Cultural Resource clearance complete |
A: 165. Complete Environmental Compliance Requirements & Tribal/Cultural Surveys |
|
12/31/2017 |
11/15/2017 |
Complete feasibility assessment and EC for proposed reservoirs |
B: 175. Complete EC and feasibility for repair/construction of reservoirs on Trail and Hunter Creek parcels |
|
12/31/2017 |
06/05/2017 |
Weed Control |
C: 198. Weed Control |
|
12/31/2017 |
12/21/2017 |
Maintain Wet Meadow Irrigation System |
D: 198. Maintain Wet Meadow Irrigation |
|
10/31/2017 |
10/16/2017 |
Haying Operations |
E: 198. Haying Operations |
|
10/15/2017 |
09/15/2017 |
Graze BLM, State and Meadows. |
F: 199. Graze State and Meadows |
|
12/31/2017 |
07/30/2017 |
Plant willows |
G: 47. Plant Willows on Riparian |
|
12/31/2017 |
10/09/2017 |
Plant Pollinator habitat |
H: 47. Plant Pollinator habitat |
|
12/31/2017 |
11/09/2017 |
Plant seed in alfalfa field |
I: 47. seed alfalfa field |
|
10/31/2017 |
06/05/2017 |
Fence Maintained |
J: 186. Maintain Fence |
|
12/31/2017 |
10/20/2017 |
complete excavation of wetland ponds / culvert installation of OWEB grant project |
K: 181. oversee OWEB grant wetland enhancement project |
|
12/31/2017 |
|
Conservation Reserve Enhancement Program Maintenance |
L: 198. Conservation Reserve Enhancement Program Maintenance |
|
12/31/2017 |
04/30/2017 |
Data Collected and entered |
M: 157. Conduct Project Surveys |
|
12/31/2017 |
12/21/2017 |
Juniper removed |
N: 199. juniper eradication - NRCS SGI contract |
|
12/31/2017 |
11/15/2017 |
Sage Grouse study |
O: 158. Sage Grouse Study |
|
12/31/2017 |
12/21/2017 |
Improved roads |
P: 38. Improve roads on mitigation site |
|
12/31/2017 |
07/28/2017 |
Update roof on barn |
Q: 186. Update roof on barn |
|
12/31/2017 |
|
Update fuel tanks with spill basins |
R: 186. Update fuel tanks with spill basins |
|
12/31/2017 |
07/30/2017 |
Inspect Bridge for structural integrity / weight limits. |
S: 186. Initiate inspection of bridge across Malheur River for structural integrity |
|
12/31/2017 |
08/17/2017 |
EC complete for update/renovating bunkhouse |
T: 186. EC for update/renovating bunkhouse |
|
12/31/2017 |
|
Access controlled |
U: 188. Control Access |
|
12/31/2017 |
12/21/2017 |
Community education and information |
V: 99. Public Education and Information |
|
12/31/2017 |
12/21/2017 |
Tribal education complete |
W: 99. Tribal Community Education |
|
12/31/2017 |
12/21/2017 |
Staff education and communication |
X: 99. Seminars/Training for staff |
|
12/31/2017 |
12/21/2017 |
Project administration |
Y: 119. Project Administration & Assist Fisheries department |
|
12/31/2017 |
12/29/2017 |
Completed Annual Report |
Z: 132. Submit Progress Report for the period 1/1/2016 to 12/31/2016 |
|
04/15/2017 |
03/14/2017 |
New well and water lines to Manager's house and bunkhouse |
AC: 186. New well and water lines to bunkhouse and Manager's house |
|
12/31/2017 |
|
Cost Share: Rebuild Greenhouse |
AD: 186. Cost share: Rebuild greenhouse |
|
10/31/2017 |
|