Province | Subbasin | % |
---|---|---|
Columbia River Estuary | Columbia Estuary | 50.00% |
Elochoman | 5.00% | |
Grays | 5.00% | |
Lower Columbia | Columbia Lower | 30.00% |
Kalama | 5.00% | |
Sandy | 5.00% |
* Expenditures data includes accruals and are based on data through 30-Nov-2024.
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Environmental Compliance Complete | B: 165. Ensure All Environmental Compliance is Complete | 09/30/2024 | 09/30/2024 | |
Effective implementation management and timely contract administration | C: 119. Provide Management and Administration of Projects | 09/30/2024 | 09/30/2024 | |
Completed 2023 Annual Report uploaded to cbfish.org | D: 132. Submit ANNUAL Progress Report for the period Jan 2023 to Dec 2023 | 04/30/2024 | 04/30/2024 | |
Submit 2023 Stewardship Fund Reports | E: 141. Other Reports for BPA | 07/26/2024 | 07/26/2024 | |
Submit LAND MANAGEMENT PLANS to BPA | F: 193. Submit outstanding LAND MANAGEMENT PLANS to BPA | 09/30/2024 | 09/30/2024 | |
Work With Landowners and WWR if approached about potential project | H: 114. Meet with stakeholders when approached with new project | 09/30/2024 | 09/30/2024 | |
Regional Data Sharing/CEERP Coordination Meetings/ERTG Participation | I: 191. Expert Regional Technical Group (ERTG) Participation | 09/30/2024 | 09/30/2024 | |
Submit Final Realty Package for BPA-identified Priority Acquisitions | J: 172. Conduct All Necessary Due Diligence Related to Land Acquisitions | 09/30/2024 | 09/30/2024 | |
COLUMBIA STOCK RANCH-- Vegetation Maintenance | K: 198. COLUMBIA STOCK RANCH -- CWTD RESTORATION -- Maintain Vegetation | 09/30/2024 | 09/30/2024 | |
LOWER ELOCHOMAN 3--Site Preparation for Planting | L: 199. LOWER ELOCHOMAN III -- RESTORATION -- Vegetation Control | 09/30/2024 | 09/30/2024 | |
LOWER ELOCHOMAN 3--Vegetation Established | M: 47. LOWER ELOCHOMAN III -- RESTORATION -- Planting | 09/30/2024 | 09/30/2024 | |
LOWER ELOCHOMAN 3--Plant Maintenance | N: 198. LOWER ELOCHOMAN III -- RESTORATION -- Plant Maintenance | 09/30/2024 | 09/30/2024 | |
RAISTAKKA ROAD--60% Project Design completed | O: 175. RAISTAKKA--DESIGN-- 60% DESIGN | 09/30/2024 | 09/30/2024 | |
RESTORATION DESIGN CHALLENGES-- Reed Canarygrass Study | Q: 157. RESTORATION DESIGN CHALLENGES Project | 09/30/2024 | 09/30/2024 | |
Collect Level 3 AEMR-- PRE-construction--RAISTAKKA ROAD | R: 157. RAISTAKKA FLOODPLAIN - Collect PRE-construction AEMR Level 3 Data | 09/30/2024 | 09/30/2024 | |
Collect Level 3 AEMR data for LE2--Post-construction--Year 5 | S: 157. LOWER ELOCHOMAN II - Collect POST-Construction Year 5 AEMR Level 3 data | 09/30/2024 | 09/30/2024 |
Primary Focal Species | Work Statement Elements |
---|---|
Chinook (Oncorhynchus tshawytscha) - All Populations |
|
Chinook (O. tshawytscha) - Lower Columbia River ESU (Threatened) |
|
Chum (Oncorhynchus keta) - Columbia River ESU (Threatened) |
|
Coho (Oncorhynchus kisutch) - Lower Columbia River ESU (Threatened) |
|
Coho (O. kisutch) - Unspecified Population |
|
Steelhead (Oncorhynchus mykiss) - All Populations |
|
Steelhead (O. mykiss) - Lower Columbia River DPS (Threatened) |
|
Wildlife |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 185 | Periodic Status Reports for BPA | |||||||
B | 165 | Ensure All Environmental Compliance is Complete | |||||||
C | 119 | Provide Management and Administration of Projects | |||||||
D | 132 | Submit ANNUAL Progress Report for the period Jan 2023 to Dec 2023 | |||||||
E | 141 | Other Reports for BPA | |||||||
F | 193 | Submit outstanding LAND MANAGEMENT PLANS to BPA | |||||||
G | 132 | Submit Data for LCEP 2023 RME Report | |||||||
H | 114 | Meet with stakeholders when approached with new project | |||||||
I | 191 | Expert Regional Technical Group (ERTG) Participation | |||||||
J | 172 | Conduct All Necessary Due Diligence Related to Land Acquisitions | |||||||
K | 198 | COLUMBIA STOCK RANCH -- CWTD RESTORATION -- Maintain Vegetation | 05/16/2024 | ||||||
L | 199 | LOWER ELOCHOMAN III -- RESTORATION -- Vegetation Control | 05/16/2024 | ||||||
M | 47 | LOWER ELOCHOMAN III -- RESTORATION -- Planting | 05/16/2024 | ||||||
N | 198 | LOWER ELOCHOMAN III -- RESTORATION -- Plant Maintenance | 05/16/2024 | ||||||
O | 175 | RAISTAKKA--DESIGN-- 60% DESIGN | 07/19/2023 | ||||||
P | 27 | *CANCELED---RAISTAKKA--RESTORATION--Structure Removal | 08/24/2023 | ||||||
Q | 157 | RESTORATION DESIGN CHALLENGES Project | 07/19/2023 | ||||||
R | 157 | RAISTAKKA FLOODPLAIN - Collect PRE-construction AEMR Level 3 Data | 07/19/2023 | ||||||
S | 157 | LOWER ELOCHOMAN II - Collect POST-Construction Year 5 AEMR Level 3 data | 07/19/2023 |