Contract 86096: 1992-026-01 EXP MIDDLE UPPER GRANDE RONDE BOULDER ADDITION
Project Number:
Title:
Grande Ronde Model Watershed
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Blue Mountain Grande Ronde 100.00%
Contract Number:
86096
Contract Title:
1992-026-01 EXP MIDDLE UPPER GRANDE RONDE BOULDER ADDITION
Contract Continuation:
Previous: Next:
n/a
Contract Status:
Closed
Contract Description:
The Middle Upper Grande Ronde River Canyon Fish Habitat Enhancement Project is located in the Upper Grande Ronde Subbasin along the Grande Ronde River between RM 156 and RM 158. The Project reach is located on the Wallowa-Whitman National Forest within the Upper Grande Ronde River Atlas Biological Significant Reach UGR15. The Project area presents a large-scale and significant opportunity to expand, create, and enhance core spawning and rearing habitat for ESA listed spring-summer Chinook salmon and summer steelhead.

The Project is a continuation of habitat restoration actions previously conducted by the US Forest Service (primarily large wood additions). Strategies include: 1) identifying and prioritizing response reaches within project area for improved floodplain connection and side channel habitat creation; 2) Utilizing apex Engineered Log Jams (ELJs) to force split channel flow and increase habitat complexity and diversity, particularly in areas identified under strategy #1; and 3) Installation of channel spanning wood structures to increase depth and pool habitat  and decrease velocity to mimic onsite examples exhibiting these key habitat conditions (e.g, ELJ’s, natural wood, and beaver dams). Proposed large wood additions include previous and existing large wood sites as well as locations with potential for achieving depth, velocity, and floodplain/peripheral habitat connectivity objectives. Additionally, boulders will be placed within ELJs as ballast and structural support. Gravel augmentation and additional large wood installation will be evaluated in conjunction with future project phases (phases II-III) along an 8 mile planning reach.

Phase 1 of the project was constructed during summer 2019.  Due to an issue associated with Section 106 permitting, the project was constructed by helicopter only, limiting sponsors ability to key in structures and install boulder ballast for structural stability as designed using ground based construction equipment.  Following construction in July 2019, project sponsors installed pins and rope selected Type A wood structures to increase and maintain structural stability.  Installation of boulder ballast under this proposal will help increase structural stability contributes towards meeting core project objectives and minimizing the risk of downstream migration of large wood material.

Approximately 270-300 boulders will be placed by helicopter as structural ballast within previously constructed Phase I engineered log jams (ELJ). An average of 5 boulders will be placed within each of the 54 ELJ at strategic locations to decrease the opportunity that logs will become buoyant or shift from original placed location, and increase the structural integrity of the ELJ to withstand river forces during high water spring runoff. Additional details of boulder placement design are included in Uploaded Documents.

Subcontractor(s) will be responsible for transporting boulders to Dry Beaver staging area/ helicopter landing zone, drilling holes through boulders for cable choker attachments, and traffic control along FS 51 road during the week of boulder placement by helicopter.
Account Type(s):
Expense
Contract Start Date:
09/01/2020
Contract End Date:
11/30/2021
Current Contract Value:
$205,260
Expenditures:
$205,260

* Expenditures data includes accruals and are based on data through 31-Oct-2024.

BPA COR:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Grant
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Environmental Compliance completed A: 165. Complete and/or initiate Environmental Permitting for Project Activities 06/30/2021 06/30/2021
Install habitat boulders using helicopter B: 29. Install habitat boulders by helicopter on the MUGRR Project 11/30/2021 10/22/2021
Construction Management Complete C: 100. Provide construction overisght and observation. 11/30/2021 11/30/2021
Effective implementation management and timely contract administration D: 119. Project/Contract Administration 11/30/2021 11/30/2021
Upload Completion E: 132. Middle Upper Grande Ronde Boulder Addition Completion Report 11/30/2021 11/30/2021

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened)
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 100 Construction Management
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 100 Construction Management
Lamprey, Pacific (Entosphenus tridentata)
  • 1 instance of WE 100 Construction Management
Trout, Bull (S. confluentus) (Threatened)
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 100 Construction Management
Trout, Interior Redband (O. mykiss gairdnerii)
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 100 Construction Management

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Complete and/or initiate Environmental Permitting for Project Activities
B 29 Install habitat boulders by helicopter on the MUGRR Project 04/20/2021
C 100 Provide construction overisght and observation.
D 119 Project/Contract Administration
E 132 Middle Upper Grande Ronde Boulder Addition Completion Report
F 185 Quarterly Status Reports