Province | Subbasin | % |
---|---|---|
Mountain Snake | Salmon | 100.00% |
* Expenditures data includes accruals and are based on data through 31-Dec-2024.
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
All administrative tasks fulfilled with timely quality products | A: 119. Routine administration of contract | 01/31/2019 | 01/31/2019 | |
Provide BPA with all necessary EC/permits | B: 165. Provide to BPA any requested EC/permits | 01/31/2019 | 01/31/2019 | |
Final Project Designs | C: 175. Final Designs for Construction | 01/31/2019 | 12/31/2018 | |
Reconnection and Flow Enhancement of Bohannon Creek | D: 85. Bohannon Creek-03 (LBC-03) Vertical Turbine Pump Station | 01/31/2019 | 01/31/2019 | |
Completed FSOC/NOAA criteria fish screen | E: 69. Pahsimeroi River-17 (P-17) Fish Screen Project | 01/31/2019 | ||
Completed FSOC/NOAA criteria fish screen | F: 69. Lemhi River-61 (L-61) Fish Screen Project | 01/31/2019 | 01/31/2019 | |
Completed FSOC/NOAA criteria fish screen | G: 69. Big Timber Creek-01 (LBTC-01) Fish Screen Project | 01/31/2019 | ||
Completed FSOC/NOAA criteria fish screen. | H: 69. Pratt Creek-Hedt (LPrC-Hedt)Fish Screen Project | 01/31/2019 | 01/31/2019 | |
Completed FSOC/NOAA criteria fish screen. | I: 69. Pratt Creek -02 (LPrC-02) Fish Screen Project | 01/31/2019 | ||
Completed FSOC/NOAA criteria fish screen. | J: 69. Eighteen Mile Creek -01 (LEmC-01) Fish Screen Project | 07/01/2018 | 07/01/2018 | |
Completed FSOC/NOAA criteria fish screen. | K: 69. Meadow Creek -01 (SVCMC-01) Fish Screen Project | 01/31/2019 | ||
Completed FSOC/NOAA criteria fish screen | L: 69. Lemhi River-08A (L-08A) Fish Screen Project - Phase 2 Ditch Restructuring | 05/01/2018 | 04/27/2018 | |
Completed FSOC/NOAA criteria fish screen | M: 69. Lemhi River-03AO (L-03AO) Fish Screen Project | 10/03/2018 | 10/12/2018 |
Primary Focal Species | Work Statement Elements |
---|---|
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened) |
|
Steelhead (O. mykiss) - Snake River DPS (Threatened) |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 119 | Routine administration of contract | 09/27/2017 | ||||||
B | 165 | Provide to BPA any requested EC/permits | 09/27/2017 | ||||||
C | 175 | Final Designs for Construction | 10/15/2018 | ||||||
D | 85 | Bohannon Creek-03 (LBC-03) Vertical Turbine Pump Station | 10/01/2017 | ||||||
E | 69 | Pahsimeroi River-17 (P-17) Fish Screen Project | |||||||
F | 69 | Lemhi River-61 (L-61) Fish Screen Project | 10/12/2018 | ||||||
G | 69 | Big Timber Creek-01 (LBTC-01) Fish Screen Project | 11/28/2018 | ||||||
H | 69 | Pratt Creek-Hedt (LPrC-Hedt)Fish Screen Project | 10/16/2018 | ||||||
I | 69 | Pratt Creek -02 (LPrC-02) Fish Screen Project | 11/30/2018 | ||||||
J | 69 | Eighteen Mile Creek -01 (LEmC-01) Fish Screen Project | 02/01/2018 | ||||||
K | 69 | Meadow Creek -01 (SVCMC-01) Fish Screen Project | |||||||
L | 69 | Lemhi River-08A (L-08A) Fish Screen Project - Phase 2 Ditch Restructuring | 02/01/2018 | ||||||
M | 69 | Lemhi River-03AO (L-03AO) Fish Screen Project | 08/28/2018 | ||||||
N | 132 | Submit Progress Report for the period September 27th, 2012 to January 31, 2018 | 09/27/2017 | ||||||
O | 185 | Periodic Status Reports for BPA | 09/27/2017 |