Contract 83002: 2010-001-00 EXP TWISP PONDS: DESIGN AND IMPLEMENTATION
Project Number:
Title:
Upper Columbia Programmatic Habitat
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Cascade Entiat 25.00%
Methow 25.00%
Okanogan 25.00%
Wenatchee 25.00%
Contract Number:
83002
Contract Title:
2010-001-00 EXP TWISP PONDS: DESIGN AND IMPLEMENTATION
Contract Continuation:
Previous: Next:
n/a
  • 85755: 2010-001-00 EXP TWISP PONDS: DESIGN AND IMPLEMENTATION
Contract Status:
Closed
Contract Description:
The Twisp Ponds project is in the Lower Twisp River Assessment Unit (AU), a major spawning area for both spring Chinook and steelhead.  Both the Biological Strategy and EDT rank the Lower Twisp/ Twisp-Lower AU as a top priority for restoration.  The project addresses important ecological concerns as identified in the Biological Strategy. Methow Salmon Recovery Foundation (MSRF) and BPA technical leads will identify in channel complexity improvements that will prevent seasonal disconnection of the intake that feeds the side channel network.  Design leads will also review potential improvements within the intake channel that could A) provide increased habitat for target species or B) reduce winter ice build up at three road crossing culverts.  

One of the project objectives is to provide a demonstration of the potential for small team efficiency in developing adaptive actions.  This project assumes that MSRF and BPA staff will be able to sufficiently develop a preferred alternative that can be fully permitted, reviewed, and constructed with limited use of an independent engineering contractor.

Project is intended to restore a perennial connection to the Twisp Ponds side channel network flowing from an existing connection to the Twisp River at River Mile 1.5.  This project will increase off-channel rearing habitat and main channel for juvenile spring Chinook and steelhead by providing a perennial connection to the Twisp Ponds side channel network and increasing instream complexity in the main channel.

MSRF Contract Manager and MSRF's design consultants will all cooperate, coordinate, collaborate, and maintain effective communication with BPA PM/COR, EC Lead, HIP Review Lead, and Hydraulic Engineer during the entire length of this contract with regards to project design.  MSRF and its subcontractors will address BPA comments and concerns, and the two entities will arrive at a mutual beneficial consensus.  MSRF contract manager will upload all the subcontracts being executed under this contract.
Account Type(s):
Expense
Contract Start Date:
09/01/2019
Contract End Date:
08/31/2020
Current Contract Value:
$45,942
Expenditures:
$45,942

* Expenditures data includes accruals and are based on data through 30-Nov-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Coop
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Brenda Aguirre Bonneville Power Administration Yes Env. Compliance Lead baguirre@bpa.gov (503) 230-5928
Jay Chong Bonneville Power Administration Yes Contracting Officer jxchong@bpa.gov (503) 230-4007
Jamie Cleveland Bonneville Power Administration Yes COR jacleveland@bpa.gov (503) 230-3160
Joseph Connor Bonneville Power Administration Yes Technical Contact jwconnor@bpa.gov (503) 230-3172
Brian Fisher Methow Salmon Recovery Foundation Yes Technical Contact brian@methowsalmon.org (509) 387-1716
Desmond Gelman Bonneville Power Administration No CO Assistant dxgelman@bpa.gov (503) 230-4960
Jessica Goldberg Methow Salmon Recovery Foundation Yes Contract Manager jessica@methowsalmon.org (360) 624-3592
Chris Johnson Methow Salmon Recovery Foundation Yes Supervisor chrisj@methowsalmon.org (509) 996-2787
Peter Lofy Bonneville Power Administration Yes F&W Approver ptlofy@bpa.gov (503) 230-4193
Deb Nickell Methow Salmon Recovery Foundation Yes Administrative Contact deb@methowsalmon.org (509) 996-2787
Sarah Walker Upper Columbia Salmon Recovery Board No Interested Party sarah.walker@ucsrb.org (509) 630-8226
Katy Williams Methow Salmon Recovery Foundation Yes Administrative Contact katy@methowsalmon.org (509) 996-2787


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Complete Environmental Compliance permitting processes A: 165. Obtain Required Permits, Authorizations, and Documentation for the Twisp Ponds project 08/31/2020
Complete Project Designs and Contract for Construction B: 175. Project Design Development and Coordination 08/31/2020
Complete instream and floodplain complexity elements C: 29. Instream and Floodplain Complexity Elements 08/31/2020
Complete side channel modifications/improvements to improve connection D: 30. Improve Side Channel Connection 08/31/2020
Watershed-wide and regional coordination with stakeholders, interested public, and cooperating entities E: 191. Watershed Stakeholder Coordination and Outreach 08/31/2020 08/31/2020
Effective implementation management and timely contract administration H: 119. Manage BPA Contracting Requirements 08/31/2020 08/31/2020

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Upper Columbia River Spring ESU (Endangered)
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 30 Realign, Connect, and/or Create Channel
  • 1 instance of WE 175 Produce Design
Steelhead (O. mykiss) - Upper Columbia River DPS (Threatened)
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 30 Realign, Connect, and/or Create Channel
  • 1 instance of WE 175 Produce Design

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Obtain Required Permits, Authorizations, and Documentation for the Twisp Ponds project
B 175 Project Design Development and Coordination
C 29 Instream and Floodplain Complexity Elements 08/06/2020
D 30 Improve Side Channel Connection 08/06/2020
E 191 Watershed Stakeholder Coordination and Outreach
F 185 Periodic Status Reports for BPA
G 132 No Report Required Per COR
H 119 Manage BPA Contracting Requirements