Complete project administration |
A: 119. Project administration |
|
09/30/2020 |
09/28/2020 |
Receipt of EC documentation/clearance from BPA |
B: 165. Satisfy environmental compliance requirements |
|
07/31/2020 |
09/28/2020 |
Complete parcel identification |
C: 115. SIWM Parcel Identification |
|
09/30/2020 |
09/28/2020 |
Complete pre-acquisition activities |
D: 172. Conduct pre-acquisitional tasks |
|
09/30/2020 |
09/30/2020 |
Coordination with other wildlife mitigation entities in the region |
E: 114. SIWM Coordination |
|
09/30/2020 |
09/30/2020 |
Maintenance of fence and corrals completed |
F: 186. Fence maintenance, , maintain infrastructure at Pole Creek Ranch |
|
09/30/2020 |
09/30/2020 |
Completed Native Plant Inventory Spreadsheetand Photos for Native Plant Inventory Database |
G: 115. Conduct baseline native plant survey on Pole Creek Ranch |
|
09/30/2020 |
09/30/2020 |
Completed Columbia Spotted Frog Surveys |
H: 115. Conduct Columbia spotted frog surveys on Pole Creek Ranch |
|
09/30/2020 |
07/29/2020 |
Document property access and trespassing issues in annual report |
I: 26. Investigate trespass on Pole Creek Ranch |
|
09/30/2020 |
09/30/2020 |
Weed treatment documentation |
J: 199. Conduct weed treatment activities |
|
09/30/2020 |
09/30/2020 |
1.63 miles of boundary fence constructed; 1.53 northern boundary fence; .10 downstream Pole Creek boundary fence |
K: 40. Complete installation of property boundary fence at two locations on Pole Creek main parcel |
|
08/31/2020 |
09/03/2020 |
Recycling income and estimate of number of pounds of debris removed |
L: 27. Remove debris from 5 sites on main parcel of Pole Creek |
|
09/30/2020 |
|
Remove .59 miles of decommissioned fence and fence wires from property at three locations |
M: 27. Decommission one fence and remove wire from two locations on main Pole Creek property |
|
09/30/2020 |
11/07/2019 |
Complete prescribed grazing treatment on Pole Creek main parcel |
N: 199. Prescribed grazing treatment on main parcel of ranch |
|
09/30/2020 |
09/07/2020 |
Native seed collection of four forb species, two grass species and one shrub species |
O: 199. Collect native plant materials |
|
09/30/2020 |
09/18/2020 |
Completed Annual Report |
P: 132. Submit Progress Report for the period (1/1/19 to 12/31/19) |
|
05/15/2020 |
06/29/2020 |
Pilot Basin Springs Fencing Project Completed |
Q: 40. Pilot temporary fence project at Basin Springs Parcel |
|
09/30/2020 |
09/29/2020 |
2000 juniper trees cut. |
R: 198. Cut and lay down 2000 stage one juniper trees from Pole Creek main parcel |
|
09/30/2020 |
09/30/2020 |