Province | Subbasin | % |
---|---|---|
Mountain Columbia | Flathead | 100.00% |
Previous: | Next: |
---|---|
84048 REL 3: 2002-003-00 EXP SECURE & RESTORE F&W HABITAT |
* Expenditures data includes accruals and are based on data through 30-Nov-2024.
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Effective implementation management and timely contract administration | B: 119. Complete necessary BPA contracting requirements | 09/30/2025 | ||
Work with BPA to complete EC requirements. | C: 165. Work with BPA staff to complete NEPA and public involvement requirements | 09/30/2025 | ||
Final Realty Package Submitted to BPA | D: 172. Conduct all pre-acquisition activities for lands purchased under the CSKT/BPA MOU | 09/30/2025 | ||
Completed Progress (Annual) Report for 10/1/2023 - 9/30/2025 | E: 132. Prepare two-year report (10/1/2023 - 9/30/2025). | 09/30/2025 |
Primary Focal Species | Work Statement Elements |
---|---|
Cutthroat Trout, Westslope (O. c. lewisi) |
|
Trout, Bull (S. confluentus) (Threatened) |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 185 | Periodic Status Reports for BPA | |||||||
B | 119 | Complete necessary BPA contracting requirements | |||||||
C | 165 | Work with BPA staff to complete NEPA and public involvement requirements | |||||||
D | 172 | Conduct all pre-acquisition activities for lands purchased under the CSKT/BPA MOU | 06/11/2024 | ||||||
E | 132 | Prepare two-year report (10/1/2023 - 9/30/2025). |