Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 74314 REL 99: 1992-009-00 EXP DELAYED SCREEN O&M - WDFW
Project Number:
Title:
Yakima Phase II Fish Screens Operations and Maintenance (O&M) with Washington Department of Fish and Wildlife (WDFW)
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Plateau Yakima 100.00%
Contract Number:
74314 REL 99
Contract Title:
1992-009-00 EXP DELAYED SCREEN O&M - WDFW
Contract Continuation:
Previous: Next:
74314 REL 76: 1992-009-00 EXP YAKIMA PH II O&M
Contract Status:
Closed
Contract Description:
Washington Department of Fish and Wildlife (WDFW) will perform a variety of tasks associated with fish screen improvements at Phase II and Fund Swap screening facilities throughout eastern Washington.  The following description provides an overview of what work will be done and approximately how much money is allocated per task.

WDFW will construct six drum screens compliant with federal and state screening criteria.  These screens will provide flexibility for WDFW to respond to issues with existing screens and better protect fish life.  The new drum screen inventory will be installed at other sites as needed.

Two of the six drum screens will be installed at the Kelly/Lowry site in the spring 2021 before irrigation season starts, in the dry.

WDFW will hire a subcontractor to refurbish 16 Phase II and Fund Swap screen facility gantry structures.  This entails removing the gantries (metal structures used to lift and place drum screens), recoating them with protective paint or plascoat, and reinstalling.  It will dramatically prolong the life of these structures and help prolong the screens as well via easier lifting to protect them from damage outside of irrigation season.  WDFW will also purchase capital equipment in the form a John Deere 50G mini excavator and a backpack lamprey specific shocker.

When the Phase II and Fund Swap fish screens were originally constructed from the early 1990's though the early 2000's, computers were either not present or relatively new to WDFW staff therefore records are all in hard copy.  This task funds WDFW staff to compile site summary sheets in electronic form that will provide a wide variety of information about each screen site such as year built, design flow, location, last refurbishment action, compliance status, and many more site details in table format.  These site summaries will be attached to the Phase II 2019-2020 annual report as an appendix and will be working documents updated as change occurs.  The appendix will continue to appear in annual reports each year.

The next four tasks, WE's F- I are project scoping and conceptual designs for screen facilities with known issues.  The Snipes/Allen bypass, Buttermilk head structure, Skyline forebay, and Chewuch control spill channel all perform sub-optimally and could use an upgrade.  This task focuses on identifying the next course of action and assuring its feasibility.

The final task is the purchase of new compliant screening panels for the Naches/Selah fish screen site.  These panels will be purchased via competitive bid process and arrive at the Yakima Construction Shop (YCS) pre-assembled.  After irrigation season in 2020 YCS staff will remove the old panels and install the new ones.

The remainder of the contract value is taken up with status reports, communication, and other budget tracking and contract tasks via FTE time.
Account Type(s):
Expense
Contract Start Date:
04/01/2020
Contract End Date:
09/30/2021
Current Contract Value:
$1,311,948
Expenditures:
$1,311,948

* Expenditures data includes accruals and are based on data through 31-Oct-2024.

BPA COR:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Release
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Documentation and Assistance to Support BPA's Environmental Compliance Group A: 165. Obtain EC Coverage for O&M Activities 06/30/2020 06/30/2020
Construct 6 Drum Screens B: 186. Construct 6 Drum Screens 09/30/2021 09/27/2021
Install 2 Drum Screens C: 69. Install 2 Drum Screens 03/31/2021 03/31/2021
Refurbish 16 Gantries and Equipment Purchased/Received D: 186. Refurbish 16 Gantries 03/31/2021 11/13/2020
Fish screen site summaries E: 174. Update Screen Records 09/30/2021 09/30/2021
Survey Evaluations and Conceptual Designs F: 175. Survey Evaluation/Produce Conceptual Designs - Snipes & Allen Bypass 09/30/2021 09/30/2021
Survey Evaluations and Conceptual Designs G: 175. Survey Evaluation/Produce Conceptual Designs - Buttermilk Head Structure 09/30/2021 09/30/2021
Survey Evaluations and Conceptual Designs H: 175. Survey Evaluation/Produce Conceptual Designs - Skyline Bypass 09/30/2021 09/30/2021
Survey Evaluations and Conceptual Designs I: 175. Survey Evaluation/Produce Conceptual Designs - Chewuck Control Spillway 09/30/2021 09/30/2021
Install compliant profile bar screen panels J: 69. Screen Replacement 03/31/2021 03/31/2021
Effective implementation management and timely contract administration M: 119. Manage and Administer Project 09/30/2021 09/30/2021

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (Oncorhynchus tshawytscha) - All Populations
  • 2 instances of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 2 instances of WE 69 Install Fish Screen
  • 1 instance of WE 174 Produce Plan
  • 4 instances of WE 175 Produce Design
Coho (O. kisutch) - Unspecified Population
  • 2 instances of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 2 instances of WE 69 Install Fish Screen
  • 1 instance of WE 174 Produce Plan
  • 4 instances of WE 175 Produce Design
Steelhead (Oncorhynchus mykiss) - All Populations
  • 2 instances of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 2 instances of WE 69 Install Fish Screen
  • 1 instance of WE 174 Produce Plan
  • 4 instances of WE 175 Produce Design

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Obtain EC Coverage for O&M Activities
B 186 Construct 6 Drum Screens 03/31/2020
C 69 Install 2 Drum Screens 03/31/2020
D 186 Refurbish 16 Gantries
E 174 Update Screen Records
F 175 Survey Evaluation/Produce Conceptual Designs - Snipes & Allen Bypass
G 175 Survey Evaluation/Produce Conceptual Designs - Buttermilk Head Structure
H 175 Survey Evaluation/Produce Conceptual Designs - Skyline Bypass
I 175 Survey Evaluation/Produce Conceptual Designs - Chewuck Control Spillway
J 69 Screen Replacement
K 185 Periodic Status Reports for BPA
L 132 No Annual Report
M 119 Manage and Administer Project