Province | Subbasin | % |
---|---|---|
Mountain Snake | Salmon | 100.00% |
* Expenditures data includes accruals and are based on data through 31-Dec-2024.
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Complete all required EC and obtain site-specific permits prior to implementation of project | B: 165. Environmental Compliance | 02/28/2019 | ||
Remove (crush and haul) dredge tailings to prep for 2018/2019 Bonanza City Habitat Project | C: 52. Remove (crush and haul) 24,700 cy of dredge tailings to prep for 2018/2019 Bonanza City Habitat Project | 10/19/2018 | 09/27/2018 | |
Remove dredge tailings to prep for 2018/2019 Bonanza City Habitat Project | D: 52. Remove ~ 80,000 cy of mine tailings to create flood-plain at Bonanza City Habitat Project | 02/28/2019 | ||
Manage removal of dredge tailings. | E: 100. Manage removal of mine tailings. | 02/28/2019 | ||
Effective implementation management and timely contract administration | F: 119. Manage and Administer Project | 02/28/2019 | ||
Completed Annual Report | G: 132. Submit Progress Report for the period June 2018 thru May 2019 | 02/28/2019 | ||
Completed Annual Report | H: 132. Submit Final Progress Report for the period June 2017 to May 2018 | 02/28/2019 | 07/18/2018 |
Primary Focal Species | Work Statement Elements |
---|---|
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened) |
|
Steelhead (O. mykiss) - Snake River DPS (Threatened) |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 185 | Periodic Status Reports for BPA | 06/01/2018 | ||||||
B | 165 | Environmental Compliance | 06/01/2018 | ||||||
C | 52 | Remove (crush and haul) 24,700 cy of dredge tailings to prep for 2018/2019 Bonanza City Habitat Project | 06/01/2018 | ||||||
D | 52 | Remove ~ 80,000 cy of mine tailings to create flood-plain at Bonanza City Habitat Project | 06/01/2018 | ||||||
E | 100 | Manage removal of mine tailings. | 06/01/2018 | ||||||
F | 119 | Manage and Administer Project | 06/01/2018 | ||||||
G | 132 | Submit Progress Report for the period June 2018 thru May 2019 | 06/01/2018 | ||||||
H | 132 | Submit Final Progress Report for the period June 2017 to May 2018 | 06/01/2018 |