70143: 2010-001-00 CAP BARKLEY IRRIGATION - MVID |
* Expenditures data includes accruals and are based on data through 30-Nov-2024.
Full Name | Organization | Write Permission | Contact Role | Work Phone | |
---|---|---|---|---|---|
Brenda Aguirre | Bonneville Power Administration | Yes | Env. Compliance Lead | baguirre@bpa.gov | (503) 230-5928 |
Jamie Cleveland | Bonneville Power Administration | Yes | COR | jacleveland@bpa.gov | (503) 230-3160 |
Joseph Connor | Bonneville Power Administration | Yes | Technical Contact | jwconnor@bpa.gov | (503) 230-3172 |
Peter Lofy | Bonneville Power Administration | Yes | F&W Approver | ptlofy@bpa.gov | (503) 230-4193 |
Lisa Pelly | Trout Unlimited (TU) | Yes | Supervisor | lpelly@tu.org | (509) 888-0970 |
Aaron Penvose | Trout Unlimited (TU) | Yes | Contract Manager | apenvose@tu.org | (509) 888-0970 |
Sarah Walker | Upper Columbia Salmon Recovery Board | No | Interested Party | sarah.walker@ucsrb.org | (509) 630-8226 |
Karen Wolfe | Bonneville Power Administration | Yes | Contracting Officer | ktwolfe@bpa.gov | (503) 230-3448 |
Elham Zolmajd-Haghighi | Bonneville Power Administration | Yes | CO Assistant | ezolmajd-haghighi@bpa.gov | (503) 230-7414 |
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Complete Environmental Compliance Permitting Processes | A: 165. Obtain Required Permits, Authorizations, and Documentation for the Project | 03/14/2019 | 12/14/2018 | |
Effective implementation management and timely contract administration | B: 119. Manage BPA Contracting Requirements | 06/19/2019 | 06/18/2019 | |
Pipeline Installed | C: 203. Purchase Pipe for Barkley | 06/19/2019 | 06/10/2019 | |
Ordered and installed functioning pipeline for MVID water conveyance. | D: 203. Purchase Pipe for MVID | 06/19/2019 | 06/10/2019 | |
Eliminate Use of Historic Barkley Diversion | E: 84. Remove Historic Barkley Irrigation Diversion | 06/19/2019 | ||
Checklist Developed & Attached in Pisces | F: 154. Develop Checklist | 07/31/2018 | 06/15/2018 |
Primary Focal Species | Work Statement Elements |
---|---|
Chinook (O. tshawytscha) - Upper Columbia River Spring ESU (Endangered) |
|
Chinook (O. tshawytscha) - Upper Columbia River Summer/Fall ESU |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 165 | Obtain Required Permits, Authorizations, and Documentation for the Project | 02/01/2018 | ||||||
B | 119 | Manage BPA Contracting Requirements | 02/01/2018 | ||||||
C | 203 | Purchase Pipe for Barkley | 12/26/2018 | ||||||
D | 203 | Purchase Pipe for MVID | 12/14/2018 | ||||||
E | 84 | Remove Historic Barkley Irrigation Diversion | 12/14/2018 | ||||||
F | 154 | Develop Checklist | 02/01/2018 | ||||||
G | 185 | Periodic Status Reports for BPA | 02/01/2018 | ||||||
H | 132 | Provide Information to UCSRB for Programmatic Annual Report | 02/01/2018 |