covered, and enhances the administrative and financial efficiency in order to maximize the direct benefit to fish and wildlife.

The goal of the project is to restore the physical and biological characteristics of the watershed to provide quality habitat for anadromous and resident fish species that support the historical, cultural, and economic practices of the Nez Perce Tribe.  The South Fork Clearwater River/Slate Creek watersheds contain designated critical habitat for Snake River steelhead trout, bull trout, and has moderate habitat potential for Spring Chinook salmon.  Restoration follows a ridge top to ridge top approach with implementation focused on restoring riparian processes by addressing limiting factors described in recent Expert Panel workshops such as increased water temperatures, increased sedimentation, cattle grazing effects, aquatic habitat connectivity, and exotic, invasive plants.  Historically, the cost share for this project has been contributed by the NPCNF who provides at least a 20% match including cash and in-kind contributions for environmental compliance, contract preparation, administration, and technical oversight.  In recent years, the BLM has also become an active partner and has been and will also be submitting cost share contributions during FY 21.

In FY21, we will work in partnership with the USFS to install some PALS in Castle Creek to help create habitat features and allow the stream to access its natural floodplain.  Castle Creek was identified in the FY12 passage inventories conducted by the Nez Perce Tribe as a fish bearing stream with a passage barrier blocking access to habitat.  Culvert surveys at stream/ road crossings were inventoried to take an assessment of passage barriers, one of the primary limiting factors in the South Fork Clearwater River; the surveys determine failure risk and fish passage barriers using the U.S. Forest Service's 2003 "National inventory and assessment procedure for identifying barriers to aquatic organism passage at road-stream crossings" .  Castle Creek was identified as a fish bearing stream with a barrier at the Highway 14 crossing, which is in the queue to be replaced in the near future in partnership with the USFS and ITD. Environmental DNA samples taken in 2020 have confirmed target species are present in Castle Creek, further highlighting the need for restoration in this stream.  Upstream of the culvert lies quality fish habitat with a stretch of stream that has been altered for the neighboring Forest Service workstation.  Adding simple instream structures, BDAs and PALS, will help restore floodplain connectivity, streamflow regimes, and aggrade the incised channel to increase habitat diversity and population diversity, a primary effort of Action Agencies identified in the 2020 CRS Biological Assessment.  

In FY21 work also includes fence maintenance (to protect riparian plants), and continued planning and coordination for next year's projects and out-year habitat improvements.  Pit tag arrays will be installed to monitor fish passage through a suspected partial velocity barrier site in the South Fork Clearwater River in preparation for a potential velocity barrier removal project in partnership with the USFS in out years.  NPT Watershed personnel will also continue an inventory of stream crossings throughout the Lower South Fork Clearwater River watershed in order to identify and prioritize fish passage barriers and associated risks to aquatic species.  
Account Type(s):
Expense
Contract Start Date:
02/01/2021
Contract End Date:
01/31/2022
Current Contract Value:
$706,622
Expenditures:
$706,622

* Expenditures data includes accruals and are based on data through 31-Oct-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Release
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Marcie Carter Nez Perce Tribe Yes Supervisor marciec@nezperce.org (208) 621-3534
Miranda Gordon Nez Perce Tribe Yes Contract Manager mirandag@nezperce.org (208) 621-3547
Arleen Henry Nez Perce Tribe No Administrative Contact arleenh@nezperce.org (208) 621-3833
Eric Leitzinger Bonneville Power Administration Yes F&W Approver ejleitzinger@bpa.gov (503) 230-3534
Jennifer Lord Bonneville Power Administration Yes COR jklord@bpa.gov (503) 230-5192
Jennifer McKenna Bonneville Power Administration No CO Assistant jmmckenna@bpa.gov (503) 314-8915
Robert Shull Bonneville Power Administration Yes Env. Compliance Lead rwshull@bpa.gov (503) 230-3962
Emmit Taylor, Jr. Nez Perce Tribe No Supervisor emmitt@nezperce.org (208) 621-3544
Karen Wolfe Bonneville Power Administration Yes Contracting Officer ktwolfe@bpa.gov (503) 230-3448


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Environmental compliance documentation submitted to BPA B: 165. Provide environmental compliance information to BPA for projects 01/31/2022 01/31/2022
Manage BPA Contract C: 119. Management, Coordination, and Communication 01/31/2022 01/31/2022
Planning and coordination duties D: 191. Planning and Coordination 01/31/2022 01/31/2022
Pit tag arrays installed E: 70. Installation of pit tag arrays in the South Fork Clearwater River 11/30/2021 08/27/2021
PALS/ BDA structures installed F: 29. Increase floodplain complexity with the addition of PALS in Castle Creek 12/20/2021 08/06/2021
Exclosure Fence Maintained G: 186. Maintain Exclosure Fences - Mill Creek 07/31/2021 06/30/2021
Exclosure fence maintained H: 186. Maintain Exclosure Fences - McComas Meadows 07/31/2021 05/26/2021
Potential Passage Barrier Inventory I: 115. Assess and Inventory Potential Passage Barriers 01/31/2022 01/31/2022
Review proposed projects, including field data, photos, maps, and plans. J: 122. Review of Proposed Partner Actions 01/31/2022 01/31/2022
Upload 2021 Annual Report to Pisces K: 132. 2021 Annual Report - 2/1/2021 - 1/31/2022 01/31/2022 01/31/2022
Fence Replaced- Buck Meadows L: 40. Replace Fence - Buck Meadows 12/30/2021 11/12/2021
Floodplain Restoration Designs M: 175. South Fork Clearwater River Floodplain Restoration Designs 01/28/2022 01/20/2022

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Snake River Fall ESU (Threatened)
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
Chinook (O. tshawytscha) - Snake River Spring/Summer (not listed)
  • 2 instances of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 40 Install Fence
  • 1 instance of WE 115 Produce Inventory or Assessment
  • 1 instance of WE 175 Produce Design
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 2 instances of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 40 Install Fence
  • 1 instance of WE 115 Produce Inventory or Assessment
  • 1 instance of WE 175 Produce Design
  • 1 instance of WE 70 Install Fish Monitoring Equipment
Trout, Bull (S. confluentus) (Threatened)
  • 1 instance of WE 175 Produce Design

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA
B 165 Provide environmental compliance information to BPA for projects
C 119 Management, Coordination, and Communication
D 191 Planning and Coordination
E 70 Installation of pit tag arrays in the South Fork Clearwater River 05/28/2021
F 29 Increase floodplain complexity with the addition of PALS in Castle Creek 08/06/2021
G 186 Maintain Exclosure Fences - Mill Creek 10/28/2020
H 186 Maintain Exclosure Fences - McComas Meadows 10/28/2020
I 115 Assess and Inventory Potential Passage Barriers 10/28/2020
J 122 Review of Proposed Partner Actions
K 132 2021 Annual Report - 2/1/2021 - 1/31/2022
L 40 Replace Fence - Buck Meadows 08/24/2021
M 175 South Fork Clearwater River Floodplain Restoration Designs 05/28/2021