Contract 84051 REL 12: 1990-018-00 EXP RAINBOW TROUT HABITAT/PASSAGE IMPROVEMENT
Project Number:
Title:
Lake Roosevelt Rainbow Trout Habitat and Passage Improvement
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Intermountain Sanpoil 100.00%
Contract Number:
84051 REL 12
Contract Title:
1990-018-00 EXP RAINBOW TROUT HABITAT/PASSAGE IMPROVEMENT
Contract Continuation:
Previous: Next:
91814: 1990-018-00 EXP RAINBOW TROUT HABITAT/PASSAGE IMPROVEMENT
  • CR-373496: 1990-018-00 EXP RAINBOW TROUT HABITAT/PASSAGE IMPROVEMENT
Contract Status:
Issued
Contract Description:
The Lake Roosevelt Rainbow Trout Habitat/Passage Improvement Project is a resident fish substitution project intended to mitigate for anadromous fish losses caused by the construction and operations of Chief Joseph and Grand Coulee Dams.  The goal is to restore healthy and harvestable salmonid populations through rehabilitation of stream habitat and restoration of ecological function in the riparian corridors of streams within the boundaries of the Colville Confederated Tribes Reservation and Traditional Territories.

The Project proposes to enhance natural production and survival of resident fish for recreation and Tribal subsistence with the implementation of several management actions designed to address habitat related limiting factors and restore the natural hydrologic function of the systems.  In 2011, the project adopted an updated habitat improvement and protection strategy that focused on process-based restoration of natural stream function and a clearly-defined, hierarchical prioritization and implementation strategy to guide improvement actions.

The results of EDT modelling and restoration plan development identified 25 priority reaches to focus our efforts in and concluded that the most common restoration measures suggested for these priority reaches were: additions of large wood to the channel, riparian restoration, livestock exclusion, floodplain reconnections, remeandering straightened channels, wetland restoration, barrier removal, and protection.

The habitat restoration actions will improve the quality and quantity of stream habitat for native fishes.  These actions are designed to increase the abundance of native fish, primarily Redband Trout, to support ecosystem health and harvest opportunities.

We will begin working toward implementation of actions identified in the plan, as well as complete and maintain restoration identified in previous years.  

Work under this contract cycle will include:
•    Maintenance of approximately 16.19 miles of existing riparian fence
•    Monitor exclosures
•    Maintain BDAs at two sites; Lost-Loony creeks and Moses Creek #1
•    Maintain riparian plantings at two sites; Lost-Loony creeks and Moses Creek #1
•    Design and implement BDAs at three sites; Moses Creek #2, Twentythree Mile Creek, and Lost Creek #1
•    Design LWD placement at two sites for implementation in FY24; Sanpoil-4B and Sanpoil-4A
•    Design fish passage structures at two sites for implementation in FY24; Lower Gold Creek and Lost Creek
Account Type(s):
Expense
Contract Start Date:
02/01/2024
Contract End Date:
01/31/2025
Current Contract Value:
$788,840
Expenditures:
$475,764

* Expenditures data includes accruals and are based on data through 30-Nov-2024.

BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Coop
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Environmental Compliance A: 165. Complete Environmental Compliance 01/31/2025
Develop or update (out-year) prioritized Habitat Project list: Upload to CBFish B: 114. Identify and Select Projects for the Upper Columbia and Sanpoil Habitat Restoration Plan (WE-B in FY23) 01/31/2025
Provide Technical Review and Recommendations C: 122. Interdisciplinary Project Planning Participation - Technical Review (WE-C in FY23) 01/31/2025
Maintain Riparian Fencing D: 186. Maintain Existing Riparian Fence (WE-D in FY23) 01/31/2025
Riparian Protection Exclosures Monitored E: 26. Monitor Exclosures (WE-E in FY23) 01/31/2025
Design Plan Set for Sanpoil River (Sanpoil 4B) Large Wood Addition F: 175. Design Specifications & Engineering: Middle Sanpoil River (Sanpoil-4B)- Large Wood Placement (WE-H in FY23) 01/31/2025
Design Plan Set for Sanpoil River (Sanpoil 4A) Large Wood Addition G: 175. Design Specifications & Engineering: Middle Sanpoil River (Sanpoil-4A)- Large Wood Placement (WE-J in FY22) 01/31/2025
Cultural surveys to BPA H: 165. Cultural Resource Surveys 01/31/2025
Design Specifications and Site Plan I: 175. Moses Creek Site #2 BDA Design - WE-K in FY23 01/31/2025
Improved Habitat Function, Complexity and Structure: Installed BDAs Functioning as Designed in Moses Creek #2 Site J: 29. Moses Creek Site #2 BDA Installation - WE-L in FY23 01/31/2025
Completed Designs for Fish Passage on Gold Creek K: 175. Replacement of Forest Road Crossing over Lower Gold Creek - WE-O in FY23 01/31/2025
Completed Designs for Fish Passage on Lost Creek L: 175. Replacement of Forest Road Crossing over Lost Creek - WE-P in FY23 01/31/2025
LiDAR Data Collection M: 115. Topobathymetric LiDAR Acquisition – Sanpoil River 01/31/2025
Produce accessible, error-checked datasets N: 157. Monitor stream discharge in Sanpoil River 01/31/2025
Completed Annual Report P: 132. Submit Progress Report for the Period (Jan 2023) to (Dec 2023) 01/10/2025
Effective implementation management and timely contract administration Q: 119. Manage & Administer the Lake Roosevelt Rainbow Trout Habitat/Passage Improvement Project 01/31/2025

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Trout, Interior Redband (O. mykiss gairdnerii)
  • 1 instance of WE 26 Investigate Trespass
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 114 Identify and Select Projects
  • 1 instance of WE 115 Produce Inventory or Assessment
  • 5 instances of WE 175 Produce Design
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Complete Environmental Compliance
B 114 Identify and Select Projects for the Upper Columbia and Sanpoil Habitat Restoration Plan (WE-B in FY23)
C 122 Interdisciplinary Project Planning Participation - Technical Review (WE-C in FY23)
D 186 Maintain Existing Riparian Fence (WE-D in FY23)
E 26 Monitor Exclosures (WE-E in FY23)
F 175 Design Specifications & Engineering: Middle Sanpoil River (Sanpoil-4B)- Large Wood Placement (WE-H in FY23)
G 175 Design Specifications & Engineering: Middle Sanpoil River (Sanpoil-4A)- Large Wood Placement (WE-J in FY22)
H 165 Cultural Resource Surveys
I 175 Moses Creek Site #2 BDA Design - WE-K in FY23
J 29 Moses Creek Site #2 BDA Installation - WE-L in FY23
K 175 Replacement of Forest Road Crossing over Lower Gold Creek - WE-O in FY23
L 175 Replacement of Forest Road Crossing over Lost Creek - WE-P in FY23
M 115 Topobathymetric LiDAR Acquisition – Sanpoil River
N 157 Monitor stream discharge in Sanpoil River
O 185 Periodic Status Reports for BPA
P 132 Submit Progress Report for the Period (Jan 2023) to (Dec 2023)
Q 119 Manage & Administer the Lake Roosevelt Rainbow Trout Habitat/Passage Improvement Project