72273: 2007-127-00 EXP SOUTH FORK SALMON WATERSHED RESTORATION |
|
* Expenditures data includes accruals and are based on data through 30-Nov-2024.
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
All administrative tasks fulfilled with timely quality products | B: 119. Project Management, Coordination, and Administration | 03/31/2018 | 03/08/2018 | |
Provide Environmental Compliance Documentation to BPA | C: 165. Provide Environmental Compliance Documentation to BPA | 11/30/2017 | 11/30/2017 | |
Watershed and Habitat Restoration Outreach and Education | D: 99. Public outreach and education | 02/28/2018 | 03/08/2018 | |
Maintain riparian plantings at Wapiti and Burgdorf Meadows | E: 198. Maintain Riparian plantings at Wapiti and Burgdorf Meadows | 11/30/2017 | 11/30/2017 | |
Remove reed canary grass at Wapiti Meadows | F: 199. Remove Reed Canary Grass | 11/30/2017 | 11/30/2017 | |
Decommission 12-14 Miles of Forest Roads on the Boise National Forest | G: 33. Dollar Creek Road Decommission 12-14 Miles of Forest Roads | 11/30/2017 | 11/30/2017 | |
Decommission 5-7 miles of road in the Big Creek Watershed | H: 33. Big Creek Road Decomissioning | 11/30/2017 | 11/30/2017 | |
Improve 4.5 miles of Willow Creek Road and Trail for sediment reduction | I: 38. Willow Creek Road and Trail Improvement | 11/30/2017 | 11/30/2017 | |
Big Creek Road Improvements | J: 38. Big Creek Road Improvement | 11/30/2017 | 11/30/2017 | |
Remove fishing trails in the riparian habitat causing sediment delivery to the SFSR | K: 55. Remove trails in riparian habitat causing sediment in the SFSR | 11/30/2017 | 11/30/2017 | |
GRAIP Road Surveys complete | L: 115. GRAIP road inventory surveys | 11/30/2017 | 11/30/2017 | |
FY 2017 Progress Report | M: 132. Submit Progress Report for the period 4/17 thru 3/18 | 03/15/2018 | 03/08/2018 | |
List of Selected FY2018 Restoration Implementation Projects | N: 114. Identify and Select FY18 Restoration Projects | 02/28/2018 | 02/28/2018 |
Primary Focal Species | Work Statement Elements |
---|---|
Chinook (O. tshawytscha) - Snake River Fall ESU (Threatened) |
|
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened) |
|
Steelhead (O. mykiss) - Snake River DPS (Threatened) |
|
Trout, Bull (S. confluentus) (Threatened) |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 185 | Periodic Status Reports for BPA | 04/01/2017 | ||||||
B | 119 | Project Management, Coordination, and Administration | 04/01/2017 | ||||||
C | 165 | Provide Environmental Compliance Documentation to BPA | 04/01/2017 | ||||||
D | 99 | Public outreach and education | 04/01/2017 | ||||||
E | 198 | Maintain Riparian plantings at Wapiti and Burgdorf Meadows | 05/03/2017 | ||||||
F | 199 | Remove Reed Canary Grass | 05/03/2017 | ||||||
G | 33 | Dollar Creek Road Decommission 12-14 Miles of Forest Roads | 05/03/2017 | ||||||
H | 33 | Big Creek Road Decomissioning | 05/03/2017 | ||||||
I | 38 | Willow Creek Road and Trail Improvement | 05/03/2017 | ||||||
J | 38 | Big Creek Road Improvement | 06/29/2017 | ||||||
K | 55 | Remove trails in riparian habitat causing sediment in the SFSR | 05/03/2017 | ||||||
L | 115 | GRAIP road inventory surveys | 05/03/2017 | ||||||
M | 132 | Submit Progress Report for the period 4/17 thru 3/18 | 04/01/2017 | ||||||
N | 114 | Identify and Select FY18 Restoration Projects | 04/01/2017 |