85908: 1992-026-01 EXP FREE WILLOW/LOWER WILLOW CK FISH PASSAGE |
* Expenditures data includes accruals and are based on data through 30-Nov-2024.
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Permitting | A: 165. Environmental Compliance | 07/01/2022 | 09/30/2022 | |
Complete installation of 1 fish ladder at Huber Dam | B: 184. Installation of the Huber fish ladder | 12/30/2022 | 09/30/2022 | |
Re-seed all disturbed areas | C: 47. Post Project seeding | 06/30/2023 | 11/01/2022 | |
Effective implementation management and timely contract administration | D: 119. Project/Contract Administration | 06/30/2023 | 11/01/2022 | |
Upload Willow Creek Fish Passage Huber Dam Completion Report | E: 132. Willow Creek Fish Passage Huber Dam Completion Report | 06/30/2023 | 12/20/2022 |
Primary Focal Species | Work Statement Elements |
---|---|
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened) |
|
Steelhead (O. mykiss) - Snake River DPS (Threatened) |
|
Lamprey, Pacific (Entosphenus tridentata) |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 165 | Environmental Compliance | |||||||
B | 184 | Installation of the Huber fish ladder | 04/11/2022 | ||||||
C | 47 | Post Project seeding | 05/04/2022 | ||||||
D | 119 | Project/Contract Administration | |||||||
E | 132 | Willow Creek Fish Passage Huber Dam Completion Report | |||||||
F | 185 | Quarterly Status Reports |