Province | Subbasin | % |
---|---|---|
Columbia Plateau | Yakima | 100.00% |
Previous: | Next: |
---|---|
74314 REL 103: 1992-009-00 EXP YAKIMA PH II O&M |
|
* Expenditures data includes accruals and are based on data through 31-Oct-2024.
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Documentation and Assistance to Support BPA's Environmental Compliance Group | A: 165. Obtain EC Coverage for O&M Activities | 06/30/2022 | 06/30/2022 | |
Properly Functioning Yakima & Walla Walla Phase II Fish Protection Facilities | B: 186. Maintain Yakima Phase II & Walla Walla Basin Fish Protection Facilities | 06/30/2022 | 06/30/2022 | |
Provide Technical Input to O&M Issues | C: 122. Participation in Annual Work Plan and Project TWG Meetings | 02/28/2022 | 02/09/2022 | |
Provide Technical Input to Development of Gleed Fixes | D: 122. Represent WDFW Interests in Developing Gleed Passage Facility Fixes | 06/30/2022 | 06/30/2022 | |
Completed Annual Report | F: 132. Submit Annual Report for the Period 7/2020 to 6/2021 | 04/01/2022 | 05/25/2022 | |
Effective implementation management and timely contract administration | G: 119. Manage and Administer Project | 06/30/2022 | 06/30/2022 |
Primary Focal Species | Work Statement Elements |
---|---|
Chinook (O. tshawytscha) - Lower Columbia River ESU (Threatened) |
|
Chinook (O. tshawytscha) - Mid-Columbia River Spring ESU |
|
Coho (Oncorhynchus kisutch) - Lower Columbia River ESU (Threatened) |
|
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened) |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 165 | Obtain EC Coverage for O&M Activities | |||||||
B | 186 | Maintain Yakima Phase II & Walla Walla Basin Fish Protection Facilities | |||||||
C | 122 | Participation in Annual Work Plan and Project TWG Meetings | |||||||
D | 122 | Represent WDFW Interests in Developing Gleed Passage Facility Fixes | |||||||
E | 185 | Periodic Status Reports for BPA | |||||||
F | 132 | Submit Annual Report for the Period 7/2020 to 6/2021 | |||||||
G | 119 | Manage and Administer Project |