Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 84053 REL 4: 2007-024-00 EXP COEUR D'ALENE TROUT PONDS
Project Number:
Title:
Coeur D'Alene Trout Ponds
Stage:
Implementation
Area:
Province Subbasin %
Intermountain Coeur D'Alene 100.00%
Contract Number:
84053 REL 4
Contract Title:
2007-024-00 EXP COEUR D'ALENE TROUT PONDS
Contract Continuation:
Previous: Next:
76828 REL 23: 2007-024-00 EXP COEUR D'ALENE TROUT PONDS
Contract Status:
Closed
Contract Description:
Due to declining native salmonid fish stocks, particularly westslope cutthroat trout, redband trout, Bull trout and pacific salmon stocks, the Coeur d’ Alene Tribe provides compensatory subsistence harvest opportunities on the Coeur d’Alene Indian Reservation through the Trout Pond project (Project #200702400) funded by the Bonneville Power Administration. The project was developed to partially mitigate for the loss of anadromous fish due to the construction of Chief Joseph and Grand Coulee Dams.

Operations and maintenance of the project involve planting approximately 11,450 pounds of triploid rainbow trout across three locations during the contract cycle.  This equates to approximately 4,643 fish at an average weight of 1.5-2.2 lbs/fish plus an additional 400 fish (special events) at an average weight of 4.0 lbs/fish.  These sites are very popular with the local angling community and exploitation is high.  Additional activities at these same sites included several educational events and fishing related experiences.
Account Type(s):
Expense
Contract Start Date:
08/15/2023
Contract End Date:
08/14/2024
Current Contract Value:
$64,383
Expenditures:
$64,383

* Expenditures data includes accruals and are based on data through 30-Nov-2024.

BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Coop
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Jon Firehammer Coeur D'Alene Tribe Yes Contract Manager jfirehammer@cdatribe-nsn.gov (208) 686-7037
Jeff Jordan Coeur D'Alene Tribe Yes Technical Contact jjjordan@cdatribe-nsn.gov (208) 686-8702
David Kaplowe Bonneville Power Administration Yes F&W Approver djkaplowe@bpa.gov (503) 230-5365
William Kozsey Jr Bonneville Power Administration Yes Contracting Officer WPKozsey@bpa.gov (503) 230-3280
Jessica Power Bonneville Power Administration Yes CO Assistant jdpower@bpa.gov (503) 230-4023
Shawn Skinner Bonneville Power Administration Yes Env. Compliance Lead srskinner@bpa.gov (503) 230-3727
Angelo Vitale Coeur D'Alene Tribe Yes Supervisor ajvitale@cdatribe-nsn.gov (208) 686-6903
Virgil Watts III Bonneville Power Administration Yes COR vlwatts@bpa.gov (503) 230-4625


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
EC Compliance Completed A: 165. Provide EC for all project needs 08/14/2024 08/09/2024
Conduct O&M for Put and Take Fisheries B: 187. Conduct O & M for Put and Take Fisheries 08/14/2024 08/09/2024
Maintain access C: 188. Provide public access and information 08/14/2024 08/09/2024
Provide outreach and education D: 99. Youth Fishing Day and/or fishing derbies 08/14/2024 08/09/2024
Completed Annual Report F: 132. Complete progress report for the period 8/2022 - 7/2024 08/14/2024 08/09/2024
Effective implementation management and timely contract administration G: 119. Manage and Administer project 08/14/2024 08/09/2024

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Trout, Rainbow (Oncorhynchus mykiss)
  • 1 instance of WE 187 Put and Take Fisheries

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Provide EC for all project needs
B 187 Conduct O & M for Put and Take Fisheries 06/02/2023
C 188 Provide public access and information 06/02/2023
D 99 Youth Fishing Day and/or fishing derbies
E 185 Periodic Status Reports for BPA
F 132 Complete progress report for the period 8/2022 - 7/2024
G 119 Manage and Administer project