Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 90768 REL 7: 1992-026-01 EXP BEAR CREEK RM 3.2-5.2 DESIGN
Project Number:
Title:
Grande Ronde Model Watershed
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Blue Mountain Grande Ronde 100.00%
Contract Number:
90768 REL 7
Contract Title:
1992-026-01 EXP BEAR CREEK RM 3.2-5.2 DESIGN
Contract Continuation:
Previous: Next:
n/a
Contract Status:
Issued
Contract Description:
The Bear Creek Restoration Project is a stand alone opportunity that could branch into more work on Bear Creek in Wallowa County, OR. This contract is to hire a design engineering firm to complete designs and all necessary documents/reviews to implement a fully comprehensive floodplain restoration project to address all limiting factors in this reach for all life stages of ESA listed salmonids. This will occur from RM 3.1 and 5.6 of Bear Creek, as well as 2 miles upstream from the confluence of Bear Creek with Little Bear Creek. Bear Creek is a tributary of the Wallowa River identified as WLL2 in the Wallowa Atlas Prioritization Document. This opportunity has been ranked as a Tier 1 or one of the highest priority subwatersheds to restore in the basin.

This reach of Bear Creek is a dynamic system experiencing a large floodpulse each year of water and sediment. Due to anthropogenic effects such as building the road, constructing two bridges, and infrastructure bank protection, Bear Creek is currently at bedrock in several places, straightened and confined thus producing a shotgun of water and sediment. The project reach lacks pools and large wood capable of slowing down the water and trapping sediment suitable for spawning. Wood additions would also increase fish habitat for juvenile rearing, and adult holding. There are many opportunities for floodplain reactivation, which would especially benefit juvenile growth and survival. Downstream from this reach, several irrigation withdrawals tend to produce incredibly low flows in Bear Creek during the summer months, so by reactivating the floodplain and restoring and protecting springs on this property, it is possible to see a significant increase in flow especially during base flow conditions. Riparian vegetation has been suppressed by overgrazing but will most likely thrive once protected.

Besides ODFW, the GRMW, landowners/managers, and the Atlas Implementation Team partners will help guide the design of this project to be successful in restoring process and function to Bear Creek.

Objectives in regard to the restoration actions will be developed and defined through the design process, reviewed and refined at each milestone.  The final objectives will be decided when seeking implementation funding.  Using the known limiting factors on this reach, objectives will continue to be developed to benefit all life stages of ESA listed species and other sensitive species within the project by 2026.

1) Increase floodplain connectivity, duration of inundation, and total wetted area.
2) Improve sediment retention and sorting to increase favorable spawning areas.
3) Increase off-channel habitat.
4) Increase instream complexity.
5) Improve riparian condition and species richness.
6) Improve springs and increase flow into the mainstem of Bear Creek.
Account Type(s):
Expense
Contract Start Date:
08/01/2024
Contract End Date:
12/31/2025
Current Contract Value:
$150,000
Expenditures:
$30,193

* Expenditures data includes accruals and are based on data through 30-Nov-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Coop
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Lindsey Arotin Bonneville Power Administration Yes Env. Compliance Lead ldarotin@bpa.gov (503) 230-4039
Amanda Coffman Grande Ronde Model Watershed Foundation No Interested Party amanda@grmw.org (541) 663-0570
Mary Estes Grande Ronde Model Watershed Foundation No Administrative Contact mary@grmw.org (541) 663-0570
Tracy Hauser Bonneville Power Administration Yes COR tlhauser@bpa.gov (503) 230-4296
Winston Morton Oregon Department of Fish and Wildlife Yes Supervisor winston.h.morton@odfw.oregon.gov (541) 962-1837
Jessica Power Bonneville Power Administration No CO Assistant jdpower@bpa.gov (503) 230-4023
Nicholas Smith Oregon Department of Fish and Wildlife Yes Contract Manager Nicholas.p.smith@odfw.oregon.gov (541) 805-5820
Jesse Steele Grande Ronde Model Watershed Foundation No Interested Party jesse@grmw.org (541) 663-0570
Connar Stone Grande Ronde Model Watershed Foundation No Interested Party connar@grmw.org (541) 663-0570
Katherine Tipton Bonneville Power Administration No Technical Contact kltipton@bpa.gov (503) 230-5708
Alexandra Towne Grande Ronde Model Watershed Foundation No Interested Party alex@grmw.org (541) 663-0570
Sean Welch Bonneville Power Administration Yes F&W Approver spwelch@bpa.gov (503) 230-7691
Karen Wolfe Bonneville Power Administration Yes Contracting Officer ktwolfe@bpa.gov (503) 230-3448
Jeff Yanke Oregon Department of Fish and Wildlife No Interested Party jeff.YANKE@odfw.oregon.gov (541) 962-5162


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
EC in progress associated with 80% design. A: 165. Environmental Compliance for Bear Creek design 12/31/2025
Final design, specifications, and bid package for Bear Creek B: 175. Produce Implementation Ready Designs for the Bear Creek project in Wallowa County, OR. 12/31/2025
Effective implementation management and timely contract administration C: 119. Oversight of Design Contractor 12/31/2025

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened)
  • 1 instance of WE 175 Produce Design
Coho (O. kisutch) - Unspecified Population
  • 1 instance of WE 175 Produce Design
Sockeye (O. nerka) - Other
  • 1 instance of WE 175 Produce Design
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 1 instance of WE 175 Produce Design

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Environmental Compliance for Bear Creek design
B 175 Produce Implementation Ready Designs for the Bear Creek project in Wallowa County, OR. 05/30/2024
C 119 Oversight of Design Contractor
D 132 Report - N/A
E 185 Quarterly Status Reports