Province | Subbasin | % |
---|---|---|
Mountain Snake | Salmon | 100.00% |
Previous: | Next: |
---|---|
75103: 2008-903-00 EXP ESA HABITAT RESTORATION |
* Expenditures data includes accruals and are based on data through 30-Nov-2024.
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Ensure that environmental compliance is complete for all work elements | B: 165. Provide support for environmental compliance | 07/15/2018 | 07/15/2018 | |
Effective implementation management and timely contract administration | C: 119. Administer & Manage ESA Habitat Contract | 02/28/2019 | 02/28/2019 | |
Yankee Fork CHaMP/AEM data collection | D: 157. Yankee Fork CHaMP/AEM data collection | 12/30/2018 | 12/30/2018 | |
Yankee Fork CHaMP/AEM disseminate data | E: 161. Yankee Fork CHaMP/AEM disseminate data | 12/30/2018 | 12/30/2018 | |
Produce designs for Panther Creek Drainage enhancement | F: 175. Produce design plan for Panther Creek Drainage enhancement | 12/21/2018 | 12/31/2018 | |
Produce designs for East Fork Salmon River Habitat Enhancement Project | G: 175. Produce design plan for East Fork Salmon River Habitat Enhancement Project | 12/21/2018 | 12/21/2018 | |
Valley Creek Road (NFS RD# 70304) Decommissioning | H: 33. Decommissioning of Valley Creek Road | 10/15/2018 | 10/15/2018 | |
North Fork Habitat Improvement project: Arbon/Barton site | I: 29. North Fork Habitat Improvement Project: Arbon/Barton | 11/30/2018 | 11/30/2018 | |
Install a total of a total of 0.64 miles of fencing at North Fork and Hughes Creek sites | J: 40. Install fencing at North Fork and Hughes Creek sites | 10/31/2018 | 10/31/2018 | |
Completed Annual Report | K: 132. Submit Progress Report for the period 1/1/2017 to 12/31/2017 | 02/28/2019 | 02/28/2019 | |
Completed Annual Report | L: 132. Submit Final Progress Report for the period (1/1/2016) to (12/31/2016) | 02/28/2019 | 02/28/2019 |
Primary Focal Species | Work Statement Elements |
---|---|
Chinook (Oncorhynchus tshawytscha) - All Populations |
|
Chinook (O. tshawytscha) - Snake River Fall ESU (Threatened) |
|
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened) |
|
Chinook (O. tshawytscha) - Snake River Spring/Summer (not listed) |
|
Chinook (O. tshawytscha) - Upper Columbia River Summer/Fall ESU |
|
Steelhead (O. mykiss) - Snake River DPS (Threatened) |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 185 | Periodic Status Reports for BPA | 01/01/2018 | ||||||
B | 165 | Provide support for environmental compliance | 01/01/2018 | ||||||
C | 119 | Administer & Manage ESA Habitat Contract | 01/01/2018 | ||||||
D | 157 | Yankee Fork CHaMP/AEM data collection | 03/01/2018 | ||||||
E | 161 | Yankee Fork CHaMP/AEM disseminate data | 01/01/2018 | ||||||
F | 175 | Produce design plan for Panther Creek Drainage enhancement | |||||||
G | 175 | Produce design plan for East Fork Salmon River Habitat Enhancement Project | |||||||
H | 33 | Decommissioning of Valley Creek Road | 09/12/2018 | ||||||
I | 29 | North Fork Habitat Improvement Project: Arbon/Barton | 06/25/2018 | ||||||
J | 40 | Install fencing at North Fork and Hughes Creek sites | 03/01/2018 | ||||||
K | 132 | Submit Progress Report for the period 1/1/2017 to 12/31/2017 | 01/01/2018 | ||||||
L | 132 | Submit Final Progress Report for the period (1/1/2016) to (12/31/2016) | 03/01/2018 |