74313 REL 18: 1994-042-00 EXP TROUT CREEK OPERATION AND MAINTENANCE |
|
* Expenditures data includes accruals and are based on data through 30-Nov-2024.
Full Name | Organization | Write Permission | Contact Role | Work Phone | |
---|---|---|---|---|---|
Alan Hansen | Oregon Department of Fish and Wildlife | No | Interested Party | alan.s.hansen@odfw.oregon.gov | (503) 947-6134 |
Mike Harrington | Oregon Department of Fish and Wildlife | No | Supervisor | michael.r.harrington@coho2.dfw.state.or.us | (541) 388-6362 |
Kelly Hope | Bonneville Power Administration | Yes | Env. Compliance Lead | kahope@bpa.gov | (503) 230-4738 |
Tom Nelson | Oregon Department of Fish and Wildlife | Yes | Contract Manager | tom.nelson@state.or.us | (541) 923-7470 |
John Skidmore | Bonneville Power Administration | Yes | F&W Approver | jtskidmore@bpa.gov | (503) 230-5494 |
Jesse Wilson | Bonneville Power Administration | Yes | COR | jcwilson@bpa.gov | (503) 230-4506 |
Elham Zolmajd-Haghighi | Bonneville Power Administration | Yes | Contracting Officer | ezolmajd-haghighi@bpa.gov | (503) 230-7414 |
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Manage & Administer Project | A: 119. Manage & Administer Project | 01/31/2020 | 01/31/2020 | |
Environmental Compliance Complete and Best Management Practices Implemented | B: 165. Obtain Environmental Compliance | 01/31/2020 | 01/31/2020 | |
Viable Restoration Projects Developed To Assist In The Attainment Of Project Goal | C: 114. Habitat Restoration Project Development | 01/31/2020 | 01/31/2020 | |
Technical Assistance Provided | D: 122. Provide Technical Assistance & Input | 01/31/2020 | 01/31/2020 | |
Complete Final Design | E: 175. Trout and Opal Creek Confluence - Final Design | 01/31/2020 | ||
Enhanced fish passage for all life history stages | F: 184. Trout and Opal Creek Confluence - Replace Undersized Culverts | 01/31/2020 | ||
Completed channel construction | G: 30. Trout and Opal Creek Confluence - Realign to Historic Channels | 01/31/2020 | ||
Road Relocated | H: 33. Trout and Opal Creek Confluence - Relocate Road | 01/31/2020 | ||
Increase Complexity | I: 29. Trout and Opal Creek Confluence - Increase Habitat Complexity | 01/31/2020 | ||
Vegetation Planted | J: 47. Trout and Opal Creek Confluence - Plant Vegetation | 01/31/2020 | ||
Reduced abundance of Noxious Weeds while promoting native vegetation in and along project areas within Trout Creek | K: 198. Establishment of a self sustaining native mix of tress shrubs grasses and forbs within project areas. | 01/31/2020 | 01/31/2020 | |
Promote native vegetation in and along project areas within Trout Creek | L: 199. Remove encroaching juniper trees from riparian exclosures to promote native tree and shrub density | 01/31/2020 | 01/31/2020 | |
Monitor Trout Creek Basin Riparian Exclosures | M: 26. Monitor Exclosures | 01/31/2020 | 01/31/2020 | |
Maintained Fences & Water Gaps | N: 186. Maintain Riparian Corridor Fence | 01/31/2020 | 01/31/2020 | |
Repaired/Maintained Off Channel Water Development Sites | O: 186. Repair/Maintain Off Channel Water Development Sites | 01/31/2020 | 01/31/2020 | |
Maintained Instream and Floodplain Structures | P: 186. Maintain Instream and Floodplain Structures | 01/31/2020 | 01/31/2020 | |
Monitor past channel realignment instream design work and floodplain shaping actions. | Q: 157. Monitor past channel realignment and floodplain restoration work to refine future habitat design | 01/31/2020 | 01/31/2020 | |
Stream Water Temperature and Ground Water Levels Monitored | R: 157. Monitor Stream Water In The Trout Creek Basin | 01/31/2020 | 01/31/2020 | |
Basin Wide Redd Counts | S: 157. Adult Steelhead Redd Counts | 01/31/2020 | 01/31/2020 | |
Data Captured In Two Data Bases (One For Adults & One For Juveniles) | T: 157. Monitor Smolt Production & Adult Escapement | 01/31/2020 | 01/31/2020 | |
Summer Steelhead Smolts PIT Tagged | U: 158. PIT Tag Out-Migrant Summer Steelhead Smolts | 09/30/2019 | 09/09/2019 | |
PIT Tag Data Submitted To PTAGIS | V: 159. Submit & Acquire PIT Tag Data To/From PTAGIS | 01/31/2020 | 01/31/2020 | |
ESA Listed Mid Columbia Summer Steelhead Monitored | W: 162. Analyze Adult Summer Steelhead Escapement & Summer Steelhead Smolt Out-Migrant Estimates | 01/31/2020 | 01/31/2020 | |
Final annual report for calendar year 2017 | Y: 132. Produce Annual report for 1/1/2018 to 12/31/2018 | 10/11/2019 | 10/11/2019 |
Primary Focal Species | Work Statement Elements |
---|---|
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened) |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 119 | Manage & Administer Project | 02/01/2019 | ||||||
B | 165 | Obtain Environmental Compliance | 02/01/2019 | ||||||
C | 114 | Habitat Restoration Project Development | 02/01/2019 | ||||||
D | 122 | Provide Technical Assistance & Input | 02/01/2019 | ||||||
E | 175 | Trout and Opal Creek Confluence - Final Design | |||||||
F | 184 | Trout and Opal Creek Confluence - Replace Undersized Culverts | |||||||
G | 30 | Trout and Opal Creek Confluence - Realign to Historic Channels | |||||||
H | 33 | Trout and Opal Creek Confluence - Relocate Road | |||||||
I | 29 | Trout and Opal Creek Confluence - Increase Habitat Complexity | |||||||
J | 47 | Trout and Opal Creek Confluence - Plant Vegetation | |||||||
K | 198 | Establishment of a self sustaining native mix of tress shrubs grasses and forbs within project areas. | |||||||
L | 199 | Remove encroaching juniper trees from riparian exclosures to promote native tree and shrub density | |||||||
M | 26 | Monitor Exclosures | 02/01/2019 | ||||||
N | 186 | Maintain Riparian Corridor Fence | 02/01/2019 | ||||||
O | 186 | Repair/Maintain Off Channel Water Development Sites | 02/01/2019 | ||||||
P | 186 | Maintain Instream and Floodplain Structures | 02/01/2019 | ||||||
Q | 157 | Monitor past channel realignment and floodplain restoration work to refine future habitat design | 02/01/2019 | ||||||
R | 157 | Monitor Stream Water In The Trout Creek Basin | |||||||
S | 157 | Adult Steelhead Redd Counts | |||||||
T | 157 | Monitor Smolt Production & Adult Escapement | |||||||
U | 158 | PIT Tag Out-Migrant Summer Steelhead Smolts | |||||||
V | 159 | Submit & Acquire PIT Tag Data To/From PTAGIS | 02/01/2019 | ||||||
W | 162 | Analyze Adult Summer Steelhead Escapement & Summer Steelhead Smolt Out-Migrant Estimates | 02/01/2019 | ||||||
X | 185 | Periodic Status Reports for BPA | 02/01/2019 | ||||||