Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 74469: 2002-011-00 EXP KOOTENAI RIVER OPS MITIGATION & EVALUATION
Project Number:
Title:
Kootenai River Floodplain Ecosystem Operational Loss Assessment, Protection, Mitigation and Rehabilitation Project
Stage:
Implementation
Area:
Province Subbasin %
Mountain Columbia Kootenai 100.00%
Contract Number:
74469
Contract Title:
2002-011-00 EXP KOOTENAI RIVER OPS MITIGATION & EVALUATION
Contract Continuation:
Previous: Next:
70698: 2002-011-00 EXP KOOTENAI RIVER OPS MITIGATION AND EVALUATION
  • 76826 REL 1: 2002-011-00 EXP KOOTENAI RIVER OPS MITIGATION & EVALUATION
Contract Status:
Closed
Contract Description:
Continue to apply Operational Loss Assessment by implementing mitigation actions to reduce wildlife impacts due to the operation of Libby Dam.  In FY2016 the contract name was changed to “Kootenai River Ops Mitigation and Evaluation (KROME)” from the previous: “Kootenai River Operational Loss Assessment”. The original name was the “Kootenai River Floodplain Ecosystem Operational Loss Assessment, Protection, Mitigation and Rehabilitation Project”. The name changes reflect the project’s evolution over time from a planning contract to one with on-the-ground mitigation implementation. Restoration planning and implementation activities conducted by KTOI are divided between three projects: 2002-011-00, 2002-008-00, and 1992-061-00. Additionally, this project coordinates and subcontracts with Montana Fish, Wildlife and Parks to mitigate wildlife impacts in the Montana section of the Kootenai River.
Account Type(s):
Expense
Contract Start Date:
12/01/2016
Contract End Date:
11/30/2017
Current Contract Value:
$730,936
Expenditures:
$730,936

* Expenditures data includes accruals and are based on data through 31-Oct-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
John Barco III Bonneville Power Administration No Interested Party jwbarco@bpa.gov (503) 230-3223
Edward Gresh Bonneville Power Administration Yes Env. Compliance Lead esgresh@bpa.gov (503) 230-5756
Sue Ireland Kootenai Tribe Yes Supervisor ireland@kootenai.org (208) 267-3620
Solomonn Marsh Bonneville Power Administration Yes Contracting Officer spmarsh@bpa.gov (503) 230-3943
Norm Merz Kootenai Tribe Yes Contract Manager merz@kootenai.org (208) 267-3620x555
Christopher Roper Bonneville Power Administration No CO Assistant cproper@bpa.gov (503) 230-3514
Edna Runyan Kootenai Tribe Yes Administrative Contact edna@kootenai.org (208) 267-3620
Tybee Sheidler Bonneville Power Administration No CO Assistant tasheidler@bpa.gov (503) 230-3820
Scott Soults Kootenai Tribe Yes Contract Manager soults@kootenai.org (208) 267-3620
Virgil Watts III Bonneville Power Administration Yes COR vlwatts@bpa.gov (503) 230-4625
Dorothy Welch Bonneville Power Administration Yes F&W Approver dwwelch@bpa.gov (503) 230-5479
Elham Zolmajd-Haghighi Bonneville Power Administration No CO Assistant ezolmajd-haghighi@bpa.gov (503) 230-7414


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Project Administration B: 119. Oversight and administer Planning and Design and new project activities 11/30/2017 11/30/2017
Reports Documenting Coordination Meetings C: 189. Planning, Design & Coordination of Existing & New Projects 11/30/2017 11/30/2017
Operational Loss Relational Database D: 160. Operational Loss Relational Database 11/30/2017 11/30/2017
Produce accessible, error-checked datasets E: 157. Monitor biological communities in the floodplain and within project areas 11/30/2017 11/30/2017
Produce a Protection, Mitigation, Restoration, and Monitoring plan F: 174. Finalize Management Plan for protection, mitigation, and restoration 11/30/2017 01/25/2017
Design restoration projects in the canyon reach of the Kootenai River G: 175. Restoration opportunity identification and design - canyon reach (FWP) 11/30/2017 11/30/2017
Design restoration project along the Meander Reach of the Kootenai River H: 175. Restoration opportunity identification and design - Meander Reach 11/30/2017 11/30/2017
EC compliance I: 165. Complete EC and permitting for Meander Reach Projects (WE 181) 10/31/2017 10/31/2017
Summary of project implementation and pictures J: 181. Implementation of select Meander Reach restoration projects. 11/30/2017 11/30/2017
EC compliance (WE 47) K: 165. Complete EC for Riparian Planting (WE 47) 11/15/2017 11/15/2017
Completion Report L: 47. Plant riparian vegetation (FWP) 11/30/2017 11/30/2017
Propose New Protection Projects to BPA M: 114. Identify potential protection mitigation purchases 11/30/2017 11/30/2017
Completed Work Related to Property Pre-Acquisition N: 172. Potential Land Acquisition Tasks and Evaluations 11/30/2017 11/30/2017
Annual Report O: 132. Produce Annual Progress Report 11/30/2017 11/30/2017

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Wildlife
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 181 Create, Restore, and/or Enhance Wetland
  • 1 instance of WE 172 Conduct Pre-Acquisition Activities
  • 1 instance of WE 114 Identify and Select Projects
  • 1 instance of WE 174 Produce Plan
  • 2 instances of WE 175 Produce Design
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 12/01/2016
B 119 Oversight and administer Planning and Design and new project activities 12/01/2016
C 189 Planning, Design & Coordination of Existing & New Projects 12/01/2016
D 160 Operational Loss Relational Database 12/01/2016
E 157 Monitor biological communities in the floodplain and within project areas 12/21/2016
F 174 Finalize Management Plan for protection, mitigation, and restoration 12/01/2016
G 175 Restoration opportunity identification and design - canyon reach (FWP) 12/01/2016
H 175 Restoration opportunity identification and design - Meander Reach 12/01/2016
I 165 Complete EC and permitting for Meander Reach Projects (WE 181) 12/01/2016
J 181 Implementation of select Meander Reach restoration projects. 04/28/2017
K 165 Complete EC for Riparian Planting (WE 47) 12/01/2016
L 47 Plant riparian vegetation (FWP) 01/20/2017
M 114 Identify potential protection mitigation purchases 12/01/2016
N 172 Potential Land Acquisition Tasks and Evaluations 12/01/2016
O 132 Produce Annual Progress Report 12/01/2016