Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 86023: 2010-001-00 EXP BARKLEY BEAR IMPLEMENTATION - PHASE 2
Project Number:
Title:
Upper Columbia Programmatic Habitat
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Cascade Entiat 25.00%
Methow 25.00%
Okanogan 25.00%
Wenatchee 25.00%
Contract Number:
86023
Contract Title:
2010-001-00 EXP BARKLEY BEAR IMPLEMENTATION - PHASE 2
Contract Continuation:
Previous: Next:
83074: 2010-001-00 EXP BARKLEY BEAR IMPLEMENTATION
  • 90369: 2010-001-00 EXP BARKLEY BEAR IMPLEMENTATION - PHASE 3
Contract Status:
Closed
Contract Description:
Methow Salmon Recovery Foundation (MSRF) and its partners, including BPA, Bureau of Reclamation (Reclamation), and UCSRB are preparing to implement a reach-scale salmon habitat enhancement project in the Middle Methow (M2) River in FY 2020 and 2021.  Project actions were developed under previous contracts for the M2 Barkley Bear Habitat Project funded through the BPA targeted solicitation process.  The project will be implemented in two phases, with the first phase scheduled for implementation in the summer of 2020 under existing contract 83074.  This new contract, beginning in September 2020, will cover all activities needed to implement Phase 2 in summer 2021.

The project was previously scheduled for construction to be completed in 2019, but was contingent on completion of the Barkley Irrigation Project in 2018 by another project sponsor.  Delays in completion of the Barkley Irrigation Project continue to limit the scope of project implementation actions in 2020 to those actions which do not impact the Barkley Irrigation Company (BIC) infrastructure.  With this limitation, MSRF has built a construction plan to implement Phase 1 actions in 2020.  The remaining project elements are scheduled for implementation in Phase 2 in 2021, after BIC releases interests in the canal and headworks.

MSRF is preparing to implement Phase I project actions in 2020 under Contract 83074, but acknowledges continued uncertainty related to current workplace restrictions, potential permitting delays, and the potential for additional restrictions due to the current COVID-19 pandemic.  It is possible that circumstances will still result in an inability to complete some or all of the Phase 1 actions in 2020 as planned.

While much of the uncertainty is outside of our control, MSRF has prepared a line item budget for 2021 (Phase 2) under the assumption that Phase 1 will be fully implemented in 2020.  MSRF currently has awarded a contract to a qualified bidder to implement a portion of the project in 2020 (Phase 1).  In the event that work place restrictions related to COVID-19 delay or reduce MSRF’s ability to complete Phase 1 actions during the 2020 in-water work window, MSRF will continue to communicate closely with BPA to update the 2021 scope and budget as needed.

The goal of this Barkley Bear Phase 2 contract is to ensure that all work actions needed to complete materials acquisition, federal/state/local environmental permitting and reporting, construction, and site restoration can be completed prior to September 14, 2021.  MSRF is working diligently to implement all required permitting activities for Phase 1 and Phase 2 of this project during the performance period of contract 83074 to the extent possible.

The majority of environmental compliance for project activities, including Section 7 ESA consultation via the BPA HIP process, have been completed under previous contracts.  Section 106 is expected to be completed in June 2020 under Contract 83074.  Remaining environmental compliance items include HIP renewal for calendar year 2021 prior to Phase 2 actions.  SEPA review for the suite of M2 projects was completed previously through Okanogan County in preparation for work at Whitefish Island (2012) and WDFW Floodplain (2013).  The SEPA review directed MSRF to complete a supplemental checklist for the 2020 actions at Barkley Bear to update any new project specific actions.  Okanogan County has issued a DNS for the Barkley actions that will be finalized on June 19, 2020.  Other permitting processes completed through APPS for the WDFW Hydraulic Project Authorization and the JARPA process for Corps of Engineers Nationwide permits, County Shorelines and Floodplain Development, and Department of Ecology water quality permits will also be finalized under contract 83074 prior to construction in 2020, but may need to be updated or renewed for construction in 2021.  

Lastly, under this contracting action, MSRF will solicit and award contracts for project construction and revegetation/site restoration to be completed under this contract.

In the event that the project or portions of the project scheduled for implementation in 2020 are delayed due to permitting, social distancing requirements, or completion of required implementation actions related to the Barkley Irrigation Project, MSRF understands that BPA may cancel specific work elements and de-obligate funding.  We understand that BPA will exercise this authority in order to not strand funding so it can be used elsewhere in the Upper Columbia or within the Habitat Program.  MSRF will coordinate with BPA staff to identify work elements for coordination and subsequent contract development that would be needed to implement the project under a future funding Agreement.

The contractor (MSRF), its designated agents, sub-consultants and project stakeholders will be available to BPA to work collaboratively to address any contract related issues during the term of the contract.  Contract issues include but are not limited to technical, policy, regulatory, project management and associated elements related to the project.  Successful execution of this contract is contingent on alignment of the preceding contract issues with the BIC and BPA contracting processes, project management plans, and integration of input and comments from BPA.

MSRF’s Contract Manager and consultants will all cooperate, coordinate, collaborate, and maintain effective communication with BPA PM/COR, EC Lead, HIP Review Lead, and Hydraulic Engineer during the entire length of this contract.  MSRF and its subcontractors will address BPA comments and concerns, and the two entities will arrive at a mutual beneficial consensus.  MSRF contract manager will upload all the subcontracts executed under this contract in cbfish.org.

MSRF will not submit an annual report under this contract.  MSRF will provide the Upper Columbia Salmon Recovery Board (UCSRB) sufficient information so they, UCSRB, can assemble a comprehensive annual report for all contracts under project #2010-001-00 including this contract.  Report will then be submitted by the Upper Columbia Salmon Recovery Board (UCSRB) to BPA to fulfill deliverable.  UCSRB will submit and upload report under project 2010-001-00, Upper Columbia Programmatic Habitat.
Account Type(s):
Expense
Contract Start Date:
09/15/2020
Contract End Date:
09/14/2021
Current Contract Value:
$540,238
Expenditures:
$540,238

* Expenditures data includes accruals and are based on data through 30-Nov-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Coop
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Complete environmental compliance permitting processes A: 165. Obtain Required Permits, Authorizations, and Documentation for the Barkley Bear project 09/14/2021 09/14/2021
Construction management complete B: 100. Construction Management Activities 09/14/2021 09/01/2021
Complete specified complexity elements C: 29. Instream and Floodplain Complexity Elements 08/31/2021 09/10/2021
Completed channel construction D: 30. Improve Side Channel and Tributary Connections 08/31/2021 09/10/2021
Remove irrigation infrastructure E: 84. Remove Barkley Irrigation Diversion 08/31/2021 09/10/2021
Remove levee F: 180. Remove Riprap along the Methow River 08/31/2021 08/06/2021
Establish native riparian vegetation (includes assessment and care the season of planting) G: 47. Plant Native Riparian Vegetation 09/14/2021 09/14/2021
Maintain native riparian plantings H: 198. Maintain Native Riparian Plantings 09/14/2021 09/14/2021
Secure all needed actions to ensure timely project implementation I: 191. Watershed Stakeholder Coordination and Outreach 09/14/2021 09/14/2021
Effective implementation management and timely contract administration L: 119. Manage BPA Contracting Requirements 09/14/2021 09/14/2021

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Upper Columbia River Spring ESU (Endangered)
  • 1 instance of WE 198 Maintain Vegetation
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 30 Realign, Connect, and/or Create Channel
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 180 Enhance Floodplain/Remove, Modify, Breach Dike
  • 1 instance of WE 84 Remove/Install Diversion
  • 1 instance of WE 100 Construction Management
Steelhead (O. mykiss) - Upper Columbia River DPS (Threatened)
  • 1 instance of WE 198 Maintain Vegetation
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 30 Realign, Connect, and/or Create Channel
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 180 Enhance Floodplain/Remove, Modify, Breach Dike
  • 1 instance of WE 84 Remove/Install Diversion
  • 1 instance of WE 100 Construction Management

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Obtain Required Permits, Authorizations, and Documentation for the Barkley Bear project
B 100 Construction Management Activities
C 29 Instream and Floodplain Complexity Elements 03/26/2021
D 30 Improve Side Channel and Tributary Connections 03/26/2021
E 84 Remove Barkley Irrigation Diversion 03/26/2021
F 180 Remove Riprap along the Methow River 03/26/2021
G 47 Plant Native Riparian Vegetation 03/26/2021
H 198 Maintain Native Riparian Plantings 03/26/2021
I 191 Watershed Stakeholder Coordination and Outreach
J 132 No Report Required Per COR
K 185 Periodic Status Reports for BPA
L 119 Manage BPA Contracting Requirements